DC Water Provides Next Steps in Environmental Remediation and Water Quality Monitoring in Potomac River

May 08, 2026
Photo of Potomac River at the overflow location

DC Water has outlined its next steps to complete the environmental cleanup and its plan for continued water quality monitoring this summer, as part of the ongoing response to January’s failure in the Potomac Interceptor sewer pipeline. The plan, submitted to the Maryland Department of the Environment (MDE), is supported by extensive data from hundreds of samples that indicate bacteria levels since at least mid-March have been back to normal.

Under the proposal, further confirmation of water quality testing will continue daily through July 5 at the ten existing sampling sites and then transition to weekly testing through September 10. While there is no technical basis to continue the monitoring, DC Water will do so during the remaining summer months to reinforce for the public that river bacteria levels are back to normal.

In addition, the first phase of comprehensive environmental restoration efforts is expected to be substantially completed by late summer 2026. The ongoing work is focused on removing the remaining affected soil in the C & O Canal which was successfully used as a bypass for up to two billion gallons of wastewater during the repair period.

“We understand just how important transparency is for our customers and the community, and ensuring our decisions are guided by science,” said Matthew T. Brown, Chief Operating Officer at DC Water. “After analyzing hundreds of our own samples along with extensive sampling by others, it is clear that Potomac River water quality is back to how it was before the incident.”

To supplement the daily water quality sampling at ten sites, the team conducted intensive weekend sampling at high public use areas, ensuring coverage of key recreational sites. The results all confirm bacteria levels consistently within the typical range for recreational use with normal historical fluctuations driven by rainfall, temperature, stormwater runoff, and other factors.

A nutrient load analysis conducted by the Virginia Department of Environmental Quality determined that the nutrient load resulting from the overflow accounted for less than 0.5% of the annual nutrient input to the Potomac River. Additionally, the Interstate Commission on the Potomac River Basin (ICPRB) reported the affected flow – given the Potomac’s natural flushing capacity - has long since passed and is no longer present in the river, reinforcing the overall findings that conditions have returned to normal.

In coordination with the U.S. Army Corps of Engineers, the Environmental Protection Agency, and the National Park Service, the initial clean-up and reseeding have been completed in the areas directly impacted by the overflow, along the drainage channel, culvert, and tributary to the river.

The second phase of restoration is expected to be completed in the fall. This includes a comprehensive plan to replant native herbaceous species, shrubs, and trees, regrading temporarily impacted wetlands, and restoration of natural hydrology. Crews will also repair the C & O Canal’s clay liner, add topsoil for the base and sides, and restore structural features.

The public is encouraged to provide feedback on the plan during a community meeting hosted by MDE on May 18, at 7 p.m. at the Glen Echo Town Hall. DC Water representatives will be available to answer questions and provide additional details about the extensive river sampling results, the ongoing restoration activities, and the plan to complete the restoration of affected areas. Register here to attend.

For details on the remediation and restoration efforts, view the Potomac Interceptor Emergency Repair and Rehabilitation Plan.

As site conditions continue to improve and environmental restoration nears completion, DC Water will conclude routine public update communications. Up-to-date water quality sampling results will continue to be available on our dedicated webpage for the Potomac Interceptor Response and updates will continue to be provided to the public regarding major project milestones and important developments.

Latest News

Photo of Potomac River at the overflow location

Hundreds of Sampling Results Confirm Return to Normal Bacteria Levels in Potomac River

DC Water has outlined its next steps to complete the environmental cleanup and its plan for continued water quality monitoring this summer, as part of the ongoing response to January’s failure in the Potomac Interceptor sewer pipeline. The plan, submitted to the Maryland Department of the Environment (MDE), is supported by extensive data from hundreds of samples.

crews removing soil in C & O Canal

Work continues to remove the remaining soil between locks 10 and 12 of the C & O Canal which was used as an emergency bypass while the Potomac Interceptor was repaired. Crews area also removing plants, trees, and shrubs in preparation for the long-term rehabilitation of the Potomac Interceptor.

The Capital Crescent Trail will shift north and remain open to pedestrians and cyclists.

DC Water will initiate the next phase of construction at the Capital Crescent Trail site near the Aqueduct by opening a temporary trail around the work zone. The new trail will open on or about May 6 ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Placeholder DC Water Image
Piney Branch Parkway Temporary Closure and Relocation

DC Water has nearly completed construction site preparation for the Piney Branch Tunnel project, including tree removal, and installation of fences

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

May 16
2:00 pm - 6:00 pm
May 20

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.