At DC Water, we understand the importance of keeping our community informed about our services, projects, and achievements. Our news web page serves as a reliable source for the latest information on a range of topics.

photo of worker going into downstream cleaning pit
10 March, 2026
  • Work is progressing to meet the mid-March target to return the flow to the Potomac Interceptor, as we reach 31 days with no overflows reaching the Potomac River.
  • The geopolymer applied to the upstream and downstream sections of the pipe has cured to reinforce the pipe and ensure structural integrity. This completes the repair on the pipe, which is now ready for the flow to return.
  • Additional work is ...
Workers putting down rye and matting for soil stabilization
9 March, 2026
  • More than one month after the last overflow into the Potomac River, DC Water is preparing to return flow in the coming days to the Potomac Interceptor and meet the mid-March target to complete the emergency repair on the damaged pipe section.
  • Crews have completed work to reinforce the pipe sections upstream and downstream of the collapse site using geopolymer to strengthen the pipe. The work ...
Tree and debris removal for environmental rehabilitation
8 March, 2026

Work is nearly complete on the downstream section of the Potomac Interceptor to reinforce the pipeline with geopolymer. The concrete-like material will strengthen and restore the structural integrity of the pipe. Completion of the geopolymer lining downstream is one of the final steps to restore flow to the interceptor and finish the emergency repair.

This comes one month since the last overflow ...

geopolymer downstream
7 March, 2026

As emergency repairs continue, today marks 27 days, nearly one month, with no overflow reaching the Potomac River.

Crews are making significant progress to reinforce the downstream section of pipe from the collapse site and completed 240 linear feet of geopolymer overnight. Crews are working to apply another layer of geopolymer today. The material is similar in strength to concrete and when ...

photo inside tunnel with geopolymer
6 March, 2026

Reinforcement of the upstream section of the Potomac Interceptor has been completed, marking the halfway point in emergency repairs following the January 19 sewer line collapse. Crews continue to advance repairs on schedule, with full project completion expected by mid-March.

John Cassidy, Matt Brown, David L. Gadis, and Moussa Wone giving technical briefing
5 March, 2026

DC Water today is releasing a comprehensive assessment detailing the condition of the Potomac Interceptor and our emergency response to the January 19 sanitary sewer line failure. This report provides clarity for customers, stakeholders, and community members about the steps taken and findings from the incident, including prior inspections of the pipe’s condition.

After the collapse, DC Water’s ...

Geopolymer lining inside the Potomac Interceptor
4 March, 2026

DC Water and its contractor have taken significant steps toward repairing the Potomac Interceptor. The repair process currently underway involves reinforcing the damaged section of the pipe using geopolymer. This material is known for its concrete-like strength and durability.

Protective Encasement for workers to apply the geopolymer lining
3 March, 2026

Repair efforts continue as we reach 23 days in which no overflows have entered the Potomac River. Crews finished pressure washing the pipe upstream of the damaged section of the Potomac Interceptor and preparations are underway for the application of the geopolymer lining to reinforce and strengthen the pipe.

Workers clearing brush and debris from drainage channel
2 March, 2026

National Park Service Issues Special Use Permit to Move Forward with Restoration Plan

DC Water has begun the rehabilitation and environmental restoration to address areas affected by the sewer overflow from a section of the Potomac Interceptor that collapsed January 19. Contaminated material is being hauled away and work is underway to clear trees, brush, and contaminated debris in and around ...

contract for construction of the Potomac River Tunnel (PRT)
1 March, 2026

Potomac Interceptor Repairs Update 
March 1, 2026

  • Today marks a milestone, as we reach the three-week point with no overflows entering the Potomac River. The last release to reach the river occurred on February 8.
  • On February 28, National Park Service (NPS) issued a Special Use Permit for the repair, rehabilitation, and environmental restoration of the Potomac Interceptor and the C&O Canal National ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains
TRAFFIC ADVISORY: Temporary Road Closure for Equipment Delivery May cause delays on Park Road NW

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m.

Latest Blog Post
Before-and-after comparison of a 12-inch blowoff connected to a 36-inch water main near Massachusetts Avenue and Macomb Street NW. The images show the inside of the structure before the repair, repair work around the pipe, and the interior after the repair was completed.
One Repair, Millions of Gallons Saved
How Teamwork Helped DC Water Stop Hidden Water Loss
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.