Now Flowing. Key Connection to New Rehabilitated Section of Potomac Interceptor Completed

October 03, 2025
Image of new pipe section with wastewater flowing
Major Milestone in Sewer Line Repair Near Great Falls

DC Water crews pumped out the last of the wastewater from the bypass system, then carefully lifted the two-ton steel gate that had sealed off the newly rehabilitated section of the Potomac Interceptor Sewer Line. With the gate raised, wastewater from Virginia surged into the new 54-inch sanitary sewer line, joining flow from Maryland and connecting both to the upgraded infrastructure for the first time.

This final connection near Great Falls signals the new pipe section is now fully operational— renewing a critical part of the region’s sewer system. This achievement represents a significant step in completing this complex and critical infrastructure project, which began in 2022 and faced a setback last year when a part of the original pipe collapsed during construction.

The Potomac Interceptor is a massive sanitary sewer system capable of carrying nearly 100 million gallons of wastewater daily from communities in Virginia and Maryland to DC Water’s Blue Plains Advanced Wastewater Treatment Plant. Rehabilitating key sections of the 54-mile-long sewer line is a high priority project, within DC Water’s Capital Improvement Program to upgrade aging infrastructure.

The newly rehabilitated section of the Potomac Interceptor also incorporated a Vortex Flow Insert (VFI) into the design to improve air quality and reduce long-term maintenance costs. The specialized device spins wastewater in a spiral design, aerating the wastewater to help reduce odor and corrosion.

Picture of vortex

While the final connection has been made, the project will continue through the end of the year to complete some remaining work, including:

  • Connect the new pipe to the existing odor control facility
  • Fill and seal the old pipe with concrete
  • Install manhole risers and a cover over the vortex
  • Backfill the excavation site
  • Restore the Potomac Heritage Trail and surrounding natural environment

*Revegetation is not expected until spring 2026, once weather conditions are more favorable.

The upgraded infrastructure reduces the risk of future failures, minimizes odors, and improves environmental conditions near residential areas and public spaces. By modernizing this critical pipeline, DC Water is also helping to safeguard public health, support regional growth, and ensure that wastewater is safely and efficiently transported for treatment. These improvements will also deliver long-term cost savings by improving reliability and reducing the need for emergency repairs and frequent maintenance.

DC Water continues to work closely with local partners, including NOVA Parks and Fairfax County, to ensure transparency and community engagement as this project moves toward completion.

For more information and project updates visit the Potomac Interceptor Project page at dcwater.com/potomacinterceptor.

Latest News

Flyer reads Join Us January 28 6 p.m. - 7 p.m.

Learn more about winter replacements and protecting pipes from the cold

When temperatures plunge and the ground freezes, replacing lead service lines becomes more challenging—but DC Water doesn’t stop. Our Lead Free DC (LFDC) crews adapt. To learn more DC Water is hosting a virtual community meeting 6 - 7 p.m., Jan 28.

Photo of a worker on the slope an the slope with hydroseeding completed

Major Milestone Paves Way for Potomac River Tunnel Construction at the Site

DC Water has completed its slope stabilization project along Canal Road, a critical step in order to move forward with construction for the Potomac River Tunnel Project. Originally scheduled to end in February, the project finished about two months ahead of schedule, minimizing additional impacts to commuters and residents.

Picture of frozen water pipes with icicles hanging off of them

With December getting off to a near-record cold start now is the time to act. Winter weather can bring risks like frozen pipes, water main breaks, and other emergencies that can disrupt your water service. Don’t wait for something to happen. DC Water encourages customers to prepare now and know what to do if the unexpected happens.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of a worker on the slope an the slope with hydroseeding completed
DC Water Announces Early Completion of Canal Road Slope Stabilization Project

Major Milestone Paves Way for Potomac River Tunnel Construction at the Site

DC Water has completed its slope stabilization project along Canal Road, a critical step in order to move forward with construction for the Potomac River Tunnel Project. Originally scheduled to end in February, the project finished about two months ahead of schedule, minimizing additional impacts to commuters and residents.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.