UPDATE: Excavation Site Extended Around Damaged Section of Potomac Interceptor to Access Rock Blockage

February 23, 2026
Photo of extended excavation site with trench boxes

Potomac Interceptor Repairs Update
February 23, 2026
 

  • The excavation around the damaged section of pipe has been extended and trench boxes installed to provide shoring and stability. This doubles the size of the excavated area, to connect the collapse site with a downstream access point to the Potomac Interceptor.
  • The newly excavated section will allow crews to reach an area of the pipe believed to be blocked by large rocks and debris. The section, adjacent to the collapse site, is too compromised for crews to safely complete this work from inside the pipe. Instead, crews plan to remove the crown of the pipe section to access the rocks and debris for removal.
  • On-site coordination continues with U.S. Army Corps of Engineers (USACE) to assist with stormwater management to protect pumping operations.
  • Cleaning efforts continue to remove muck and debris upstream from the damaged section and downstream portions. 
  • Development of the Environmental Restoration Plan is ongoing in coordination with Environmental Protection Agency (EPA), National Park Service, Maryland Department of the Environment, USACE, and the District Department of Energy and Environment with some preliminary mediation efforts underway.
  • DC Water is partnering with USACE and EPA to divert runoff away from the contaminated land and install “catchment basins” below street drains and in the creek to capture runoff that may carry residual wastewater contaminants to the Potomac River. 

Water Quality Sampling Results

DC Water is performing daily water quality sampling. It’s important to note that historically the E. coli levels in the Potomac and Anacostia rivers vary widely from day to day. This is reflected in recent sampling results. Fluctuations in water quality are influenced by factors such as weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways. Given these variables, measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day.A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs

Below are the results of sampling from the one-week period of February 16-22, 2026. Past results may be found on our dedicated Potomac Interceptor Response page.

Graphic with water quality results

For more information about the ongoing repair efforts go to dcwater.com/Potomac-interceptor-collapse.

Latest News

Workers doing ongoing rehabilitation work

As work nears completion on the initial clean-up and temporary stabilization of the areas directly impacted by the Potomac Interceptor overflows, DC Water is beginning preparations for beautification and revegetation to restore native plants, trees, and shrubs.

Before moving to the next phase of environmental rehabilitation, DC Water is working with the Environmental Protection Agency to conduct soil sampling to verify the clean-up efforts.

Photo of someone using the tap water with the dates of the annual water line cleaning March 23 - May 4

Spring cleaning isn’t just for closets and cabinets. DC Water’s system gets a refresh too!

Starting March 23, DC Water will begin work that helps maintain more than 1,300 miles of water lines across the District. During this time, the disinfectant used in drinking water will temporarily switch from chloramine to chlorine through May 4. This switch helps support overall water quality throughout the year.

photos of workers with hoses vacuuming out canal

Work is ongoing to complete the initial phase of environmental rehabilitation and temporary stabilization this week in areas directly impacted by the overflows. A small section of the drainage channel along Clara Barton Parkway remains. Preliminary clean-up of the culvert, tributary, and Potomac River shoreline has also been completed.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.