UPDATE: No Sewer Overflows Reported Today from Damaged Sewer Line as Excavation Work, Pumping Continues

January 29, 2026
Photo of collapse site and federal, state, local officials in background
Federal, State, and Local Officials Get Firsthand Look at Collapse Site and Repair Efforts

Over the past 24-hours, DC Water engineers for the first time report no sanitary sewer overflows escaping from a damaged section of the Potomac Interceptor since the incident happened. The 72-inch diameter pipe section collapsed on January 19, along Clara Barton Parkway and the C & O Canal National Historical Park in Montgomery County, MD.

This marks major progress in containment efforts, achieved through the continued operation of bypass pumps, focused excavation, and cleaning and monitoring at the site. These efforts have greatly reduced the possibility of additional overflow, although some risk remains. A small amount of residual wastewater is still in the creek bed, but most of the flow to the river has stopped in the interim.

Today, officials with the U.S. Environmental Protection Agency (EPA), Maryland Department of Environment (MDE), and DC Department of Energy and Environment (DOEE) toured the collapse site. The visit provided a firsthand look into ongoing bypass operations, excavation, and the repair process, underscoring the strong oversight and collaboration among federal, state, and local agencies.

Crews have excavated a section of the sewer line about 30 feet downstream of the collapse site and removed the crown of the pipe. Active flow is visible indicating the sewer line is partially functioning – despite the damage - with some wastewater getting past the break and continuing downstream in the Potomac Interceptor.

Work will begin tomorrow to clean debris and obstructions in the pipe, a critical step toward restoring full flow through the system and eliminate dry and wet weather overflows. Additional work will also get underway to stabilize the ground at the collapse site. Trench boxes, acting as giant retaining walls, will be installed around the damaged section for containment and to prevent more erosion. Once debris is cleared and wastewater levels around the collapse drop further, teams will excavate the damaged pipe section to thoroughly assess the damage. This will determine the repairs needed and timeline.

Eight bypass pumps remain in operation, with crews monitoring the site 24/7 to keep the pumps running through difficult conditions posed by the extreme cold. The system began operation on Saturday, diverting a significant volume of wastewater around the damaged pipe and carrying it back into the Potomac Interceptor further downstream of the collapse.

For your safety, DC Water urges residents and visitors to avoid the affected area along Clara Barton Parkway and nearby trails in Montgomery County. Work zones are active and may pose hazards. Please adhere to posted warning signs.

As a reminder, there is no impact to drinking water. The drinking water system is separate from the wastewater system and the Washington Aqueduct’s primary intakes for drinking water are upstream from the overflow.

DC Water will continue to work closely with federal, state, and local partners to assess potential environmental impacts and remediation.

 For questions or updates, please contact DC Water’s Customer Care team at (202) 354-3600 (Monday–Friday, 8 a.m. to 5 p.m.) or the 24-Hour Command Center at (202) 612-3400. 

 

Latest News

Picture of flow back in the Potomac Interceptor

DC Water Celebrates Massive 55-Day Effort, Outlines Next Steps for Rehabilitation and Environmental Restoration

After 55 days of extraordinary effort with crews working around the clock, DC Water has successfully completed emergency repairs and returned the flow to the Potomac Interceptor to mark a major milestone.

graphic with meeting times

Second Meeting Scheduled in Bethesda; Community Forum in Alexandria Next Week

As DC Water nears completion of emergency repairs on the Potomac Interceptor sewer line, we remain committed to transparent communication and partnership with our community. Next week, two meetings are scheduled on March 18, in Bethesda, MD and March 19, in Alexandria, VA to hear from the community and provide informational updates.

Photo of PI ready for return of flow
  • DC Water has completed final site preparations to return the flow to the Potomac Interceptor, marking and important milestone after 33 consecutive days without an overflow to the Potomac River.
  • The ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Map of lane closure
Traffic Advisory: Rock Creek and Potomac Parkway NW Lane Closure Beginning Jan 19

Beginning on or about January 19, 2026, weather permitting, DC Water will implement a temporary lane closure on Rock Creek and Potomac Parkway NW b

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
March 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.