UPDATE: DC Water Begins Excavation to Assess Damaged Sewer Line and Lay Groundwork for Repair Efforts

January 28, 2026
Photo of collapse site of Potomac Interceptor and excavation underway

Excavation is underway to access a damaged section of the Potomac Interceptor, a major sewer line that collapsed on January 19, along Clara Barton Parkway near the 495-interchange and C & O National Historical Park in Montgomery County, MD. This marks a pivotal step forward in the recovery process, allowing DC Water and its contractor to directly inspect the damaged pipe, exposing the affected section to assess its condition and formulate the best possible repair strategy.

A bypass system activated this weekend continues to successfully divert wastewater back into the sewer line further downstream of the collapse site.  Engineers on-site report the lowest level of overflow from the area around the collapse since the incident started allowing the excavation activities to begin.

While still in the early stages of excavation, the site is stabilized with work progressing as a high priority repair. The focus over the next few days is to safely reach the break location to remove debris and collapsed material blocking the sewer line. This is vital to restoring the system’s functionality and eliminate dry and wet weather overflows. Preliminarily, engineers will be evaluating whether they can remove the crown of the damaged section of pipe, allowing the flow to go downstream through the pipe, fully contain the overflow, and reduce reliance on temporary pumping.

Repairing the pipe will be a complex and timely process, given the size of the 72-inch diameter sewer line and the volume of wastewater flow. Until the damaged pipe is inspected, the timeline for the repair cannot be determined. Engineers are exploring whether they can fix the broken pipe using 50 feet of 72-inch pipe from a previous project just completed upstream. This could potentially expedite the repairs.  

Two additional pumps began operating today to support the bypass pump operations. This is in addition to the six industrial sized pumps that have been working since Saturday – each with a capacity to pump seven million gallons a day. The additional pumps will provide more pumping capacity and redundancy when pumps need to be taken out of service for cleaning and maintenance.

While a small volume of wastewater is still escaping, the bypass has greatly minimized overflows, with no overflow reported for more than ten hours today. During peak periods when people wake up and return home from work and school demand may increase. This can cause some temporary overflow which is being monitored closely around the clock. Additionally, given the volume of the overflow over the past week it will take time to fully drain the creek bed and stop the flow into the Potomac – even with full containment.

Once the damaged pipe section is excavated, contractors will work to install trench boxes for shoring – acting as giant retaining walls – to contain the flow while repairs are being made.

Since the collapse occurred, DC Water has been working closely with federal, state and local partners, including the U.S. Environmental Protection Agency (EPA), National Park Service, U.S. Coast Guard, Washington Aqueduct, District Department of Energy and Environment (DOEE), DC Homeland Security and Emergency Management Agency, Maryland Department of the Environment, and the Montgomery County, Fairfax County and Loudoun County governments. Together, we are coordinating efforts to contain the overflow, monitor and assess environmental impacts, and keep the public informed.

DC Water continues to remind the public to follow all warning signs, avoid contact with sewer overflows, and keep pets away. Anyone who comes in contact with wastewater should wash exposed skin immediately, disinfect shoes or other items, and seek medical attention in the event of illness.

If you have any questions or need additional information contact DC Water’s Customer Care team at (202) 354-3600 (Monday–Friday, 8 a.m. to 5 p.m.) or the 24-Hour Command Center at (202) 612-3400. 

Latest News

image of clara barton parkway with lane closure marked in red

Beginning this week and continuing through mid-August, DC Water will temporarily close one lane overnight on Clara Barton Parkway at the Maryland-D.C. border. The closures are needed so crews can ...

Pennyfield Lock Potomac Interceptor bypass pipeline running next to C & O Canal with equipment

There is no active spill or overflow. Work to strengthen the pipe to begin soon.

Today, DC Water completed construction on a temporary bypass system as part of sewer repairs on the Potomac Interceptor near Pennyfield Lock in Potomac, Maryland. Crews turned on the pumps and successfully tested the system. With the bypass now ready, it will allow us to begin the emergency repairs inside the pipe by carrying the wastewater around the repair area.

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking
DC Water Breaks Ground on Piney Branch Tunnel, Final Phase of DC Clean Rivers Project

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Latest Blog Post
Five photos from the American Water Works Association (AWWA) ACE26 conference featuring panel discussions, technical presentations, networking, and attendees posing at the ACE26 display.
ACE26 Highlights: How DC Water Advanced the Conversation on Water
More than 80 DC Water employees joined thousands of water professionals in Washington, D.C., sharing expertise, building partnerships and advancing conversations that will help shape the future of water.
Upcoming Meeting
Date
July 23, 2026
Thursday, 9:30 AM

Upcoming Events

Jul 23
Jul 25

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.