UPDATE: Potomac Interceptor Repair, February 21

February 21, 2026
workers inside pipe cleaned of rocks and debris

Potomac Interceptor Repair Update
February 21, 2026

  • For nearly two weeks, no overflows have entered the Potomac River. The last release to the river occurred on February 8.
  • Crews are continuing to remove debris and large rocks from inside the damaged pipe section.
  • An initial assessment of the damaged pipe section determined the remaining intact structure downstream, which is blocked by an extensive rock dam, is structurally compromised and unsafe for crews to continue work inside the pipe.
  • Alternate measures are being developed to extend the excavation around the damaged section, stabilize the area, and remove portions of the pipe to remove the rock dam for repairs to begin.
  • Crews continue working around the clock to ensure continued bypass pumping operations, and ongoing cleaning efforts downstream of the collapse site.
  • Preparations are underway for forecasted rain and snow event, which could increase flow and create difficult conditions for equipment and crews.
  • Coordination continues with the National Park Service, U.S. Environmental Protection Agency, and Maryland Department of the Environment on an Environmental Restoration Plan.

Protecting public health and the Potomac River remains DC Water’s top priority. Updates will be provided as work continues.

Water Quality Sampling Results

DC Water is performing daily water quality sampling. It’s important to note that historically the E. coli levels in the Potomac and Anacostia rivers vary widely from day to day. Fluctuations in water quality are influenced by factors such as weather events, river flow, runoff, pollutants, and other sources discharging into waterways; and measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day.

A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs

DC Water has added two new sampling locations to the daily sampling.  These locations add data points closer to the overflow site. The Minnie’s Island sample locations are approximately 0.54 miles from the overflow site compared to the Fletcher's location which is 5.2 miles from the overflow site. These sample locations provide a better understanding of the impact in the river near the collapse site and allow us to compare the main stem of the Potomac River (south side sample) to the inlet areas along the shoreline around Minnie’s Island (north side sample) where the water flows more slowly.

*Lab results are unavailable on weekends and will be provided the following Monday (excluding holidays).

graphic of sampling results

For more information about the ongoing repair efforts go to dcwater.com/Potomac-interceptor-collapse.

 

 

Latest News

A section of the canal where the soil has been removed
  • Crews are close to completing the removal of remaining soil from Locks 11 to 13 in the section of the C&O Canal that was used as an emergency bypass after the collapse of the Potomac Interceptor sewer ...
Excavation site outside the I-495 Beltway showing section of the PI

Crews completed cleaning on Lock 11 of the C & O Canal as prescribed by the National Park Service, with soil removal also nearing completion within the lock area. Tree removal is also underway, after DC Water received the permits to move forward as part of the site preparations for the long-term accelerated rehabilitation of more than 2700 linear feet of the Potomac Interceptor sewer line that had been previously planned.

Photo of long stretch of C & O Canal with soil removed

DC Water has excavated a section of the Potomac Interceptor along Clara Barton Parkway, outside the I-495 Beltway as part of the accelerated rehabilitation of more than 2700 linear feet of the interceptor that was previously planned. As part of the long-term rehabilitation project, crews are beginning to remove trees which is necessary to construct a bypass chamber that will divert wastewater around sections of the pipe while they are being rehabilitated.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

The shields for the tunnel boring machine Mary being lowered by cranes into the shaft
DC Water Earns Prominent Award for Sustainable Finance Leadership through Green Bonds

Recognition highlights DC Water’s commitment to environmental stewardship during Earth Month

DC Water has been honored with the “Green Bond of the Year – US Muni Bond” Award by Environmental Finance, a leading industry publication. This achievement celebrates DC Water’s leadership in sustainability and its dedication to responsible municipal financing.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
May 5, 2026
Tuesday, 1:00 PM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.