UPDATE: No Sewer Overflows Reported Today from Damaged Sewer Line as Excavation Work, Pumping Continues

January 29, 2026
Photo of collapse site and federal, state, local officials in background
Federal, State, and Local Officials Get Firsthand Look at Collapse Site and Repair Efforts

Over the past 24-hours, DC Water engineers for the first time report no sanitary sewer overflows escaping from a damaged section of the Potomac Interceptor since the incident happened. The 72-inch diameter pipe section collapsed on January 19, along Clara Barton Parkway and the C & O Canal National Historical Park in Montgomery County, MD.

This marks major progress in containment efforts, achieved through the continued operation of bypass pumps, focused excavation, and cleaning and monitoring at the site. These efforts have greatly reduced the possibility of additional overflow, although some risk remains. A small amount of residual wastewater is still in the creek bed, but most of the flow to the river has stopped in the interim.

Today, officials with the U.S. Environmental Protection Agency (EPA), Maryland Department of Environment (MDE), and DC Department of Energy and Environment (DOEE) toured the collapse site. The visit provided a firsthand look into ongoing bypass operations, excavation, and the repair process, underscoring the strong oversight and collaboration among federal, state, and local agencies.

Crews have excavated a section of the sewer line about 30 feet downstream of the collapse site and removed the crown of the pipe. Active flow is visible indicating the sewer line is partially functioning – despite the damage - with some wastewater getting past the break and continuing downstream in the Potomac Interceptor.

Work will begin tomorrow to clean debris and obstructions in the pipe, a critical step toward restoring full flow through the system and eliminate dry and wet weather overflows. Additional work will also get underway to stabilize the ground at the collapse site. Trench boxes, acting as giant retaining walls, will be installed around the damaged section for containment and to prevent more erosion. Once debris is cleared and wastewater levels around the collapse drop further, teams will excavate the damaged pipe section to thoroughly assess the damage. This will determine the repairs needed and timeline.

Eight bypass pumps remain in operation, with crews monitoring the site 24/7 to keep the pumps running through difficult conditions posed by the extreme cold. The system began operation on Saturday, diverting a significant volume of wastewater around the damaged pipe and carrying it back into the Potomac Interceptor further downstream of the collapse.

For your safety, DC Water urges residents and visitors to avoid the affected area along Clara Barton Parkway and nearby trails in Montgomery County. Work zones are active and may pose hazards. Please adhere to posted warning signs.

As a reminder, there is no impact to drinking water. The drinking water system is separate from the wastewater system and the Washington Aqueduct’s primary intakes for drinking water are upstream from the overflow.

DC Water will continue to work closely with federal, state, and local partners to assess potential environmental impacts and remediation.

 For questions or updates, please contact DC Water’s Customer Care team at (202) 354-3600 (Monday–Friday, 8 a.m. to 5 p.m.) or the 24-Hour Command Center at (202) 612-3400. 

 

Latest News

image of clara barton parkway with lane closure marked in red

Beginning this week and continuing through mid-August, DC Water will temporarily close one lane overnight on Clara Barton Parkway at the Maryland-D.C. border. The closures are needed so crews can ...

Pennyfield Lock Potomac Interceptor bypass pipeline running next to C & O Canal with equipment

There is no active spill or overflow. Work to strengthen the pipe to begin soon.

Today, DC Water completed construction on a temporary bypass system as part of sewer repairs on the Potomac Interceptor near Pennyfield Lock in Potomac, Maryland. Crews turned on the pumps and successfully tested the system. With the bypass now ready, it will allow us to begin the emergency repairs inside the pipe by carrying the wastewater around the repair area.

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking
DC Water Breaks Ground on Piney Branch Tunnel, Final Phase of DC Clean Rivers Project

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Latest Blog Post
Plastic bottles, cups and other floating debris on the surface of the Anacostia River before the Anacostia River Tunnel began operating.
Cleaner Waterways Start With Everyday Choices
Protecting our waterways starts with everyday actions and continues through critical infrastructure designed to keep pollution out of our rivers.
Upcoming Meeting
Date
July 28, 2026
Tuesday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.