UPDATE: Potomac Interceptor Overflow, February 1, 2026

February 01, 2026
Potomac Interceptor Access Point showing sewer line where vacuum hoses are going in to clear debris

DC Water and its contractor are working to clean out the damaged section of the Potomac Interceptor, a sanitary sewer line which overflowed January 19, along Clara Barton Parkway and the 495 interchange and into the C & O Canal National Historical Park. Below is an update on the work being done and progress to date. 

Potomac Interceptor Update
Sunday, February 1, 2026

Containment

  • Overflow from the pipe remains contained for now.
  • This marks the fourth straight day with no overflows from the pipe.
  • The risk of overflow remains minimal with the bypass pumping operations, ongoing cleaning activities, and some existing flow that is safely moving through the collapse site within the sewer line. 

Excavation & Cleaning

  • Excavation and site preparation to allow access for cleaning efforts are complete.
  • Cleaning equipment has been mobilized.
  • Crews using truck-mounted, high powered vacuum equipment have begun work to clean out debris and obstructions blocking the pipe.
  • The equipment is being deployed from an access point in the pipe downstream from the damage.
  • The cleaning effort is slowly working toward the blockage in the collapsed section. 
  • This is to prevent an uncontrolled release of large amounts of material moving downstream with the potential to block flow again. 
  • Cleaning is expected to continue for a few days.
  • Once cleaning is complete, the goal is to isolate the pipe and restore full flow in the sewer line to eliminate the risk of dry and wet weather overflows.
  • This will also allow wastewater levels to draw down around the collapse so crews can access the damaged pipe, perform a full assessment, and determine the plan and timeline for repair. 
 
Pumping & Site Operations
  • Bypass operations continue with eight pumps to divert flow around the damaged section and back into the system further downstream.
  • Crews are working 24/7 to monitor the site and to clean and maintain the bypass pumps being utilized.
  • Cold weather continues to be a challenge for workers and equipment.  

Latest News

Section of Potomac River in Cabin John, MD showing river and trees

Testing will continue through September 10 at six Maryland locations closest to January sewer collapse

DC Water is moving from daily Potomac River water quality testing to testing twice a week. The change is part of our continued response to the January Potomac Interceptor sewer collapse. Daily testing continued past the original July 31 end date and today will be the last day DC Water will test at the 10 current locations.

Map: Temporary southbound lane closure on Rock Creek and Potomac Parkway NW.

Starting on or about Aug. 7, 2026, weather permitting, drivers can expect a temporary lane closure southbound on Rock Creek and Potomac Parkway NW near the intersection of Virginia Avenue NW and F ...

Photo of inside Potomac Interceptor at Dulles showing newly lined tunnel

First of four emergency repairs on Potomac Interceptor finished

DC Water has finished the first of four emergency repair projects on the Potomac Interceptor sewer line. Crews completed work today to strengthen a 600-foot section of pipe at Dulles International Airport.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Latest Blog Post
Plastic bottles, cups and other floating debris on the surface of the Anacostia River before the Anacostia River Tunnel began operating.
Cleaner Waterways Start With Everyday Choices
Protecting our waterways starts with everyday actions and continues through critical infrastructure designed to keep pollution out of our rivers.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.