Work To Return Flow to Potomac Interceptor by Mid-March on Target

March 10, 2026
photo of worker going into downstream cleaning pit
  • Work is progressing to meet the mid-March target to return the flow to the Potomac Interceptor, as we reach 31 days with no overflows reaching the Potomac River.
  • The geopolymer applied to the upstream and downstream sections of the pipe has cured to reinforce the pipe and ensure structural integrity. This completes the repair on the pipe, which is now ready for the flow to return.
  • Additional work is necessary to seal the excavation sites. Crews are working around the clock to apply geopolymer to the trench boxes surrounding the open pipe sections, which will provide a waterproof seal to create an open flow channel once the flow returns.
  • Using the open trenches where the crown of the pipe has been removed is more efficient for the next phase of rehabilitation work. The existing pipe openings will be used to insert new pipe sections – called slip lining - as part of the previously planned rehabilitation of the interceptor. The work is being accelerated on more than 2700 linear feet of the interceptor including this section and when complete will restore the pipe to like-new condition.
  • The bypass pumping operation continues to divert flow around the collapse site and back into the Potomac Interceptor and will be carefully deactivated as the full flow returns to the pipe.
  • A CCTV camera inspection is expected to be performed late Wednesday to confirm the pipe’s readiness to return the wastewater flow.
  • Environmental rehabilitation work continues in Area 1, the area adjacent to the collapse site and drainage channel. DC Water and its contractor are working in the west section, with the Environmental Protection Agency working on the east section.
  • The US Army Corp of Engineers is assisting DC Water with rehabilitation work in Area 2, around the Rock Run Culvert and stream.
  • Work on Area 3, along the Potomac River and shoreline, has not yet begun and needs the river flow to lower for the area to be assessed.

Water Quality Sampling Results

Fluctuations in water quality are influenced by factors such as rain, heat, or other weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways. Given these variables, measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs.

As of March 4, two new sampling locations have been added at Sycamore Island and Lock 6. Sample results from March 2 - present. Past results may be found here.

graphic of water quality sampling results

For more information, including the latest news and updates, and to provide feedback on the Environmental Rehabilitation Plan go to our dedicated page for the Potomac Interceptor Repairs.

Latest News

Photo of soil removal and excavation

DC Water and its contractor have removed all the soil down to the clay liner between locks 12 and 13, marking 50% completion of the canal clean-up. Soil removal between Locks 13 and 14 was completed earlier this month. Meanwhile, clean-up efforts continue between locks 10 and 12, with sludge removal complete and soil removal now underway.

View of Mary at bottom of shaft inside tunnel shown from above

First turn of cutterhead signals the start of excavation for the Potomac River Tunnel Project

In a defining moment for one of the District’s largest infrastructure investments, DC Water has marked its next major milestone in the Potomac River Tunnel Project. The first tunnel boring machine, Mary, has launched her northbound journey breaking through the soil to signal the start of excavation.

With the first turn of Mary’s drill-like cutterhead underground, the machine pushed forward to begin tunneling, representing the transition from years of planning and preparation to active tunnel construction on the $819 million project.

Photo of the vegetation growing back in the culvert area
  • DC Water has completed soil removal, utilizing excavators and manual digging, to expose the clay lining for the C & O Canal between locks 13 and 14. This is the final step in the clean-up process ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

View of Mary at bottom of shaft inside tunnel shown from above
DC Water Launches Tunnel Boring Machine Mary, Marking Important Step for Potomac River Tunnel Project

First turn of cutterhead signals the start of excavation for the Potomac River Tunnel Project

In a defining moment for one of the District’s largest infrastructure investments, DC Water has marked its next major milestone in the Potomac River Tunnel Project. The first tunnel boring machine, Mary, has launched her northbound journey breaking through the soil to signal the start of excavation.

With the first turn of Mary’s drill-like cutterhead underground, the machine pushed forward to begin tunneling, representing the transition from years of planning and preparation to active tunnel construction on the $819 million project.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
April 15, 2026
Wednesday, 9:30 AM

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.