DC Water Announces Early Completion of Canal Road Slope Stabilization Project

December 22, 2025
Photo of a worker on the slope an the slope with hydroseeding completed
Major Milestone Paves Way for Potomac River Tunnel Construction at the Site

DC Water has completed its slope stabilization project along Canal Road, a critical step in order to move forward with construction for the Potomac River Tunnel Project. Originally scheduled to end in February, the project finished about two months ahead of schedule, minimizing additional impacts to commuters and residents. 

With all major construction activities now finalized, the sidewalk adjacent to the slope is expected to reopen tomorrow, December 23, after the safety fencing and barriers are removed. An ADA-accessible shuttle which had been operating during the sidewalk closure will end service on Wednesday, December 24. Signage will be posted at the two stops - Georgetown University and Foxhall Road NW - to notify shuttle users the service is ending.

Additional work will continue on a few outstanding items to ensure the site is fully restored and ready for the next phase of construction.

Work on the slope began in September and required extensive coordination due to the complexity of the project, high traffic volumes, and the ongoing need to maintain safe access for both pedestrians and vehicles.  

Input from local residents, commuters, and stakeholders—including ongoing communication with the District Department of Transportation (DDOT)—helped to develop a revised plan to mitigate traffic and minimize disruption to the community.

During the course of work, crews removed trees and loose materials, drilling approximately 725 steel dowels into the slope and installing mesh to to ensure long-term slope stability. Crews also installed 9,300 linear feet of steel soil nails, applied 36,000 square feet of shotcrete facing, and constructed advanced draining systems. Over the past week, crews seeded the slope to allow new vegetation to grow, the final step in the process.

The instability of the slope has been a safety issue, previously identified by DDOT, after repeated shallow landslides and rockfalls over the years that posed a risk to motorists and pedestrians.

Without stabilizing the slope, DC Water could not advance construction to meet the aggressive schedule for the 5.5 mile tunnel project which will connect to DC Water’s existing system via seven shafts, including the site near Georgetown University.

Construction began on the Potomac River Tunnel in 2024 and is scheduled to finish in 2030. Once operational, the tunnel will reduce the amount of stormwater runoff and untreated sewage released into the Potomac River by approximately 93% and decrease the amount of times this happens from about 75 each year to only four in a typical year.

The project is a core component of DC Water’s Clean Rivers initiative and is being delivered under a Federal Consent Decree with the District of Columbia, the US Environmental Protection Agency (EPA), and the US Department of Justice.

For more information and updates on the Potomac River Tunnel Project, visit dcwater.com/PRT.

Latest News

DC Water team on stage receiving Merit Award from DBIA during awards ceremony

DC Water is being honored with a national award from the Design-Build Institute of America (DBIA). The award recognizes DC Water for its rehabilitation of a critical section of the Potomac Interceptor ...

Photo of workers on M St doing repairs

On Thursday, November 5, beginning at 9 p.m., DC Water will be doing valve repair work involving lane closures and potential delays along M Street NW in Georgetown. Crews will replace one large valve ...

Map of lane closure inbound on Clara Barton Parkway

Drivers should expect periodic traffic delays midday and overnight on Clara Barton Parkway at the Maryland-DC border through December 23, 2026, as DC Water works to complete emergency repairs on the ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Christening of TBM Emily with DC Water Interim General Manager Matt Brown holding bottle of tap water to christen Emily
DC Water Welcomes the Community Underground to See the Potomac River Tunnel and Christens Tunnel Boring Machine Emily

DC Water celebrated the christening of Emily today. It’s the second giant tunnel boring machine (TBM) that will help build the 5.5-mile Potomac River Tunnel. The celebration continued with Community Day. Residents and families met Emily and stepped inside the tunnel where she will soon begin digging.

Latest Blog Post
Emergency supplies arranged on a table, including bottled water, canned food, a backpack, first aid kit, flashlight, phone, medication and other essential items.
Simple Ways to Stay Prepared at Home
A few simple steps can help your household prepare for severe weather and temporary water or sewer service interruptions.
Upcoming Meeting
Date
November 12, 2026
Thursday, 9:30 AM

Upcoming Events

Nov 12
6:30 pm - 7:30 pm

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.