UPDATE: Potomac Interceptor Overflow, February 1, 2026

February 01, 2026
Potomac Interceptor Access Point showing sewer line where vacuum hoses are going in to clear debris

DC Water and its contractor are working to clean out the damaged section of the Potomac Interceptor, a sanitary sewer line which overflowed January 19, along Clara Barton Parkway and the 495 interchange and into the C & O Canal National Historical Park. Below is an update on the work being done and progress to date. 

Potomac Interceptor Update
Sunday, February 1, 2026

Containment

  • Overflow from the pipe remains contained for now.
  • This marks the fourth straight day with no overflows from the pipe.
  • The risk of overflow remains minimal with the bypass pumping operations, ongoing cleaning activities, and some existing flow that is safely moving through the collapse site within the sewer line. 

Excavation & Cleaning

  • Excavation and site preparation to allow access for cleaning efforts are complete.
  • Cleaning equipment has been mobilized.
  • Crews using truck-mounted, high powered vacuum equipment have begun work to clean out debris and obstructions blocking the pipe.
  • The equipment is being deployed from an access point in the pipe downstream from the damage.
  • The cleaning effort is slowly working toward the blockage in the collapsed section. 
  • This is to prevent an uncontrolled release of large amounts of material moving downstream with the potential to block flow again. 
  • Cleaning is expected to continue for a few days.
  • Once cleaning is complete, the goal is to isolate the pipe and restore full flow in the sewer line to eliminate the risk of dry and wet weather overflows.
  • This will also allow wastewater levels to draw down around the collapse so crews can access the damaged pipe, perform a full assessment, and determine the plan and timeline for repair. 
 
Pumping & Site Operations
  • Bypass operations continue with eight pumps to divert flow around the damaged section and back into the system further downstream.
  • Crews are working 24/7 to monitor the site and to clean and maintain the bypass pumps being utilized.
  • Cold weather continues to be a challenge for workers and equipment.  

Latest News

Map of lane closure on Clara Barton Parkway at Maryland-DC Border

Drivers should expect delays on Clara Barton Parkway at the Maryland – DC border on Saturday, Sept 26. One lane will be closed from 7 a.m. to 3 p.m. while DC Water makes repairs as part of ongoing ...

Christening of TBM Emily with DC Water Interim General Manager Matt Brown holding bottle of tap water to christen Emily

DC Water celebrated the christening of Emily today. It’s the second giant tunnel boring machine (TBM) that will help build the 5.5-mile Potomac River Tunnel. The celebration continued with Community Day. Residents and families met Emily and stepped inside the tunnel where she will soon begin digging.

Map: Temporary closure of the southbound curb lane on Rock Creek and Potomac Parkway NW

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT

Drivers should expect a temporary southbound lane closure on Rock Creek and Potomac Parkway NW between F St and Virginia Ave on Saturday, September 19, and Sunday, September 20, 2026. The closure will be in place from 7 a.m. to 7 p.m. each day, weather permitting.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Christening of TBM Emily with DC Water Interim General Manager Matt Brown holding bottle of tap water to christen Emily
DC Water Welcomes the Community Underground to See the Potomac River Tunnel and Christens Tunnel Boring Machine Emily

DC Water celebrated the christening of Emily today. It’s the second giant tunnel boring machine (TBM) that will help build the 5.5-mile Potomac River Tunnel. The celebration continued with Community Day. Residents and families met Emily and stepped inside the tunnel where she will soon begin digging.

Latest Blog Post
Emergency supplies arranged on a table, including bottled water, canned food, a backpack, first aid kit, flashlight, phone, medication and other essential items.
Simple Ways to Stay Prepared at Home
A few simple steps can help your household prepare for severe weather and temporary water or sewer service interruptions.
Upcoming Meeting
Date
October 8, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.