DC Water to Begin Canal Rd Nightwork with Single Westbound Lane Closure

October 27, 2025
View the slope stabilization project area on Canal Road NW.

As part of DC Water’s slope stabilization project, one westbound lane of Canal Road NW will be closed during overnight work between Foxhall Road (Glover-Archbold Trailhead) and the Georgetown University entrance. The project has entered a new phase involving the removal of loose material from the slope. The lane closure will be in effect Monday through Friday from 8 p.m. to 5 a.m. and Saturdays from 7 a.m. to 7 p.m.

This construction activity is part of the ongoing preparations for the Potomac River Tunnel Project—an essential infrastructure initiative aimed at enhancing water quality in the Potomac River. Due to recurring landslides and falling debris along the slope, the District Department of Transportation (DDOT) has identified the area as a public safety hazard. Stabilizing the slope is a necessary step to safely build a deep drop shaft that will connect to the tunnel system, helping to significantly reduce wastewater overflows into the river.


Map of single westbound lane closure on Canal Road Northwest

Traffic Pattern Changes
One westbound lane will be closed during off-peak hours.
Time: Monday -- Friday from 8:00 p.m. to 5:00 a.m. and Saturdays from 7:00 a.m. to 7:00 p.m.
Duration: Starting Monday, October 27, 2025, and continuing for approximately three weeks.

Sidewalk Closure
The sidewalk will be closed on the north side of Canal Rd adjacent to the work zone. Detours and shuttle available:

  • Pedestrian/cyclist detours via Reservoir Road, C&O Canal Towpath, Capital Crescent Trail, and Glover-Archbold Trail
  • Shuttle Service:
    • An ADA-accessible shuttle will transport pedestrians and bicyclists between designated stops on Canal Road near the Georgetown University (GU) entrance and on Foxhall Road near the intersection with 44th Street NW.
    • Request Canal Road shuttle from the Foxhall or GU stops.
    • Call (703) 919-7430 for free ADA-accessible shuttle with bike transport

The slope stabilization supports the Potomac River Tunnel Project, an $819 million, 5.5-mile-long tunnel that will significantly reduce the amount of untreated sewage and stormwater entering the Potomac River. The Project is included in DC Water’s Capital Improvement Program, which invests in infrastructure to protect public health, improve water quality, and enhance service reliability across the District.

For more information 
Visit dcwater.com/slope or call (202) 787-4400 
 

Latest News

Photo of giant rock and boulder removed

DC Water is releasing new findings regarding the environmental impacts following the January 19, collapse in a section of the Potomac Interceptor. Based on flow monitoring data collected before and after interim bypass pumping was activated, DC Water estimates approximately 243 million gallons of wastewater has overflowed from the collapse site.

Image of rock blockage taken by CCTV inside the Potomac Interceptor downstream of the collapse

Update on Extended Repairs, Safety Measures, and Water Quality Monitoring

Overnight CCTV inspection of the Potomac Interceptor revealed the blockage inside the collapsed sewer line is far more significant, showing a large rock dam stretching approximately 30 feet downstream of the original failure.

Three workers over the pit accessing the Potomac Interceptor for Cleaning

DC Water and its contractor are working to clean debris from a damaged section of the Potomac Interceptor, a sanitary sewer line that collapsed on January 19, along Clara Barton Parkway and the 495 ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.