UPDATE: Potomac Interceptor Overflow Repair - February 8, 2026

February 08, 2026

Work continues on the Potomac Interceptor, a section of which collapsed on January 19, along Clara Barton Parkway and the I-495 interchange and C & O Canal Historical Park causing a sanitary sewer overflow. 

A bypass system established five days after the overflow occurred continues to successfully divert wastewater around the collapse site and back into the Potomac Interceptor further downstream. 

However, late this evening a limited overflow occurred at the site but wastewater did not reach the Potomac River. An estimated 3600 gallons overflowed and was captured by site containment measures and pumped back into the sewer system. These overflows are primarily due to increased wastewater flow associated with snowmelt and brief pump maintenance and operational issues. 

Until full functionality is restored to the Potomac Interceptor, there remains a residual risk of additional limited overflows.

Daily water quality testing continues. Sampling results at downstream sampling locations continue to remain within EPA standards for acceptable levels.

Water Quality Sampling Results

Graphic of water quality samples.

Historical data indicate typical levels in the Potomac River can range from 10 to 5,000 MPN/100mL. Variability in E. coli results are common and are influenced by multiple factors, such as weather and subwatershed activities and conditions, including aging sewer infrastructure and illicit discharges. 

Latest News

Collapse site with equipment idle due to weather conditions
  • Environmental Rehabilitation and Emergency Repair work on the Potomac Interceptor sewer line was slowed by rain and snow, as we enter day 33 without an overflow into the Potomac River.
  • When there are ...
Photo of workers doing environmental rehab in west section of Area 1

With 32 days of no overflows reaching the Potomac River, DC Water and its contractor continue to make progress on the Environmental Rehabilitation of the areas impacted by the failure in the Potomac Interceptor. Meanwhile work is nearing completion in the coming days on the emergency repair and is expected to meet the mid-March target.

photo of worker going into downstream cleaning pit
  • Work is progressing to meet the mid-March target to return the flow to the Potomac Interceptor, as we reach 31 days with no overflows reaching the Potomac River.
  • The geopolymer applied to the upstream ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
March 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.