DC Water Completes Construction to Rehabilitate Sewer Line Along Clara Barton Parkway

Area of repair

DC Water has completed an eight-month construction project to rehabilitate a major sewer line that runs along Clara Barton Parkway near I-495. The work, which started on September 8th, focuses on restoring an 800-foot segment of the sanitary sewer system known as the Potomac Interceptor.

During construction, expect lane restrictions and reduced speeds eastbound on Clara Barton Parkway starting west of the I-495 ramp to just past the underpass. Access to the inner and outer loop of the Beltway/I-495 will remain available, however, drivers inbound on the parkway may experience some delays.

The Potomac Interceptor is a vital piece of infrastructure, transporting 60 million gallons of wastewater daily from Virginia, Maryland, and the District to the Potomac Pumping Station and the Blue Plains Advanced Wastewater Treatment Facility.

DC Water and its contractors will use a method called sliplining to repair the pipe by inserting a new, smaller diameter pipe into the existing larger line. This method reduces the need for major excavation, limits traffic impacts, and extends the life of the existing infrastructure.

This work is expected to continue through April and is part of an effort to rehabilitate the 78-inch sewer line before its condition deteriorates further. Completing the project now will help streamline construction activities and reduce future disruptions. A larger upgrade on the 54-mile Potomac Interceptor is planned for later this year.


Project Details


What
Potomac Interceptor Sanitary Sewer System Rehabilitation

Date
September 8th, and continuing through April 2026

Hours
9:30 a.m. to 2:00 p.m.

Location
Clara Barton Parkway inbound prior to the I-495 ramp and just past the overpass

Impact
One lane closed and speed reduced to 30 mph through the construction zone


For more information


Click here for Project Factsheet.

Project email: potomacinterceptor@dcwater.com

Project Website: dcwater.com/potomacinterceptor

DC Water 24-hour Emergency: 202-612-3400

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Last gantry at the bottom of the shaft where crews connect it
Now Fully Assembled, It’s Full Speed Ahead for the tunnel boring machine Mary and the Potomac River Tunnel

Final Gantry Completes Mobile Support Train Behind Mary Stretching More Than 700 Feet

DC Water’s tunnel boring machine Mary may be the muscle behind the Potomac River Tunnel Project, but the gantries that trail behind her form the heart, brains, and guts of the operation. Now crews have lowered and connected the final gantry section, giving Mary the tools and equipment she needs to continue tunneling north.

Latest Blog Post
Emergency supplies arranged on a table, including bottled water, canned food, a backpack, first aid kit, flashlight, phone, medication and other essential items.
Simple Ways to Stay Prepared at Home
A few simple steps can help your household prepare for severe weather and temporary water or sewer service interruptions.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.