Work Nearly Complete to Reinforce Downstream Section of Damaged Potomac Interceptor

March 08, 2026
Tree and debris removal for environmental rehabilitation
  • Today marks one month since the last overflow reached the Potomac River as the emergency repair on the damaged Potomac Interceptor nears completion. 
  • Crews today finished applying geopolymer on 300 linear feet of the pipe downstream of the collapse site. Work is also underway to apply geopolymer to a drop section of the pipe where the line changes elevation. 
  • The concrete-like material will strengthen and restore the structural integrity of the pipe. Completion of the downstream section is one of the final steps to restore flow to the interceptor and finish the emergency repair. 
  • Environmental rehabilitation work continues with crews focused on erosion and sediment control, site clean-up, and clearing trees and brush. 
  • Work also continues on mucking and waste removal from the drainage channel along Clara Barton Parkway. 

Water Quality Sampling Results

Fluctuations in water quality are influenced by factors such as weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways. Given these variables, measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs.

As of March 4, two new sampling locations have been added at Sycamore Island and Lock 6. Sample results from February 23 - present. Past results may be found here.

For quality assurance purposes, lab results are unavailable on weekends and will be posted on the following Monday, excluding holidays.

graphic of water qualilty results

For more information, including the latest news and updates, and to provide feedback on the Environmental Rehabilitation Plan, go to our dedicated page for the Potomac Interceptor Repairs

Latest News

Section of Potomac River in Cabin John, MD showing river and trees

Testing will continue through September 10 at six Maryland locations closest to January sewer collapse

DC Water is moving from daily Potomac River water quality testing to testing twice a week. The change is part of our continued response to the January Potomac Interceptor sewer collapse. Daily testing continued past the original July 31 end date and today will be the last day DC Water will test at the 10 current locations.

Map: Temporary southbound lane closure on Rock Creek and Potomac Parkway NW.

Starting on or about Aug. 7, 2026, weather permitting, drivers can expect a temporary lane closure southbound on Rock Creek and Potomac Parkway NW near the intersection of Virginia Avenue NW and F ...

Photo of inside Potomac Interceptor at Dulles showing newly lined tunnel

First of four emergency repairs on Potomac Interceptor finished

DC Water has finished the first of four emergency repair projects on the Potomac Interceptor sewer line. Crews completed work today to strengthen a 600-foot section of pipe at Dulles International Airport.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Latest Blog Post
Plastic bottles, cups and other floating debris on the surface of the Anacostia River before the Anacostia River Tunnel began operating.
Cleaner Waterways Start With Everyday Choices
Protecting our waterways starts with everyday actions and continues through critical infrastructure designed to keep pollution out of our rivers.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.