Now Flowing. Key Connection to New Rehabilitated Section of Potomac Interceptor Completed

October 03, 2025
Image of new pipe section with wastewater flowing
Major Milestone in Sewer Line Repair Near Great Falls

DC Water crews pumped out the last of the wastewater from the bypass system, then carefully lifted the two-ton steel gate that had sealed off the newly rehabilitated section of the Potomac Interceptor Sewer Line. With the gate raised, wastewater from Virginia surged into the new 54-inch sanitary sewer line, joining flow from Maryland and connecting both to the upgraded infrastructure for the first time.

This final connection near Great Falls signals the new pipe section is now fully operational— renewing a critical part of the region’s sewer system. This achievement represents a significant step in completing this complex and critical infrastructure project, which began in 2022 and faced a setback last year when a part of the original pipe collapsed during construction.

The Potomac Interceptor is a massive sanitary sewer system capable of carrying nearly 100 million gallons of wastewater daily from communities in Virginia and Maryland to DC Water’s Blue Plains Advanced Wastewater Treatment Plant. Rehabilitating key sections of the 54-mile-long sewer line is a high priority project, within DC Water’s Capital Improvement Program to upgrade aging infrastructure.

The newly rehabilitated section of the Potomac Interceptor also incorporated a Vortex Flow Insert (VFI) into the design to improve air quality and reduce long-term maintenance costs. The specialized device spins wastewater in a spiral design, aerating the wastewater to help reduce odor and corrosion.

Picture of vortex

While the final connection has been made, the project will continue through the end of the year to complete some remaining work, including:

  • Connect the new pipe to the existing odor control facility
  • Fill and seal the old pipe with concrete
  • Install manhole risers and a cover over the vortex
  • Backfill the excavation site
  • Restore the Potomac Heritage Trail and surrounding natural environment

*Revegetation is not expected until spring 2026, once weather conditions are more favorable.

The upgraded infrastructure reduces the risk of future failures, minimizes odors, and improves environmental conditions near residential areas and public spaces. By modernizing this critical pipeline, DC Water is also helping to safeguard public health, support regional growth, and ensure that wastewater is safely and efficiently transported for treatment. These improvements will also deliver long-term cost savings by improving reliability and reducing the need for emergency repairs and frequent maintenance.

DC Water continues to work closely with local partners, including NOVA Parks and Fairfax County, to ensure transparency and community engagement as this project moves toward completion.

For more information and project updates visit the Potomac Interceptor Project page at dcwater.com/potomacinterceptor.

Latest News

Image of new pipe section with wastewater flowing

Major Milestone in Sewer Line Repair Near Great Falls

DC Water has completed the final connection on the rehabilitated section of the Potomac Interceptor near Great Falls, renewing an integral part of the region's sewer system. This achievement signals the new pipe section is now fully operational and represents a significant step in completing this complex and critical infrastructure project.

Picture showing inside of Rock Creek Main Interceptor with large crack in crown

Weekend Closure of Rock Creek Multi-Use Trail Begins Friday evening, Oct 3 for Gate Restoration Work

DC Water is advancing to the next critical phase of the Rock Creek Main Interceptor (RCMI) repair project, following the discovery in May of structural vulnerabilities in the 72-inch diameter sewer line that carries over 100 million gallons of wastewater daily. These repairs are a high priority to prevent potential sewage discharge into Rock Creek.

Aerial View of Construction near Watergate Complex Shows cranes and construction of drop shaft underway

Rock Creek and Potomac Parkway NW Beginning September 23, 2025, to Mid-November 2025

DC Water is installing temporary scaffolding at the Rock Creek Trail site, west of the Watergate Complex. Trail users are advised to adhere to flagger instructions during installation.

Scaffolding installation is expected to be completed by September 26, 2025, and will remain in place until mid-November 2025.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Aerial View of Construction near Watergate Complex Shows cranes and construction of drop shaft underway
Scaffolding Installation Begins near Watergate Complex for Potomac River Tunnel Project

Rock Creek and Potomac Parkway NW Beginning September 23, 2025, to Mid-November 2025

DC Water is installing temporary scaffolding at the Rock Creek Trail site, west of the Watergate Complex. Trail users are advised to adhere to flagger instructions during installation.

Scaffolding installation is expected to be completed by September 26, 2025, and will remain in place until mid-November 2025.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
October 7, 2025
Tuesday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.