DC Water Takes Measures Ahead of Rain, Snow to Prevent Flooding and Impacts on Potomac Interceptor Repairs

February 22, 2026
CEO David L. Gadis with HSEMA, EPA and USACE

DC Water crews are working around the clock to keep the Potomac Interceptor repair site safe as another storm approaches. Since February 8, there have been no overflows to the Potomac River, and efforts are underway to bolster pump capacity and manage stormwater runoff due to expected heavy rain and snow that could flood the pumping site and endanger pumping operations.

Keeping the pumping system running is critical to prevent overflows and support ongoing emergency repairs. At the collapse site, workers are assembling materials and equipment to extend the excavation around the damaged section, stabilize the area, and remove portions of the pipe to access the rock and debris inside.

In preparation for the winter storm event, DC Water has also partnered with the U.S. Army Corps of Engineers (USACE) to provide critical support to help with stormwater management. During heavy rains earlier this week, stormwater runoff from the American Legion Bridge and Clara Barton Parkway inundated the pumping site. USACE teams have completed a site assessment and are actively implementing measures to contain and divert stormwater away from the pumping site.

Floodwaters not only put the pumps at risk but make it difficult for workers to perform the maintenance and cleaning to keep operations moving. Increased flow from stormwater rushing into the bypass system also puts additional strain on the pumps.

A section of the Potomac Interceptor, a sanitary sewer line, collapsed near Clara Barton Parkway and the C & O Canal National Historical Park on January 19. Emergency repairs are expected to restore full flow and function to the interceptor by mid-March, which will contain the risk of overflow and eliminate the need for the bypass system.

The next step in repairs is removing the rock and debris blocking the pipe near the collapse site. An initial assessment found the pipe section housing the rock dam was compromised and unsafe for crews to manually remove the rocks from inside the pipe. Once excavation is complete, workers will then cut the crown of the pipe for direct access to safely remove the large rocks and boulders forming the dam while protecting workers and the integrity of the structure.

DC Water is coordinating with National Park Service, Environmental Protection Agency, Maryland Department of the Environment, and USACE on the Environmental Restoration Plan and are looking at options to begin implementing some remediation measures in advance of the larger restoration work once the emergency repair is complete.

DC Water at collapse site left and right USACE crews working on stormwater runoff

(Left) DC Water crews working to stabilize and extend excavation around collapse site. (Right) USACE crews installing stormwater management along Clara Barton Parkway.

We continue to conduct water quality sampling, and are working with our federal, state, and local partners to protect the river and mitigate the impact on the environment.

DC Water shares community concerns about the impact on the Potomac River. The public is invited to join us this week to learn more about DC Water’s response, current system status, and next steps in emergency repair and long-term rehabilitation efforts:

Wednesday, February 25 - Washington, DC

DC Water Headquarters, 1385 Canal St SE, Washington, DC 20003

Time: 7:00 PM

Thursday, February 26 – Bethesda, Maryland

Walt Whitman High School (cafeteria), 7100 Whittier Blvd., Bethesda, MD 20817

Time: 7:00 PM

Water Quality Sampling Results

DC Water is performing daily water quality sampling. It’s important to note that historically the E. coli levels in the Potomac and Anacostia rivers vary widely from day to day. Fluctuations in water quality are influenced by factors such as weather events, river flow, runoff, pollutants, and other sources discharging into waterways; and measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day.

A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs

*Lab results are unavailable on weekends and will be provided the following Monday (excluding holidays).

graphic of sampling results

For more information about the ongoing repair efforts go to dcwater.com/Potomac-interceptor-collapse

 

Latest News

image of clara barton parkway with lane closure marked in red

Beginning this week and continuing through mid-August, DC Water will temporarily close one lane overnight on Clara Barton Parkway at the Maryland-D.C. border. The closures are needed so crews can ...

Pennyfield Lock Potomac Interceptor bypass pipeline running next to C & O Canal with equipment

There is no active spill or overflow. Work to strengthen the pipe to begin soon.

Today, DC Water completed construction on a temporary bypass system as part of sewer repairs on the Potomac Interceptor near Pennyfield Lock in Potomac, Maryland. Crews turned on the pumps and successfully tested the system. With the bypass now ready, it will allow us to begin the emergency repairs inside the pipe by carrying the wastewater around the repair area.

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking
DC Water Breaks Ground on Piney Branch Tunnel, Final Phase of DC Clean Rivers Project

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Latest Blog Post
Five photos from the American Water Works Association (AWWA) ACE26 conference featuring panel discussions, technical presentations, networking, and attendees posing at the ACE26 display.
ACE26 Highlights: How DC Water Advanced the Conversation on Water
More than 80 DC Water employees joined thousands of water professionals in Washington, D.C., sharing expertise, building partnerships and advancing conversations that will help shape the future of water.
Upcoming Meeting
Date
July 23, 2026
Thursday, 9:30 AM

Upcoming Events

Jul 23
Jul 25

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.