DC Water Takes Measures Ahead of Rain, Snow to Prevent Flooding and Impacts on Potomac Interceptor Repairs

February 22, 2026
CEO David L. Gadis with HSEMA, EPA and USACE

DC Water crews are working around the clock to keep the Potomac Interceptor repair site safe as another storm approaches. Since February 8, there have been no overflows to the Potomac River, and efforts are underway to bolster pump capacity and manage stormwater runoff due to expected heavy rain and snow that could flood the pumping site and endanger pumping operations.

Keeping the pumping system running is critical to prevent overflows and support ongoing emergency repairs. At the collapse site, workers are assembling materials and equipment to extend the excavation around the damaged section, stabilize the area, and remove portions of the pipe to access the rock and debris inside.

In preparation for the winter storm event, DC Water has also partnered with the U.S. Army Corps of Engineers (USACE) to provide critical support to help with stormwater management. During heavy rains earlier this week, stormwater runoff from the American Legion Bridge and Clara Barton Parkway inundated the pumping site. USACE teams have completed a site assessment and are actively implementing measures to contain and divert stormwater away from the pumping site.

Floodwaters not only put the pumps at risk but make it difficult for workers to perform the maintenance and cleaning to keep operations moving. Increased flow from stormwater rushing into the bypass system also puts additional strain on the pumps.

A section of the Potomac Interceptor, a sanitary sewer line, collapsed near Clara Barton Parkway and the C & O Canal National Historical Park on January 19. Emergency repairs are expected to restore full flow and function to the interceptor by mid-March, which will contain the risk of overflow and eliminate the need for the bypass system.

The next step in repairs is removing the rock and debris blocking the pipe near the collapse site. An initial assessment found the pipe section housing the rock dam was compromised and unsafe for crews to manually remove the rocks from inside the pipe. Once excavation is complete, workers will then cut the crown of the pipe for direct access to safely remove the large rocks and boulders forming the dam while protecting workers and the integrity of the structure.

DC Water is coordinating with National Park Service, Environmental Protection Agency, Maryland Department of the Environment, and USACE on the Environmental Restoration Plan and are looking at options to begin implementing some remediation measures in advance of the larger restoration work once the emergency repair is complete.

DC Water at collapse site left and right USACE crews working on stormwater runoff

(Left) DC Water crews working to stabilize and extend excavation around collapse site. (Right) USACE crews installing stormwater management along Clara Barton Parkway.

We continue to conduct water quality sampling, and are working with our federal, state, and local partners to protect the river and mitigate the impact on the environment.

DC Water shares community concerns about the impact on the Potomac River. The public is invited to join us this week to learn more about DC Water’s response, current system status, and next steps in emergency repair and long-term rehabilitation efforts:

Wednesday, February 25 - Washington, DC

DC Water Headquarters, 1385 Canal St SE, Washington, DC 20003

Time: 7:00 PM

Thursday, February 26 – Bethesda, Maryland

Walt Whitman High School (cafeteria), 7100 Whittier Blvd., Bethesda, MD 20817

Time: 7:00 PM

Water Quality Sampling Results

DC Water is performing daily water quality sampling. It’s important to note that historically the E. coli levels in the Potomac and Anacostia rivers vary widely from day to day. Fluctuations in water quality are influenced by factors such as weather events, river flow, runoff, pollutants, and other sources discharging into waterways; and measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day.

A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs

*Lab results are unavailable on weekends and will be provided the following Monday (excluding holidays).

graphic of sampling results

For more information about the ongoing repair efforts go to dcwater.com/Potomac-interceptor-collapse

 

Latest News

A section of the canal where the soil has been removed
  • Crews are close to completing the removal of remaining soil from Locks 11 to 13 in the section of the C&O Canal that was used as an emergency bypass after the collapse of the Potomac Interceptor sewer ...
Excavation site outside the I-495 Beltway showing section of the PI

Crews completed cleaning on Lock 11 of the C & O Canal as prescribed by the National Park Service, with soil removal also nearing completion within the lock area. Tree removal is also underway, after DC Water received the permits to move forward as part of the site preparations for the long-term accelerated rehabilitation of more than 2700 linear feet of the Potomac Interceptor sewer line that had been previously planned.

Photo of long stretch of C & O Canal with soil removed

DC Water has excavated a section of the Potomac Interceptor along Clara Barton Parkway, outside the I-495 Beltway as part of the accelerated rehabilitation of more than 2700 linear feet of the interceptor that was previously planned. As part of the long-term rehabilitation project, crews are beginning to remove trees which is necessary to construct a bypass chamber that will divert wastewater around sections of the pipe while they are being rehabilitated.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

The shields for the tunnel boring machine Mary being lowered by cranes into the shaft
DC Water Earns Prominent Award for Sustainable Finance Leadership through Green Bonds

Recognition highlights DC Water’s commitment to environmental stewardship during Earth Month

DC Water has been honored with the “Green Bond of the Year – US Muni Bond” Award by Environmental Finance, a leading industry publication. This achievement celebrates DC Water’s leadership in sustainability and its dedication to responsible municipal financing.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
May 5, 2026
Tuesday, 1:00 PM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.