Work To Return Flow to Potomac Interceptor by Mid-March on Target

March 10, 2026
photo of worker going into downstream cleaning pit
  • Work is progressing to meet the mid-March target to return the flow to the Potomac Interceptor, as we reach 31 days with no overflows reaching the Potomac River.
  • The geopolymer applied to the upstream and downstream sections of the pipe has cured to reinforce the pipe and ensure structural integrity. This completes the repair on the pipe, which is now ready for the flow to return.
  • Additional work is necessary to seal the excavation sites. Crews are working around the clock to apply geopolymer to the trench boxes surrounding the open pipe sections, which will provide a waterproof seal to create an open flow channel once the flow returns.
  • Using the open trenches where the crown of the pipe has been removed is more efficient for the next phase of rehabilitation work. The existing pipe openings will be used to insert new pipe sections – called slip lining - as part of the previously planned rehabilitation of the interceptor. The work is being accelerated on more than 2700 linear feet of the interceptor including this section and when complete will restore the pipe to like-new condition.
  • The bypass pumping operation continues to divert flow around the collapse site and back into the Potomac Interceptor and will be carefully deactivated as the full flow returns to the pipe.
  • A CCTV camera inspection is expected to be performed late Wednesday to confirm the pipe’s readiness to return the wastewater flow.
  • Environmental rehabilitation work continues in Area 1, the area adjacent to the collapse site and drainage channel. DC Water and its contractor are working in the west section, with the Environmental Protection Agency working on the east section.
  • The US Army Corp of Engineers is assisting DC Water with rehabilitation work in Area 2, around the Rock Run Culvert and stream.
  • Work on Area 3, along the Potomac River and shoreline, has not yet begun and needs the river flow to lower for the area to be assessed.

Water Quality Sampling Results

Fluctuations in water quality are influenced by factors such as rain, heat, or other weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways. Given these variables, measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs.

As of March 4, two new sampling locations have been added at Sycamore Island and Lock 6. Sample results from March 2 - present. Past results may be found here.

graphic of water quality sampling results

For more information, including the latest news and updates, and to provide feedback on the Environmental Rehabilitation Plan go to our dedicated page for the Potomac Interceptor Repairs.

Latest News

A section of the canal where the soil has been removed
  • Crews are close to completing the removal of remaining soil from Locks 11 to 13 in the section of the C&O Canal that was used as an emergency bypass after the collapse of the Potomac Interceptor sewer ...
Excavation site outside the I-495 Beltway showing section of the PI

Crews completed cleaning on Lock 11 of the C & O Canal as prescribed by the National Park Service, with soil removal also nearing completion within the lock area. Tree removal is also underway, after DC Water received the permits to move forward as part of the site preparations for the long-term accelerated rehabilitation of more than 2700 linear feet of the Potomac Interceptor sewer line that had been previously planned.

Photo of long stretch of C & O Canal with soil removed

DC Water has excavated a section of the Potomac Interceptor along Clara Barton Parkway, outside the I-495 Beltway as part of the accelerated rehabilitation of more than 2700 linear feet of the interceptor that was previously planned. As part of the long-term rehabilitation project, crews are beginning to remove trees which is necessary to construct a bypass chamber that will divert wastewater around sections of the pipe while they are being rehabilitated.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

The shields for the tunnel boring machine Mary being lowered by cranes into the shaft
DC Water Earns Prominent Award for Sustainable Finance Leadership through Green Bonds

Recognition highlights DC Water’s commitment to environmental stewardship during Earth Month

DC Water has been honored with the “Green Bond of the Year – US Muni Bond” Award by Environmental Finance, a leading industry publication. This achievement celebrates DC Water’s leadership in sustainability and its dedication to responsible municipal financing.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
May 5, 2026
Tuesday, 1:00 PM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.