DC Water Mobilizing Construction Site at Canal Road NW Entrance of Georgetown University

January 12, 2026
Picture of survey worker at the top of the hill off Canal Road

Beginning on or about January 12, 2026, DC Water will begin the next phase of construction for the Potomac River Tunnel Project at the Georgetown University entrance site along the Canal Road NW. The construction site is located in the wooded area between the Georgetown University entrance and Canal Road NW.

Project Scope and Timeline

At this location, DC Water will construct a drop shaft and an underground facility to connect the existing sewer infrastructure to the Potomac River Tunnel to capture combined sewage and stormwater from overflowing into the river and divert it for treatment. 

Increased construction activity, equipment, and personnel in the area are expected for the duration of the project, which is scheduled to be completed in 2030.

Map showing the diversion facility in orange and yellow, connecting to the existing sewer system in green and the tunnel in blue.
Map showing the diversion facility in orange and yellow, connecting to the existing sewer system in green and the tunnel in blue.
  • Work hours: 7 a.m. to 7 p.m., Monday through Friday
  • Lane Closures: 10 a.m. to 4 p.m., Monday through Friday
  • Duration: Through early 2030

What to Expect: Site Mobilization and Preparation

The mobilization phase will last approximately three to four months and includes the following key activities:

  • Installing fencing, signage, and safety barriers
  • Clearing and securing the construction zone
  • Relocation of temporary crosswalk and installation of ADA ramps
  • Delivery and hauling of materials
  • Protecting nearby buildings and infrastructure
  • Installing underground utility protection

Safety Measures

The Canal Road NW entrance will remain open. To ensure public safety and maintain access:

  • The primary work zone will be in the wooded area adjacent to and above the University’s Canal Road NW entrance
  • The site will be fully enclosed and restricted to the public
  • Clear signage and physical barriers will guide all road users safely around the work zone

Map highlighting the location of the construction site.

Map: The blue line indicates the work zone, while the existing traffic pattern on West Road will remain unchanged.

Stay Informed

Learn more about the project at dcwater.com/prt or contact our outreach team at dcpotomacrivertunnel@dcwater.com for additional information and to receive advance traffic advisories and the latest project updates. 

We thank you for your patience and cooperation as we work to build a cleaner, healthier future for the District.

Project Details

The Potomac River Tunnel is part of DC Water’s Clean Rivers Project, a long-term effort to reduce pollution in our waterways. Each year, about 650 million gallons of untreated sewer overflows enter the Potomac River and, ultimately, Chesapeake Bay, releasing trash and increasing bacteria levels harmful to aquatic life. The 5.5-mile tunnel system will help capture and redirect this overflow to the Blue Plains Advanced Wastewater Treatment Plant, reducing the volume of overflow by 93% and the number of times this occurs from 74 to 4 in a typical year. 

This work is being completed in compliance with a 2005 Federal Consent Decree entered by DC Water, the District of Columbia, the US Environmental Protection Agency, and the US Department of Justice, as amended in January 2016.

Latest News

Map of lane closure on Clara Barton Parkway at Maryland-DC Border

Drivers should expect delays on Clara Barton Parkway at the Maryland – DC border on Saturday, Sept 26. One lane will be closed from 7 a.m. to 3 p.m. while DC Water makes repairs as part of ongoing ...

Christening of TBM Emily with DC Water Interim General Manager Matt Brown holding bottle of tap water to christen Emily

DC Water celebrated the christening of Emily today. It’s the second giant tunnel boring machine (TBM) that will help build the 5.5-mile Potomac River Tunnel. The celebration continued with Community Day. Residents and families met Emily and stepped inside the tunnel where she will soon begin digging.

Map: Temporary closure of the southbound curb lane on Rock Creek and Potomac Parkway NW

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT

Drivers should expect a temporary southbound lane closure on Rock Creek and Potomac Parkway NW between F St and Virginia Ave on Saturday, September 19, and Sunday, September 20, 2026. The closure will be in place from 7 a.m. to 7 p.m. each day, weather permitting.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Christening of TBM Emily with DC Water Interim General Manager Matt Brown holding bottle of tap water to christen Emily
DC Water Welcomes the Community Underground to See the Potomac River Tunnel and Christens Tunnel Boring Machine Emily

DC Water celebrated the christening of Emily today. It’s the second giant tunnel boring machine (TBM) that will help build the 5.5-mile Potomac River Tunnel. The celebration continued with Community Day. Residents and families met Emily and stepped inside the tunnel where she will soon begin digging.

Latest Blog Post
Emergency supplies arranged on a table, including bottled water, canned food, a backpack, first aid kit, flashlight, phone, medication and other essential items.
Simple Ways to Stay Prepared at Home
A few simple steps can help your household prepare for severe weather and temporary water or sewer service interruptions.
Upcoming Meeting
Date
October 8, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.