UPDATE: Potomac Interceptor Overflow, February 1, 2026

February 01, 2026
Potomac Interceptor Access Point showing sewer line where vacuum hoses are going in to clear debris

DC Water and its contractor are working to clean out the damaged section of the Potomac Interceptor, a sanitary sewer line which overflowed January 19, along Clara Barton Parkway and the 495 interchange and into the C & O Canal National Historical Park. Below is an update on the work being done and progress to date. 

Potomac Interceptor Update
Sunday, February 1, 2026

Containment

  • Overflow from the pipe remains contained for now.
  • This marks the fourth straight day with no overflows from the pipe.
  • The risk of overflow remains minimal with the bypass pumping operations, ongoing cleaning activities, and some existing flow that is safely moving through the collapse site within the sewer line. 

Excavation & Cleaning

  • Excavation and site preparation to allow access for cleaning efforts are complete.
  • Cleaning equipment has been mobilized.
  • Crews using truck-mounted, high powered vacuum equipment have begun work to clean out debris and obstructions blocking the pipe.
  • The equipment is being deployed from an access point in the pipe downstream from the damage.
  • The cleaning effort is slowly working toward the blockage in the collapsed section. 
  • This is to prevent an uncontrolled release of large amounts of material moving downstream with the potential to block flow again. 
  • Cleaning is expected to continue for a few days.
  • Once cleaning is complete, the goal is to isolate the pipe and restore full flow in the sewer line to eliminate the risk of dry and wet weather overflows.
  • This will also allow wastewater levels to draw down around the collapse so crews can access the damaged pipe, perform a full assessment, and determine the plan and timeline for repair. 
 
Pumping & Site Operations
  • Bypass operations continue with eight pumps to divert flow around the damaged section and back into the system further downstream.
  • Crews are working 24/7 to monitor the site and to clean and maintain the bypass pumps being utilized.
  • Cold weather continues to be a challenge for workers and equipment.  

Latest News

Workers doing ongoing rehabilitation work

As work nears completion on the initial clean-up and temporary stabilization of the areas directly impacted by the Potomac Interceptor overflows, DC Water is beginning preparations for beautification and revegetation to restore native plants, trees, and shrubs.

Before moving to the next phase of environmental rehabilitation, DC Water is working with the Environmental Protection Agency to conduct soil sampling to verify the clean-up efforts.

Photo of someone using the tap water with the dates of the annual water line cleaning March 23 - May 4

Spring cleaning isn’t just for closets and cabinets. DC Water’s system gets a refresh too!

Starting March 23, DC Water will begin work that helps maintain more than 1,300 miles of water lines across the District. During this time, the disinfectant used in drinking water will temporarily switch from chloramine to chlorine through May 4. This switch helps support overall water quality throughout the year.

photos of workers with hoses vacuuming out canal

Work is ongoing to complete the initial phase of environmental rehabilitation and temporary stabilization this week in areas directly impacted by the overflows. A small section of the drainage channel along Clara Barton Parkway remains. Preliminary clean-up of the culvert, tributary, and Potomac River shoreline has also been completed.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.