Final Steps Complete, Preparations Underway for Returning Flow to the Potomac Interceptor

March 13, 2026
Photo of PI ready for return of flow
  • DC Water has completed final site preparations to return the flow to the Potomac Interceptor, marking and important milestone after 33 consecutive days without an overflow to the Potomac River.
  • The geopolymer – used to seal and waterproof the trench boxes around the open pipe sections – finished curing today. This will allow the flow to safely be returned to the interceptor itself, allowing the bypass pumping system and use of the C & O Canal to be deactivated.
  • Testing is expected to begin this weekend to confirm the flow can safely be restored to the interceptor. Once confirmed, DC Water and its contractors will remove the steel bulkhead gate blocking flow in the pipe and shut down the bypass pumps that have been diverting the flow into the C & O Canal, around the collapse site, and back into the sewer system further downstream.
  • After flow is restored, the trench boxes and pipe sections where the crown has been removed will remain open to facilitate the previously planned rehabilitation of this section of the interceptor.
  • Crews will monitor the flow for 48-hours, keeping pumps on standby, before beginning to demobilize the site.
  • Work will then transition to the long-term rehabilitation of more than 2,700 linear feet of the pipe. This phase of the project is being accelerated, and efforts will soon begin to build out the mechanical system that will push new pipe sections into place using the existing open areas. The process called slip lining – will strengthen and reinforce the pipe to like-new condition.
  • Although the emergency repairs are nearing completion, activity at the site continues to rehabilitate the surrounding environment. DC Water, working with the U.S. Army Corps of Engineers and the Environmental Protection Agency, continue to clear brush and debris, remove impacted soils, and provide temporary erosion and sediment control and soil stabilization measures.
  • Once flow is returned to the interceptor, DC Water teams will also begin the environmental rehabilitation of the C & O Canal.

The initial clean-up of the canal will involve flushing the canal with freshwater from the Potomac River coming in at Violet’s Lock and flowing downstream.  The flushed water and sludge from the cleaning operation will be routed into to the Potomac Interceptor using the existing bypass channels downstream.

 

Water Quality Sampling Results

Fluctuations in water quality are influenced by factors such as rain, heat, or other weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways. This is reflected in the sampling results for March 12, which coincides with heavy rain and stormwater runoff. Given these variables, measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs.

Sample results from March 2 - present. Past results may be found here.

graphic of water quality sampling

Latest News

Excavators in the canal digging up soil and another excavator removing the soil to a dump truck to be hauled away

DC Water and its contractor have made significant progress on soil removal, reaching the clay liner between locks 13 and 14 of the C & O Canal, which was used as a bypass for wastewater during the Potomac Interceptor repairs.

Work continues to remove sludge between locks 10 and 13, which is expected to be completed by mid- to late-April. The soil will then be removed down to the clay liner as the final step, and the canal reconstructed to meet National Park Service specifications.

Soil Removal Underway with Excavator in Canal

Today, DC Water and its contractors began removing contaminated soil between locks 13 and 14 in the C & O Canal, which was used as a temporary bypass during the Potomac Interceptor repair effort. Clean-up efforts are ongoing at Lock 10 with work to remove sludge now getting underway between locks 11 and 13.

Aerial shot of Blue Plains Advanced Wastewater Treatement Plant

Series 2026 Bond Transaction Delivers Significant Long-Term Cost Savings

DC Water has closed on a refinancing deal for its Series 2026 bonds that will save customers millions of dollars and keep rates affordable across the District. The refinancing transaction, which closed this month, delivers approximately $54 million in budget savings over the next twenty years, directly benefiting DC ratepayers through reduced costs.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Map of lane closure
Traffic Advisory: Rock Creek and Potomac Parkway NW Lane Closure Beginning Jan 19

Beginning on or about January 19, 2026, weather permitting, DC Water will implement a temporary lane closure on Rock Creek and Potomac Parkway NW b

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
April 7, 2026
Tuesday, 9:30 AM

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.