DC Water's

News & Updates

At DC Water, we understand the importance of keeping our community informed about our services, projects, and achievements. Our news web page serves as a reliable source for the latest information on a range of topics.

Image of the collapse site drained of water
18 February, 2026

Efforts to isolate the damaged section of pipe are moving forward. Engineers are on site and preparations are underway to permanently install a steel bulkhead gate that will cut off flow to the collapse site in combination with an enhanced bypass pumping system that will continue to divert wastewater around the failure and into the Potomac Interceptor further downstream. Once fully activated, the ...

Enhanced bypass with pumps and bulkhead gate in position
17 February, 2026

Potomac Interceptor Collapse Update
Tuesday, February 17, 2026

  • No overflow events impacting surface waters were reported overnight. No overflow events impacting surface waters have been reported since February 9, 2026.
  • DC Water continues making significant progress toward stabilizing the Potomac Interceptor, with crews successfully testing the bulkhead system and bypass pumps. Six of the seven new ...
Photo fo new access pit for enhanced bypass and pumps
16 February, 2026

Emergency repair expected to take 4-6 weeks, followed by long-term rehabilitation

DC Water crews and its contractors, working under challenging conditions over the past month, are nearing completion of an enhanced bypass system that will allow emergency repairs to begin on a damaged section of the Potomac Interceptor.

Bypass pumps in operation to reroute wastewater around the break
15 February, 2026

Potomac Interceptor Repairs Update

February 15, 2026 

  • No overflow events impacting surface waters have been reported in the past 24 hours.
  • The four high-capacity bypass pumps installed this week are now fully primed and operational, increasing overall system capacity and reliability. 
  • In addition, the third flume at the downstream end of the canal near Lock 10 is now active and conveying wastewater ...
Photo of access pit upstream with four pumps lined up ready for installation
14 February, 2026

Crews have completed construction of the two new access pits to support full installation of the enhanced bypass pumping system. Three high-capacity bypass pumps have been installed and are operational, with a fourth pump expected to be activated later tonight or early Sunday ahead of the forecasted weather to help manage anticipated higher flows associated with rainfall and snowmelt.

contract for construction of the Potomac River Tunnel (PRT)
13 February, 2026

No overflow events impacting surface waters have been reported in the past 24 hours as crews continue advancing construction of the two new access pits to support full installation of the enhanced bypass pumping system. Additional high-capacity bypass pumps are on site in advance of the forecasted weather on Sunday to help manage anticipated higher flows associated with rainfall and snowmelt.

Photo of concrete being poured through a manhole or access point
13 February, 2026

DC Water Completes Critical Work, Ensuring Public Safety and Roadway Stability
Tonight, DC Water has reopened the northbound lanes of 14th Street NW between L Street and Thomas Circle, following the successful completion of emergency repairs to a century-old, abandoned sewer tunnel beneath the roadway. These repairs took place over the past week, ensuring the safety and stability of this critical ...

DC Water CEO David Gadis talks to Chief Operating Officer Matt Brown on site.
12 February, 2026

Potomac Interceptor Repair Update
February 12, 2026

Highlights:

  • No overflow events impacting surface waters have been reported in the past 24 hours.
  • Crews continue advancing construction of two new access pits to support installation of the enhanced bypass pumping system. The first of the new high-capacity bypass pumps is scheduled to arrive on site Friday.
  • These pumps will increase redundancy and ...
contract for construction of the Potomac River Tunnel (PRT)
11 February, 2026

To our neighbors, community partners, and everyone who cares deeply about the Potomac River and our shared commitment to the Potomac River.

Photo of trucks and construction at downstream location working on the enhanced bypass pumping system
11 February, 2026

Work remains ongoing, and protecting public health and the Potomac River continues to be the top priority of DC Water.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Christening of TBM Emily with DC Water Interim General Manager Matt Brown holding bottle of tap water to christen Emily
DC Water Welcomes the Community Underground to See the Potomac River Tunnel and Christens Tunnel Boring Machine Emily

DC Water celebrated the christening of Emily today. It’s the second giant tunnel boring machine (TBM) that will help build the 5.5-mile Potomac River Tunnel. The celebration continued with Community Day. Residents and families met Emily and stepped inside the tunnel where she will soon begin digging.

Latest Blog Post
Emergency supplies arranged on a table, including bottled water, canned food, a backpack, first aid kit, flashlight, phone, medication and other essential items.
Simple Ways to Stay Prepared at Home
A few simple steps can help your household prepare for severe weather and temporary water or sewer service interruptions.
Upcoming Meeting
Date
November 12, 2026
Thursday, 9:30 AM

Upcoming Events

Nov 12
6:30 pm - 7:30 pm

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.