DC Water Announces Early Completion of Canal Road Slope Stabilization Project

December 22, 2025
Photo of a worker on the slope an the slope with hydroseeding completed
Major Milestone Paves Way for Potomac River Tunnel Construction at the Site

DC Water has completed its slope stabilization project along Canal Road, a critical step in order to move forward with construction for the Potomac River Tunnel Project. Originally scheduled to end in February, the project finished about two months ahead of schedule, minimizing additional impacts to commuters and residents. 

With all major construction activities now finalized, the sidewalk adjacent to the slope is expected to reopen tomorrow, December 23, after the safety fencing and barriers are removed. An ADA-accessible shuttle which had been operating during the sidewalk closure will end service on Wednesday, December 24. Signage will be posted at the two stops - Georgetown University and Foxhall Road NW - to notify shuttle users the service is ending.

Additional work will continue on a few outstanding items to ensure the site is fully restored and ready for the next phase of construction.

Work on the slope began in September and required extensive coordination due to the complexity of the project, high traffic volumes, and the ongoing need to maintain safe access for both pedestrians and vehicles.  

Input from local residents, commuters, and stakeholders—including ongoing communication with the District Department of Transportation (DDOT)—helped to develop a revised plan to mitigate traffic and minimize disruption to the community.

During the course of work, crews removed trees and loose materials, drilling approximately 725 steel dowels into the slope and installing mesh to to ensure long-term slope stability. Crews also installed 9,300 linear feet of steel soil nails, applied 36,000 square feet of shotcrete facing, and constructed advanced draining systems. Over the past week, crews seeded the slope to allow new vegetation to grow, the final step in the process.

The instability of the slope has been a safety issue, previously identified by DDOT, after repeated shallow landslides and rockfalls over the years that posed a risk to motorists and pedestrians.

Without stabilizing the slope, DC Water could not advance construction to meet the aggressive schedule for the 5.5 mile tunnel project which will connect to DC Water’s existing system via seven shafts, including the site near Georgetown University.

Construction began on the Potomac River Tunnel in 2024 and is scheduled to finish in 2030. Once operational, the tunnel will reduce the amount of stormwater runoff and untreated sewage released into the Potomac River by approximately 93% and decrease the amount of times this happens from about 75 each year to only four in a typical year.

The project is a core component of DC Water’s Clean Rivers initiative and is being delivered under a Federal Consent Decree with the District of Columbia, the US Environmental Protection Agency (EPA), and the US Department of Justice.

For more information and updates on the Potomac River Tunnel Project, visit dcwater.com/PRT.

Latest News

Photo of LFDC work on a street in the Trinidad NE Neighborhood

Public Encouraged to Provide Comment through June 23

DC residents who want to replace their lead service lines may soon have more options to do it sooner—without having to wait for construction to reach their block.  While the Lead Free DC Program replaces lead service lines at no cost, DC Water has proposed two updates to its program that would make it easier and faster for some residents to get their lead pipes replaced, especially those at higher risk of lead exposure. These proposed changes have been published in the DC Register and are now open for public review. 

Graphic with details for the public hearing on June 23 at 6:30 p.m.

As DC Water’s Board of Directors considers proposed rate increases for the upcoming 2027 and 2028 fiscal years, we’re asking customers to provide feedback during a public hearing on Tuesday, June 23 at 6:30 p.m.

The proposed rate changes would support critical investments in safe, reliable drinking water, replacement of aging water and sewer lines, cleaner local waterways, and continued lead service line replacement across the District.

Placeholder DC Water Image

DC Water will host a virtual community meeting on Thursday, June 11, 2026, to inform residents and other stakeholders about the emergency rehabilitation of a section of the Potomac Interceptor at Muddy Branch in Potomac, Maryland.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of temporarily relocated section of Piney Branch Parkway
Piney Branch Parkway Section to Reopen Monday, Restoring a Key Route for DC Commuters

Following a 27-day closure, DC Water will reopen a section of Piney Branch Parkway between Arkansas Avenue and Beach Drive NW early Monday morning, restoring an important cross-town connection for thousands of District commuters. During the closure, a section of the road was temporarily relocated for construction of DC Water’s Piney Branch Tunnel Project.

Latest Blog Post
DC Water General Manager and CEO David Gadis recognizes Lily MacDonald during the May Board of Directors meeting.
From Classroom to Community: A Student Spotlight on DC Water's SPLASH Program
A speechwriting assignment became a call to action for water access and affordability through DC Water's SPLASH program.
Upcoming Meeting
Date
June 25, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.