DC Water's

News & Updates

At DC Water, we understand the importance of keeping our community informed about our services, projects, and achievements. Our news web page serves as a reliable source for the latest information on a range of topics.

Photo of person getting water saying Stability You can County on and listing the ratings from each agency
11 February, 2026

DC Water Secures 10 Consecutive Years of a “AAA” credit rating from S&P

The District of Columbia Water and Sewer Authority (DC Water) has once again secured high credit ratings from all three major rating agencies—S&P Global Ratings, Moody’s Investors Service, and Fitch Ratings—further strengthening our position as a national leader in public utilities.

Image of overflow from the collapse site being captured by the trench system and returned to the Potomac Interceptor
10 February, 2026

Pumping capacity remains a challenge, due to ongoing maintenance and operational issues. An overflow occurred late Monday night, when two pumps – clogged with non-disposable wipes – were taken out of service for cleaning and maintenance. During a period of high flow, the volume of wastewater temporarily exceeded pumping capacity resulting in the overflow.

The overflow did not enter the Potomac ...

Image of pump with a large pile of wipes next to it that clogged the pump and had to be removed
9 February, 2026

DC Water and its contractors continue working around the clock, to operate, clean and maintain bypass pumps that divert wastewater around the damaged section of the Potomac Interceptor and return flows into the system further downstream. Despite these efforts, a significant overflow occurred late Sunday.

contract for construction of the Potomac River Tunnel (PRT)
8 February, 2026

DC Water is taking emergency measures with the immediate and ongoing closure of all northbound lanes of 14th Street between L Street NW and Thomas Circle, due to the imminent risk of collapse posed by an abandoned, century-old, brick-lined sewer tunnel beneath the roadway.

contract for construction of the Potomac River Tunnel (PRT)
8 February, 2026

Work continues on the Potomac Interceptor, a section of which collapsed on January 19, along Clara Barton Parkway and the I-495 interchange and C & O Canal Historical Park causing a sanitary sewer overflow. 

A bypass system established five days after the overflow occurred continues to successfully divert wastewater around the collapse site and back into the Potomac Interceptor further downstream.  ...

Trench boxes at construction site for new pit accessing Potomac Interceptor Upstream
7 February, 2026

DC Water and its contractors continue to make progress constructing new access points to the Potomac Interceptor, one upstream of the damaged section, and an additional entry downstream to divert more wastewater flow from the pipe. These access points will allow crews to install a bulkhead, blocking flow in the pipe upstream of the collapsed area, keeping the site as dry as possible so crews can ...

Photo of giant rock and boulder removed
6 February, 2026

DC Water is releasing new findings regarding the environmental impacts following the January 19, collapse in a section of the Potomac Interceptor. Based on flow monitoring data collected before and after interim bypass pumping was activated, DC Water estimates approximately 243 million gallons of wastewater has overflowed from the collapse site.

Image of rock blockage taken by CCTV inside the Potomac Interceptor downstream of the collapse
5 February, 2026

Update on Extended Repairs, Safety Measures, and Water Quality Monitoring

Overnight CCTV inspection of the Potomac Interceptor revealed the blockage inside the collapsed sewer line is far more significant, showing a large rock dam stretching approximately 30 feet downstream of the original failure.

Three workers over the pit accessing the Potomac Interceptor for Cleaning
4 February, 2026

DC Water and its contractor are working to clean debris from a damaged section of the Potomac Interceptor, a sanitary sewer line that collapsed on January 19, along Clara Barton Parkway and the 495 interchange and the C & O Canal National Historical Park. While limited overflows occurred earlier in the week, no overflows from the site were reported today. Here is an update on the cleaning and ...

Picture of the work site where cleaning is taking place and pumps being installed
3 February, 2026

Potomac Interceptor Overflow Update
Tuesday, February 3, 2026

 Work to clean and repair the damaged section of the Potomac Interceptor continues, though progress is being slowed by large boulders and rocks inside the pipe. Meanwhile, increased flow from groundwater infiltration attributed to snowmelt, along with periodic clogging of the bypass pumps, at times, resulted in minor overflows near the ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Christening of TBM Emily with DC Water Interim General Manager Matt Brown holding bottle of tap water to christen Emily
DC Water Welcomes the Community Underground to See the Potomac River Tunnel and Christens Tunnel Boring Machine Emily

DC Water celebrated the christening of Emily today. It’s the second giant tunnel boring machine (TBM) that will help build the 5.5-mile Potomac River Tunnel. The celebration continued with Community Day. Residents and families met Emily and stepped inside the tunnel where she will soon begin digging.

Latest Blog Post
Emergency supplies arranged on a table, including bottled water, canned food, a backpack, first aid kit, flashlight, phone, medication and other essential items.
Simple Ways to Stay Prepared at Home
A few simple steps can help your household prepare for severe weather and temporary water or sewer service interruptions.
Upcoming Meeting
Date
November 12, 2026
Thursday, 9:30 AM

Upcoming Events

Nov 12
6:30 pm - 7:30 pm

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.