Now Fully Assembled, It’s Full Speed Ahead for the tunnel boring machine Mary and the Potomac River Tunnel

August 27, 2026
Last gantry at the bottom of the shaft where crews connect it
Final Gantry Completes Mobile Support Train Behind Mary Stretching More Than 700 Feet

DC Water’s tunnel boring machine Mary may be the muscle behind the Potomac River Tunnel Project, but the gantries that trail behind her form the heart, brains, and guts of the operation. Now crews have lowered and connected the final gantry section, giving Mary the tools and equipment she needs to continue tunneling north.

This is a major turning point for the project because Mary can now move forward at full capacity. The cutterhead at the front of the machine does the digging, but it cannot operate for long without the gantries behind it.

The gantries provide the power, hydraulic, and logistics systems that push Mary forward. They also carry dirt and rock out of the tunnel, install the concrete tunnel liner, and provide ventilation and space for crews. With the gantries fully attached, Mary stretches 706 feet from end to end. That is more than twice the length of two football fields and nearly as long as the Golden Gate Bridge is tall.

“With Mary and the gantries assembled, we now have a moving factory underground to build one of the District’s largest and most important infrastructure projects,” said DC Water Interim General Manager Matthew T. Brown. “This feat shows the scale of the work and the important role it will play in improving water quality and protecting the Potomac River for the region.”

Mary is so large crews could not lower her and the gantries into the shaft in one piece. Instead, as Mary moved underground a crane lowered each 30-ton gantry into the shaft. Another machine then pulled each gantry into the tunnel, where crews connected it.

With the final gantry attached, Mary will excavate about 350 feet farther into the tunnel. Crews will then get the machine ready for the next stage of digging when Mary will shift from softer soil near the river to hard bedrock for the rest of her journey.

During this shift, Mary will stay in place inside the tunnel. The changeover will take more than two months. After that, the machine will keep moving north to dig the rest of the 2.4-mile tunnel from West Potomac Park to Georgetown University.

The Potomac River Tunnel is part of DC Water’s Clean Rivers Program, a long-term effort to reduce pollution in the Potomac River and Chesapeake Bay. Mary’s sister machine, Emily, will dig 3.1 miles south toward Joint Base Anacostia-Bolling. When the full 5.5-mile tunnel system is complete, it will reduce stormwater and sewage overflows to the Potomac River by 93 percent. It will also cut the number of overflow events from about 74 to four in a typical year.

Learn more about the Potomac River Tunnel Project at dcwater.com/prt.

Mary's last gantry hanging from a crane as it is being lowered into the shaft

Latest News

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m. - 1 p.m. while tree removal equipment is delivered to DC Water’s Park Road construction site ...

Image of DC Water mascot Wendy with a child and the Lead Free DC Logo highlighting the Ward Wide Tour

First Stop Nov 19: Enjoy Free Giveaways and Live Music While Learning about LFDC

DC Water’s Lead Free DC (LFDC) Program is going on the road with a Ward Wide Tour. We’ll be spreading the word about replacing lead service lines with fun, festive community pop-up events making stops in all eight wards.

Workers inside the pit pushing in the new pipe section at Pennyfield Lock
Update

Work on the Potomac Interceptor at Pennyfield Lock is moving faster than expected. Crews were able to make significant progess, finishing preparationg work to begin the permanent repair this ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains
TRAFFIC ADVISORY: Temporary Road Closure for Equipment Delivery May cause delays on Park Road NW

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m.

Latest Blog Post
Before-and-after comparison of a 12-inch blowoff connected to a 36-inch water main near Massachusetts Avenue and Macomb Street NW. The images show the inside of the structure before the repair, repair work around the pipe, and the interior after the repair was completed.
One Repair, Millions of Gallons Saved
How Teamwork Helped DC Water Stop Hidden Water Loss
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.