DC Water's

News & Updates

At DC Water, we understand the importance of keeping our community informed about our services, projects, and achievements. Our news web page serves as a reliable source for the latest information on a range of topics.

Photo of PI ready for return of flow
13 March, 2026
  • DC Water has completed final site preparations to return the flow to the Potomac Interceptor, marking and important milestone after 33 consecutive days without an overflow to the Potomac River.
  • The geopolymer – used to seal and waterproof the trench boxes around the open pipe sections – finished curing today. This will allow the flow to safely be returned to the interceptor itself, allowing the ...
Collapse site with equipment idle due to weather conditions
12 March, 2026
  • Environmental Rehabilitation and Emergency Repair work on the Potomac Interceptor sewer line was slowed by rain and snow, as we enter day 33 without an overflow into the Potomac River.
  • When there are measurable rain and snow, crews are unable to do environmental rehabilitation work due to the risk of spreading contamination. In addition, geopolymer being used to waterproof the trench boxes around ...
Photo of workers doing environmental rehab in west section of Area 1
11 March, 2026

With 32 days of no overflows reaching the Potomac River, DC Water and its contractor continue to make progress on the Environmental Rehabilitation of the areas impacted by the failure in the Potomac Interceptor. Meanwhile work is nearing completion in the coming days on the emergency repair and is expected to meet the mid-March target.

photo of worker going into downstream cleaning pit
10 March, 2026
  • Work is progressing to meet the mid-March target to return the flow to the Potomac Interceptor, as we reach 31 days with no overflows reaching the Potomac River.
  • The geopolymer applied to the upstream and downstream sections of the pipe has cured to reinforce the pipe and ensure structural integrity. This completes the repair on the pipe, which is now ready for the flow to return.
  • Additional work is ...
Workers putting down rye and matting for soil stabilization
9 March, 2026
  • More than one month after the last overflow into the Potomac River, DC Water is preparing to return flow in the coming days to the Potomac Interceptor and meet the mid-March target to complete the emergency repair on the damaged pipe section.
  • Crews have completed work to reinforce the pipe sections upstream and downstream of the collapse site using geopolymer to strengthen the pipe. The work ...
Tree and debris removal for environmental rehabilitation
8 March, 2026

Work is nearly complete on the downstream section of the Potomac Interceptor to reinforce the pipeline with geopolymer. The concrete-like material will strengthen and restore the structural integrity of the pipe. Completion of the geopolymer lining downstream is one of the final steps to restore flow to the interceptor and finish the emergency repair.

This comes one month since the last overflow ...

geopolymer downstream
7 March, 2026

As emergency repairs continue, today marks 27 days, nearly one month, with no overflow reaching the Potomac River.

Crews are making significant progress to reinforce the downstream section of pipe from the collapse site and completed 240 linear feet of geopolymer overnight. Crews are working to apply another layer of geopolymer today. The material is similar in strength to concrete and when ...

photo inside tunnel with geopolymer
6 March, 2026

Reinforcement of the upstream section of the Potomac Interceptor has been completed, marking the halfway point in emergency repairs following the January 19 sewer line collapse. Crews continue to advance repairs on schedule, with full project completion expected by mid-March.

John Cassidy, Matt Brown, David L. Gadis, and Moussa Wone giving technical briefing
5 March, 2026

DC Water today is releasing a comprehensive assessment detailing the condition of the Potomac Interceptor and our emergency response to the January 19 sanitary sewer line failure. This report provides clarity for customers, stakeholders, and community members about the steps taken and findings from the incident, including prior inspections of the pipe’s condition.

After the collapse, DC Water’s ...

Geopolymer lining inside the Potomac Interceptor
4 March, 2026

DC Water and its contractor have taken significant steps toward repairing the Potomac Interceptor. The repair process currently underway involves reinforcing the damaged section of the pipe using geopolymer. This material is known for its concrete-like strength and durability.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of temporarily relocated section of Piney Branch Parkway
Piney Branch Parkway Section to Reopen Monday, Restoring a Key Route for DC Commuters

Following a 27-day closure, DC Water will reopen a section of Piney Branch Parkway between Arkansas Avenue and Beach Drive NW early Monday morning, restoring an important cross-town connection for thousands of District commuters. During the closure, a section of the road was temporarily relocated for construction of DC Water’s Piney Branch Tunnel Project.

Latest Blog Post
DC Water General Manager and CEO David Gadis recognizes Lily MacDonald during the May Board of Directors meeting.
From Classroom to Community: A Student Spotlight on DC Water's SPLASH Program
A speechwriting assignment became a call to action for water access and affordability through DC Water's SPLASH program.
Upcoming Meeting
Date
June 25, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.