Emergency Repair on Potomac Interceptor Reaches Halfway Mark — Upstream Section Reinforcement Complete

March 06, 2026
photo inside tunnel with geopolymer

Reinforcement of the upstream section of the Potomac Interceptor has been completed, marking the halfway point in emergency repairs following the January 19 sewer line collapse. Crews continue to advance repairs on schedule, with full project completion expected by mid-March.

The upstream section of the damaged Potomac Interceptor was reinforced using geopolymer to restore its structural integrity. Crews lined approximately 320 linear feet of the pipe with geopolymer, which is as tough as concrete and is resistant to sewer gases. Teams are now preparing to apply the same advanced geopolymer technology to the downstream portion. This next phase will further secure the pipe and complete the emergency repair.

Once the downstream reinforcement is finished, a final CCTV inspection will be completed inside the pipe. Crews will then waterproof the existing containment around the exposed pipe sections, and DC Water will begin restoring flow to the Potomac Interceptor. This involves carefully removing the bulkhead gate that had been blocking the flow in the pipe, shutting down the bypass pumping system, and reintroducing wastewater service through the repaired pipe.

The remaining wastewater in the C & O Canal, which was temporarily used to divert flow, will drain into the Potomac Interceptor downstream and any residual wastewater will be pumped out of the canal. Work will then begin on the clean-up and rehabilitation of the canal and historic lock structures.

Environmental rehabilitation work continues in parallel with pipe repairs. The Phase 1 clean-up of Area 1, adjacent to the collapse site and the drainage channel, is now about 15% complete, including soil scraping, excavation, and installation of temporary erosion control matting. Crews are actively removing contaminated soil and vegetation, while coordination continues with the US Army Corps of Engineers, Environmental Protection Agency, National Park Service, and Maryland Department of the Environment to manage the remaining areas including the river channel and shoreline.

A section of the Potomac Interceptor, a 54-mile sanitary sewer system, collapsed January 19, along Clara Barton Parkway and C & O Canal National Historical Park near I-495. It’s now believed the large boulders and rocks used as backfill during initial construction in the 1960’s amplified the scale and magnitude of the event by blocking almost all the flow in the pipe when it failed.

This week, a comprehensive technical assessment examining the Potomac Interceptor’s condition and the events leading to the collapse, found no evidence of imminent structural failure. The review included reports over seven years, including multiple internal inspections.  All data—video reviews, structural ratings, and engineering assessments—indicated that emergency action was not necessary prior to the incident.

DC Water remains committed to keeping the public, stakeholders, and partners informed as work progresses. Updates will continue to be shared as we move toward full repair and environmental recovery. DC Water is also giving residents and community members with an opportunity to provide feedback on the Environmental Rehabilitation Plan. You will find a link to contact us, as well as  the latest information on our dedicated webpage for the Potomac Interceptor Repair.

Water Quality Sampling Results

Fluctuations in water quality are influenced by factors such as weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways. Given these variables, measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs.

As of March 4, two new sampling locations have been added at Sycamore Island and Lock 6. Sample results from February 23 - present. Past results may be found here.

 

graphic of water quality results

Latest News

image of clara barton parkway with lane closure marked in red

Beginning this week and continuing through mid-August, DC Water will temporarily close one lane overnight on Clara Barton Parkway at the Maryland-D.C. border. The closures are needed so crews can ...

Pennyfield Lock Potomac Interceptor bypass pipeline running next to C & O Canal with equipment

There is no active spill or overflow. Work to strengthen the pipe to begin soon.

Today, DC Water completed construction on a temporary bypass system as part of sewer repairs on the Potomac Interceptor near Pennyfield Lock in Potomac, Maryland. Crews turned on the pumps and successfully tested the system. With the bypass now ready, it will allow us to begin the emergency repairs inside the pipe by carrying the wastewater around the repair area.

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking
DC Water Breaks Ground on Piney Branch Tunnel, Final Phase of DC Clean Rivers Project

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Latest Blog Post
Five photos from the American Water Works Association (AWWA) ACE26 conference featuring panel discussions, technical presentations, networking, and attendees posing at the ACE26 display.
ACE26 Highlights: How DC Water Advanced the Conversation on Water
More than 80 DC Water employees joined thousands of water professionals in Washington, D.C., sharing expertise, building partnerships and advancing conversations that will help shape the future of water.
Upcoming Meeting
Date
July 23, 2026
Thursday, 9:30 AM

Upcoming Events

Jul 23
Jul 25

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.