Final Steps Complete, Preparations Underway for Returning Flow to the Potomac Interceptor

March 13, 2026
Photo of PI ready for return of flow
  • DC Water has completed final site preparations to return the flow to the Potomac Interceptor, marking and important milestone after 33 consecutive days without an overflow to the Potomac River.
  • The geopolymer – used to seal and waterproof the trench boxes around the open pipe sections – finished curing today. This will allow the flow to safely be returned to the interceptor itself, allowing the bypass pumping system and use of the C & O Canal to be deactivated.
  • Testing is expected to begin this weekend to confirm the flow can safely be restored to the interceptor. Once confirmed, DC Water and its contractors will remove the steel bulkhead gate blocking flow in the pipe and shut down the bypass pumps that have been diverting the flow into the C & O Canal, around the collapse site, and back into the sewer system further downstream.
  • After flow is restored, the trench boxes and pipe sections where the crown has been removed will remain open to facilitate the previously planned rehabilitation of this section of the interceptor.
  • Crews will monitor the flow for 48-hours, keeping pumps on standby, before beginning to demobilize the site.
  • Work will then transition to the long-term rehabilitation of more than 2,700 linear feet of the pipe. This phase of the project is being accelerated, and efforts will soon begin to build out the mechanical system that will push new pipe sections into place using the existing open areas. The process called slip lining – will strengthen and reinforce the pipe to like-new condition.
  • Although the emergency repairs are nearing completion, activity at the site continues to rehabilitate the surrounding environment. DC Water, working with the U.S. Army Corps of Engineers and the Environmental Protection Agency, continue to clear brush and debris, remove impacted soils, and provide temporary erosion and sediment control and soil stabilization measures.
  • Once flow is returned to the interceptor, DC Water teams will also begin the environmental rehabilitation of the C & O Canal.

The initial clean-up of the canal will involve flushing the canal with freshwater from the Potomac River coming in at Violet’s Lock and flowing downstream.  The flushed water and sludge from the cleaning operation will be routed into to the Potomac Interceptor using the existing bypass channels downstream.

 

Water Quality Sampling Results

Fluctuations in water quality are influenced by factors such as rain, heat, or other weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways. This is reflected in the sampling results for March 12, which coincides with heavy rain and stormwater runoff. Given these variables, measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs.

Sample results from March 2 - present. Past results may be found here.

graphic of water quality sampling

Latest News

A section of the canal where the soil has been removed
  • Crews are close to completing the removal of remaining soil from Locks 11 to 13 in the section of the C&O Canal that was used as an emergency bypass after the collapse of the Potomac Interceptor sewer ...
Excavation site outside the I-495 Beltway showing section of the PI

Crews completed cleaning on Lock 11 of the C & O Canal as prescribed by the National Park Service, with soil removal also nearing completion within the lock area. Tree removal is also underway, after DC Water received the permits to move forward as part of the site preparations for the long-term accelerated rehabilitation of more than 2700 linear feet of the Potomac Interceptor sewer line that had been previously planned.

Photo of long stretch of C & O Canal with soil removed

DC Water has excavated a section of the Potomac Interceptor along Clara Barton Parkway, outside the I-495 Beltway as part of the accelerated rehabilitation of more than 2700 linear feet of the interceptor that was previously planned. As part of the long-term rehabilitation project, crews are beginning to remove trees which is necessary to construct a bypass chamber that will divert wastewater around sections of the pipe while they are being rehabilitated.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

The shields for the tunnel boring machine Mary being lowered by cranes into the shaft
DC Water Earns Prominent Award for Sustainable Finance Leadership through Green Bonds

Recognition highlights DC Water’s commitment to environmental stewardship during Earth Month

DC Water has been honored with the “Green Bond of the Year – US Muni Bond” Award by Environmental Finance, a leading industry publication. This achievement celebrates DC Water’s leadership in sustainability and its dedication to responsible municipal financing.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
May 5, 2026
Tuesday, 1:00 PM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.