Update: Work Underway to Drain Remaining Wastewater from Damaged Sewer Line to Begin Excavation and Repair

January 25, 2026
Photo of the Potomac Interceptor Bypass where overflow reentering the sewer line

DC Water is nearing full containment on a sanitary sewer overflow, nearly a week after a section of the Potomac Interceptor – a major sewer line – collapsed along Clara Barton Parkway and the C & O Canal National Historical Park in Montgomery County, MD. In the first full day of operation since a temporary bypass system was activated, the flow of wastewater downstream where it re-enters the sewer line has increased by about 40 million gallons per day.

This indicates significant progress towards containment. Some of the wastewater continues to escape around the break site, which is expected. The damaged pipe section sits at a lower elevation than the pumps and still contains residual wastewater that requires time to drain. Additional pumps are being brought in to accelerate removing the remaining wastewater and achieve full containment. Once conditions allow, crews will then be able to isolate the damaged section, expose the pipe, and begin repairs.

The bypass system began operating early yesterday evening, when six large pumps were turned on to convey wastewater into a controlled section of the C&O Canal, routing it around the break and back into the sewer system further downstream. Overnight monitoring confirmed the pumps are operating as intended with increased flow successfully returning to DC Water’s Blue Plains Advanced Wastewater Treatment Plant.

Now that the bypass is operating, and site conditions stabilized, DC Water crews will begin focusing on next steps: excavation, inspection, and development of a long‑term repair plan. This work involves assessing the extents of the damage, including inside the affected pipe, mobilizing equipment, stabilizing surrounding ground conditions, installing shoring supports, and removing debris from the collapse that is currently blocking the line.

Pictures of bypass flow utilizing contained area of C & O Canal

The failure occurred on January 19, 2026, in a large, 72-inch diameter section of the Potomac Interceptor. The break caused wastewater to spill into a creek bed leading to the Potomac River. In the days that followed, crews worked around the clock to build the temporary bypass system—clearing access, installing pipes, coordinating with the National Park Service to adjust canal structures, and setting up the pumps needed to redirect the flow. 

Drinking water remains completely safe and unaffected. The drinking water and wastewater systems are separate, and the incident occurred downstream of the Washington Aqueduct intakes for drinking water.

After the overflow is fully contained and the pipe repaired, work will begin to assess the areas where the overflow occurred. This will be done in conjunction with the National Park Service, Maryland Department of the Environment, and other partner agencies to survey factors such as erosion, debris removal, cleaning, and assessing the need for remediation.

DC Water reminds the public to avoid any posted areas along the canal or river. If someone accidentally comes into contact with wastewater, they should immediately wash with soap and clean water, disinfect any items that were splashed or exposed, avoid consuming food or drinks that may have been contaminated, and seek medical attention if they feel sick.

Anyone with questions or in need of support may contact DC Water’s Customer Care team at (202) 354-3600 (Monday–Friday, 8 a.m. to 5 p.m.) DC Water’s 24‑Hour Command Center at (202) 612‑3400.

 

Latest News

Photo of manhole entrance withe completed geopolymer

Second of four high-priority repair projects is now complete

DC Water has completed the second of four critical repair projects on the Potomac Interceptor Sewer Line. Crews finished strengthening a 490-foot section of the pipe at Broad Run in Loudoun County today.

Image of Clara Barton Parkway showing lane closure

Beginning this week and continuing through the end of September, DC Water will temporarily close one lane overnight on Clara Barton Parkway at the Maryland-D.C. border. The closures are necessary to allow crews to safely begin geopolymer work, a concrete-like material, applied inside the sewer line as part of emergency repairs to a section of the Potomac Interceptor.

Last gantry at the bottom of the shaft where crews connect it

Final Gantry Completes Mobile Support Train Behind Mary Stretching More Than 700 Feet

DC Water’s tunnel boring machine Mary may be the muscle behind the Potomac River Tunnel Project, but the gantries that trail behind her form the heart, brains, and guts of the operation. Now crews have lowered and connected the final gantry section, giving Mary the tools and equipment she needs to continue tunneling north.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Last gantry at the bottom of the shaft where crews connect it
Now Fully Assembled, It’s Full Speed Ahead for the tunnel boring machine Mary and the Potomac River Tunnel

Final Gantry Completes Mobile Support Train Behind Mary Stretching More Than 700 Feet

DC Water’s tunnel boring machine Mary may be the muscle behind the Potomac River Tunnel Project, but the gantries that trail behind her form the heart, brains, and guts of the operation. Now crews have lowered and connected the final gantry section, giving Mary the tools and equipment she needs to continue tunneling north.

Latest Blog Post
Emergency supplies arranged on a table, including bottled water, canned food, a backpack, first aid kit, flashlight, phone, medication and other essential items.
Simple Ways to Stay Prepared at Home
A few simple steps can help your household prepare for severe weather and temporary water or sewer service interruptions.
Upcoming Meeting

Upcoming Events

Sep 6
Sep 19

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.