EMERGENCY WATER OUTAGE
Dec 17, 2025 | 06:18 PM

EMERGENCY WATER OUTAGE
Dec 17, 2025 | 05:52 PM

EMERGENCY WATER OUTAGE
Dec 17, 2025 | 02:00 PM

Now Flowing. Key Connection to New Rehabilitated Section of Potomac Interceptor Completed

October 03, 2025
Image of new pipe section with wastewater flowing
Major Milestone in Sewer Line Repair Near Great Falls

DC Water crews pumped out the last of the wastewater from the bypass system, then carefully lifted the two-ton steel gate that had sealed off the newly rehabilitated section of the Potomac Interceptor Sewer Line. With the gate raised, wastewater from Virginia surged into the new 54-inch sanitary sewer line, joining flow from Maryland and connecting both to the upgraded infrastructure for the first time.

This final connection near Great Falls signals the new pipe section is now fully operational— renewing a critical part of the region’s sewer system. This achievement represents a significant step in completing this complex and critical infrastructure project, which began in 2022 and faced a setback last year when a part of the original pipe collapsed during construction.

The Potomac Interceptor is a massive sanitary sewer system capable of carrying nearly 100 million gallons of wastewater daily from communities in Virginia and Maryland to DC Water’s Blue Plains Advanced Wastewater Treatment Plant. Rehabilitating key sections of the 54-mile-long sewer line is a high priority project, within DC Water’s Capital Improvement Program to upgrade aging infrastructure.

The newly rehabilitated section of the Potomac Interceptor also incorporated a Vortex Flow Insert (VFI) into the design to improve air quality and reduce long-term maintenance costs. The specialized device spins wastewater in a spiral design, aerating the wastewater to help reduce odor and corrosion.

Picture of vortex

While the final connection has been made, the project will continue through the end of the year to complete some remaining work, including:

  • Connect the new pipe to the existing odor control facility
  • Fill and seal the old pipe with concrete
  • Install manhole risers and a cover over the vortex
  • Backfill the excavation site
  • Restore the Potomac Heritage Trail and surrounding natural environment

*Revegetation is not expected until spring 2026, once weather conditions are more favorable.

The upgraded infrastructure reduces the risk of future failures, minimizes odors, and improves environmental conditions near residential areas and public spaces. By modernizing this critical pipeline, DC Water is also helping to safeguard public health, support regional growth, and ensure that wastewater is safely and efficiently transported for treatment. These improvements will also deliver long-term cost savings by improving reliability and reducing the need for emergency repairs and frequent maintenance.

DC Water continues to work closely with local partners, including NOVA Parks and Fairfax County, to ensure transparency and community engagement as this project moves toward completion.

For more information and project updates visit the Potomac Interceptor Project page at dcwater.com/potomacinterceptor.

Latest News

Worker on side of steep slope

TRAFFIC ADVISORY - CLEAN RIVERS - POTOMAC RIVER TUNNEL PROJECT

DC Water is in the final stretch of its slope stabilization project along Canal Road NW, a critical project that will pave the way for Potomac River Tunnel construction at this site. Beginning, the week of December 15, 2025, one westbound lane of Canal Road will be closed during daytime, off-peak hours on weekdays and Saturdays to hydroseed the slope.

Image of Wendy with EPA Letter

DC Water is reaching out to nearly 25,000 customers this month with important information about the material of their water service lines. These annual notifications are part of DC Water’s ongoing commitment to prevent exposure to lead and remove lead service lines from the District’s drinking water system through the Lead Free DC initiative.

Placeholder DC Water Image

Following the completion of priority valve repairs, DC Water will be doing road restoration work along New York Ave and Bladensburg Rd NE this weekend. The work will require lane closures for the duration of the weekend, reduce capacity, and may cause a significant impact to traffic.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Worker on side of steep slope
Canal Road Slope Stabilization Project Nears End; Off-peak Lane Closure to Replant Slope

TRAFFIC ADVISORY - CLEAN RIVERS - POTOMAC RIVER TUNNEL PROJECT

DC Water is in the final stretch of its slope stabilization project along Canal Road NW, a critical project that will pave the way for Potomac River Tunnel construction at this site. Beginning, the week of December 15, 2025, one westbound lane of Canal Road will be closed during daytime, off-peak hours on weekdays and Saturdays to hydroseed the slope.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
December 18, 2025
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.