EMERGENCY WATER OUTAGE
Jul 09, 2026 | 09:26 AM

EMERGENCY WATER OUTAGE
Jul 09, 2026 | 07:16 AM

Work Underway on Final Steps to Return Flow to the Potomac Interceptor, Complete Emergency Repair

March 09, 2026
Workers putting down rye and matting for soil stabilization
  • More than one month after the last overflow into the Potomac River, DC Water is preparing to return flow in the coming days to the Potomac Interceptor and meet the mid-March target to complete the emergency repair on the damaged pipe section.
  • Crews have completed work to reinforce the pipe sections upstream and downstream of the collapse site using geopolymer to strengthen the pipe. The work included 320 linear feet of the upstream section, 300 linear feet of the downstream section, and drop sections where the elevation changes. Geopolymer, is strong like concrete but more resistant to sewer gases and when applied strengthens the pipe and provides structural integrity.
  • Work is now underway to waterproof the excavation sites where the pipe is open. This is necessary to prepare the sites to restore flow to the interceptor. A CCTV camera inspection will take place later this week to verify the pipe is ready to restore flow.
  • Returning the flow to the Potomac Interceptor is a phased process, slowly lifting the bulkhead gate blocking the pipe to gradually reintroduce flow. Crews will monitor the pipe sections to ensure there are no issues. As more flow is introduced, the pumps will be systematically taken out of service in careful coordination until all flow is restored and the bypass pumping system deactivated.
  • The remaining wastewater in the C & O Canal will flow downstream back into the Potomac Interceptor, and the residual wastewater that remains in the canal will be pumped out.
  • When the emergency repair is completed, the full flow and function of the Potomac Interceptor will be restored with what is known as “open channel flow.” Wastewater will continue to flow through the open pipe sections contained within the trenches while the long-term rehabilitation work takes place.
  • DC Water is accelerating rehabilitation for this section of the Potomac Interceptor which was part of a planned rehabilitation project. Crews will slip line more than 2700 linear feet of the sewer line, using the pipe that is already open to insert new pipe segments into the existing pipe. The slip lining, expected to take 9-10 months will restore this section of the sewer line to like new condition.
  • Environmental rehabilitation work continues in Area 1, adjacent to the collapse site and the drainage channel along Clara Barton Parkway. Crews are clearing vegetation, excavating contaminated soil, mucking the area, and implementing erosion control measures and soil stabilization as part of the initial clean-up.
  • Area 1 is divided into two sections – east and west. On the western section, the initial phase of rehabilitation work is now more than 30% complete.

Water Quality Sampling Results

Fluctuations in water quality are influenced by factors such as rain, heat, or other weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways. Given these variables, measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs.

As of March 4, two new sampling locations have been added at Sycamore Island and Lock 6. Sample results from February 23 - present. Past results may be found here.

Graphic of water quality sampling

For more information, including the latest news and updates, and to provide feedback on the Environmental Rehabilitation Plan go to our dedicated page for the Potomac Interceptor Repairs.

Latest News

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Photo of the drop shaft looking from above down into the bottom

Starting the week of July 13, 2026, people who live, work or travel near the Canal Road NW entrance to Georgetown University may hear controlled blasting. This work is part of our Potomac River Tunnel Project.

When blasting happens, neighbors may hear a brief noise or feel light shaking. Drivers, cyclists, and pedestrians on Canal Road NW may also be stopped for a few minutes while we safely complete each blast.

Photo of Pipe Fusing at Cabin John PI Rehabilitation Site

DC Water will continue daily Potomac River water quality testing through July 31. The testing is part of ongoing monitoring after the January 19 collapse of a section of the Potomac Interceptor, a ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking
DC Water Breaks Ground on Piney Branch Tunnel, Final Phase of DC Clean Rivers Project

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Latest Blog Post
Five photos from the American Water Works Association (AWWA) ACE26 conference featuring panel discussions, technical presentations, networking, and attendees posing at the ACE26 display.
ACE26 Highlights: How DC Water Advanced the Conversation on Water
More than 80 DC Water employees joined thousands of water professionals in Washington, D.C., sharing expertise, building partnerships and advancing conversations that will help shape the future of water.
Upcoming Meeting
Date
July 13, 2026
Monday, 2:00 PM

Upcoming Events

Jul 23
Jul 25

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.