DC Water's

News & Updates

At DC Water, we understand the importance of keeping our community informed about our services, projects, and achievements. Our news web page serves as a reliable source for the latest information on a range of topics.

geopolymer downstream
7 March, 2026

As emergency repairs continue, today marks 27 days, nearly one month, with no overflow reaching the Potomac River.

Crews are making significant progress to reinforce the downstream section of pipe from the collapse site and completed 240 linear feet of geopolymer overnight. Crews are working to apply another layer of geopolymer today. The material is similar in strength to concrete and when ...

photo inside tunnel with geopolymer
6 March, 2026

Reinforcement of the upstream section of the Potomac Interceptor has been completed, marking the halfway point in emergency repairs following the January 19 sewer line collapse. Crews continue to advance repairs on schedule, with full project completion expected by mid-March.

John Cassidy, Matt Brown, David L. Gadis, and Moussa Wone giving technical briefing
5 March, 2026

DC Water today is releasing a comprehensive assessment detailing the condition of the Potomac Interceptor and our emergency response to the January 19 sanitary sewer line failure. This report provides clarity for customers, stakeholders, and community members about the steps taken and findings from the incident, including prior inspections of the pipe’s condition.

After the collapse, DC Water’s ...

Geopolymer lining inside the Potomac Interceptor
4 March, 2026

DC Water and its contractor have taken significant steps toward repairing the Potomac Interceptor. The repair process currently underway involves reinforcing the damaged section of the pipe using geopolymer. This material is known for its concrete-like strength and durability.

Protective Encasement for workers to apply the geopolymer lining
3 March, 2026

Repair efforts continue as we reach 23 days in which no overflows have entered the Potomac River. Crews finished pressure washing the pipe upstream of the damaged section of the Potomac Interceptor and preparations are underway for the application of the geopolymer lining to reinforce and strengthen the pipe.

Workers clearing brush and debris from drainage channel
2 March, 2026

National Park Service Issues Special Use Permit to Move Forward with Restoration Plan

DC Water has begun the rehabilitation and environmental restoration to address areas affected by the sewer overflow from a section of the Potomac Interceptor that collapsed January 19. Contaminated material is being hauled away and work is underway to clear trees, brush, and contaminated debris in and around ...

contract for construction of the Potomac River Tunnel (PRT)
1 March, 2026

Potomac Interceptor Repairs Update 
March 1, 2026

  • Today marks a milestone, as we reach the three-week point with no overflows entering the Potomac River. The last release to reach the river occurred on February 8.
  • On February 28, National Park Service (NPS) issued a Special Use Permit for the repair, rehabilitation, and environmental restoration of the Potomac Interceptor and the C&O Canal National ...
contract for construction of the Potomac River Tunnel (PRT)
28 February, 2026

Potomac Interceptor Repairs Update
February 28, 2026

  • The bypass pumping system continues to divert wastewater around the collapse site and back into the Potomac Interceptor, preventing any overflows from reaching the Potomac River in nearly three weeks. The last time an overflow reached the river was 20 days ago, February 8.
  • Crews continue to clean the pipe and progress is being made to remove the ...
contract for construction of the Potomac River Tunnel (PRT)
27 February, 2026

DC Water will be performing repairs to the Rock Creek Main Interceptor (RCMI) within the West End and Georgetown Neighborhoods. This will require temporary lane closures beginning tonight, February 27, at 8 PM through Monday, March 2, at 5 AM.

Photo of workers doing environmental rehab site preps
27 February, 2026

No overflows reaching the Potomac River for 19 days. The last release to enter the river occurred on February 8. Crews were able to reach some of the additional large rocks downstream of the collapsed section and remove them without additional excavation. Cleaning continues in the area upstream of the damaged section of the Potomac Interceptor to remove muck, debris, and smaller rocks.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Placeholder DC Water Image
Piney Branch Parkway Temporary Closure and Relocation

DC Water has nearly completed construction site preparation for the Piney Branch Tunnel project, including tree removal, and installation of fences

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

May 16
2:00 pm - 6:00 pm
May 20

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.