EMERGENCY WATER OUTAGE
Feb 27, 2026 | 03:00 PM

EMERGENCY WATER OUTAGE
Feb 27, 2026 | 02:00 PM

DC Water Mobilizing Construction Site at Canal Road NW Entrance of Georgetown University

January 12, 2026
Picture of survey worker at the top of the hill off Canal Road

Beginning on or about January 12, 2026, DC Water will begin the next phase of construction for the Potomac River Tunnel Project at the Georgetown University entrance site along the Canal Road NW. The construction site is located in the wooded area between the Georgetown University entrance and Canal Road NW.

Project Scope and Timeline

At this location, DC Water will construct a drop shaft and an underground facility to connect the existing sewer infrastructure to the Potomac River Tunnel to capture combined sewage and stormwater from overflowing into the river and divert it for treatment. 

Increased construction activity, equipment, and personnel in the area are expected for the duration of the project, which is scheduled to be completed in 2030.

Map showing the diversion facility in orange and yellow, connecting to the existing sewer system in green and the tunnel in blue.
Map showing the diversion facility in orange and yellow, connecting to the existing sewer system in green and the tunnel in blue.
  • Work hours: 7 a.m. to 7 p.m., Monday through Friday
  • Lane Closures: 10 a.m. to 4 p.m., Monday through Friday
  • Duration: Through early 2030

What to Expect: Site Mobilization and Preparation

The mobilization phase will last approximately three to four months and includes the following key activities:

  • Installing fencing, signage, and safety barriers
  • Clearing and securing the construction zone
  • Relocation of temporary crosswalk and installation of ADA ramps
  • Delivery and hauling of materials
  • Protecting nearby buildings and infrastructure
  • Installing underground utility protection

Safety Measures

The Canal Road NW entrance will remain open. To ensure public safety and maintain access:

  • The primary work zone will be in the wooded area adjacent to and above the University’s Canal Road NW entrance
  • The site will be fully enclosed and restricted to the public
  • Clear signage and physical barriers will guide all road users safely around the work zone

Map highlighting the location of the construction site.

Map: The blue line indicates the work zone, while the existing traffic pattern on West Road will remain unchanged.

Stay Informed

Learn more about the project at dcwater.com/prt or contact our outreach team at dcpotomacrivertunnel@dcwater.com for additional information and to receive advance traffic advisories and the latest project updates. 

We thank you for your patience and cooperation as we work to build a cleaner, healthier future for the District.

Project Details

The Potomac River Tunnel is part of DC Water’s Clean Rivers Project, a long-term effort to reduce pollution in our waterways. Each year, about 650 million gallons of untreated sewer overflows enter the Potomac River and, ultimately, Chesapeake Bay, releasing trash and increasing bacteria levels harmful to aquatic life. The 5.5-mile tunnel system will help capture and redirect this overflow to the Blue Plains Advanced Wastewater Treatment Plant, reducing the volume of overflow by 93% and the number of times this occurs from 74 to 4 in a typical year. 

This work is being completed in compliance with a 2005 Federal Consent Decree entered by DC Water, the District of Columbia, the US Environmental Protection Agency, and the US Department of Justice, as amended in January 2016.

Latest News

Graphic with meeting information

DC Water is inviting Maryland residents to join us tonight for a community meeting at Walt Whitman High School at 7 p.m. for an update about ongoing repair efforts on a section of the Potomac Interceptor sewer line that failed, directly impacting the surrounding Montgomery County communities. The meeting will provide an opportunity for residents to ask questions, learn about planned environmental restoration efforts, and next steps in the emergency repair and long-term rehabilitation efforts.

Placeholder DC Water Image

Crews continue work to clean the remaining debris upstream and downstream of the damaged Potomac Interceptor Pipe, with no overflows entering the Potomac River in 18 days.
A rock and debris dam that had been blocking the pipe has been removed, but some large rocks and boulders remain in other sections of the pipe and may require additional excavation to remove.

Photo of remaining rocks and debris

DC Water has made significant progress toward repairing a damaged section of the Potomac Interceptor. Crews are nearly done removing a rock and debris dam that was blocking the pipe. Several feet of rocks and debris remain to be cleared and is expected to be completed overnight. Ongoing work continues to maintain bypass pumping operations 24/7 with no overflows reported for 17 days.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.