EMERGENCY WATER OUTAGE
Sep 23, 2026 | 07:00 AM

EMERGENCY WATER OUTAGE EXTENDED
Sep 23, 2026 | 04:00 AM

UPDATE: No Sewer Overflows Reported Today from Damaged Sewer Line as Excavation Work, Pumping Continues

January 29, 2026
Photo of collapse site and federal, state, local officials in background
Federal, State, and Local Officials Get Firsthand Look at Collapse Site and Repair Efforts

Over the past 24-hours, DC Water engineers for the first time report no sanitary sewer overflows escaping from a damaged section of the Potomac Interceptor since the incident happened. The 72-inch diameter pipe section collapsed on January 19, along Clara Barton Parkway and the C & O Canal National Historical Park in Montgomery County, MD.

This marks major progress in containment efforts, achieved through the continued operation of bypass pumps, focused excavation, and cleaning and monitoring at the site. These efforts have greatly reduced the possibility of additional overflow, although some risk remains. A small amount of residual wastewater is still in the creek bed, but most of the flow to the river has stopped in the interim.

Today, officials with the U.S. Environmental Protection Agency (EPA), Maryland Department of Environment (MDE), and DC Department of Energy and Environment (DOEE) toured the collapse site. The visit provided a firsthand look into ongoing bypass operations, excavation, and the repair process, underscoring the strong oversight and collaboration among federal, state, and local agencies.

Crews have excavated a section of the sewer line about 30 feet downstream of the collapse site and removed the crown of the pipe. Active flow is visible indicating the sewer line is partially functioning – despite the damage - with some wastewater getting past the break and continuing downstream in the Potomac Interceptor.

Work will begin tomorrow to clean debris and obstructions in the pipe, a critical step toward restoring full flow through the system and eliminate dry and wet weather overflows. Additional work will also get underway to stabilize the ground at the collapse site. Trench boxes, acting as giant retaining walls, will be installed around the damaged section for containment and to prevent more erosion. Once debris is cleared and wastewater levels around the collapse drop further, teams will excavate the damaged pipe section to thoroughly assess the damage. This will determine the repairs needed and timeline.

Eight bypass pumps remain in operation, with crews monitoring the site 24/7 to keep the pumps running through difficult conditions posed by the extreme cold. The system began operation on Saturday, diverting a significant volume of wastewater around the damaged pipe and carrying it back into the Potomac Interceptor further downstream of the collapse.

For your safety, DC Water urges residents and visitors to avoid the affected area along Clara Barton Parkway and nearby trails in Montgomery County. Work zones are active and may pose hazards. Please adhere to posted warning signs.

As a reminder, there is no impact to drinking water. The drinking water system is separate from the wastewater system and the Washington Aqueduct’s primary intakes for drinking water are upstream from the overflow.

DC Water will continue to work closely with federal, state, and local partners to assess potential environmental impacts and remediation.

 For questions or updates, please contact DC Water’s Customer Care team at (202) 354-3600 (Monday–Friday, 8 a.m. to 5 p.m.) or the 24-Hour Command Center at (202) 612-3400. 

 

Latest News

Christening of TBM Emily with DC Water Interim General Manager Matt Brown holding bottle of tap water to christen Emily

DC Water celebrated the christening of Emily today. It’s the second giant tunnel boring machine (TBM) that will help build the 5.5-mile Potomac River Tunnel. The celebration continued with Community Day. Residents and families met Emily and stepped inside the tunnel where she will soon begin digging.

Map: Temporary closure of the southbound curb lane on Rock Creek and Potomac Parkway NW

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT

Drivers should expect a temporary southbound lane closure on Rock Creek and Potomac Parkway NW between F St and Virginia Ave on Saturday, September 19, and Sunday, September 20, 2026. The closure will be in place from 7 a.m. to 7 p.m. each day, weather permitting.

Map of Potomac Interceptor at MD/DC Line Lane Closure Area

Beginning this week and continuing through the end of September, DC Water may close one lane temporarily between 10 a.m. to 2 p.m. on Clara Barton Parkway at the Maryland - DC border. The closures are ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Christening of TBM Emily with DC Water Interim General Manager Matt Brown holding bottle of tap water to christen Emily
DC Water Welcomes the Community Underground to See the Potomac River Tunnel and Christens Tunnel Boring Machine Emily

DC Water celebrated the christening of Emily today. It’s the second giant tunnel boring machine (TBM) that will help build the 5.5-mile Potomac River Tunnel. The celebration continued with Community Day. Residents and families met Emily and stepped inside the tunnel where she will soon begin digging.

Latest Blog Post
Emergency supplies arranged on a table, including bottled water, canned food, a backpack, first aid kit, flashlight, phone, medication and other essential items.
Simple Ways to Stay Prepared at Home
A few simple steps can help your household prepare for severe weather and temporary water or sewer service interruptions.
Upcoming Meeting
Date
September 24, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.