EMERGENCY WATER OUTAGE
Jul 16, 2026 | 07:30 PM

EMERGENCY WATER OUTAGE
Jul 16, 2026 | 10:30 AM

UPDATE: Potomac Interceptor Overflow, February 1, 2026

February 01, 2026
Potomac Interceptor Access Point showing sewer line where vacuum hoses are going in to clear debris

DC Water and its contractor are working to clean out the damaged section of the Potomac Interceptor, a sanitary sewer line which overflowed January 19, along Clara Barton Parkway and the 495 interchange and into the C & O Canal National Historical Park. Below is an update on the work being done and progress to date. 

Potomac Interceptor Update
Sunday, February 1, 2026

Containment

  • Overflow from the pipe remains contained for now.
  • This marks the fourth straight day with no overflows from the pipe.
  • The risk of overflow remains minimal with the bypass pumping operations, ongoing cleaning activities, and some existing flow that is safely moving through the collapse site within the sewer line. 

Excavation & Cleaning

  • Excavation and site preparation to allow access for cleaning efforts are complete.
  • Cleaning equipment has been mobilized.
  • Crews using truck-mounted, high powered vacuum equipment have begun work to clean out debris and obstructions blocking the pipe.
  • The equipment is being deployed from an access point in the pipe downstream from the damage.
  • The cleaning effort is slowly working toward the blockage in the collapsed section. 
  • This is to prevent an uncontrolled release of large amounts of material moving downstream with the potential to block flow again. 
  • Cleaning is expected to continue for a few days.
  • Once cleaning is complete, the goal is to isolate the pipe and restore full flow in the sewer line to eliminate the risk of dry and wet weather overflows.
  • This will also allow wastewater levels to draw down around the collapse so crews can access the damaged pipe, perform a full assessment, and determine the plan and timeline for repair. 
 
Pumping & Site Operations
  • Bypass operations continue with eight pumps to divert flow around the damaged section and back into the system further downstream.
  • Crews are working 24/7 to monitor the site and to clean and maintain the bypass pumps being utilized.
  • Cold weather continues to be a challenge for workers and equipment.  

Latest News

image of clara barton parkway with lane closure marked in red

Beginning this week and continuing through mid-August, DC Water will temporarily close one lane overnight on Clara Barton Parkway at the Maryland-D.C. border. The closures are needed so crews can ...

Pennyfield Lock Potomac Interceptor bypass pipeline running next to C & O Canal with equipment

There is no active spill or overflow. Work to strengthen the pipe to begin soon.

Today, DC Water completed construction on a temporary bypass system as part of sewer repairs on the Potomac Interceptor near Pennyfield Lock in Potomac, Maryland. Crews turned on the pumps and successfully tested the system. With the bypass now ready, it will allow us to begin the emergency repairs inside the pipe by carrying the wastewater around the repair area.

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking
DC Water Breaks Ground on Piney Branch Tunnel, Final Phase of DC Clean Rivers Project

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Latest Blog Post
Five photos from the American Water Works Association (AWWA) ACE26 conference featuring panel discussions, technical presentations, networking, and attendees posing at the ACE26 display.
ACE26 Highlights: How DC Water Advanced the Conversation on Water
More than 80 DC Water employees joined thousands of water professionals in Washington, D.C., sharing expertise, building partnerships and advancing conversations that will help shape the future of water.
Upcoming Meeting
Date
July 17, 2026
Friday, 2:00 PM

Upcoming Events

Jul 23
Jul 25

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.