UPDATE: Emergency Repair Work Set to Begin on Potomac Interceptor

March 03, 2026
Protective Encasement for workers to apply the geopolymer lining

Potomac Interceptor Repair Update
March 3, 2026

  • Repair efforts continue as we reach 23 days in which no overflows have entered the Potomac River. The last release to reach the river occurred on February 8.
  • Crews finished pressure washing the pipe upstream of the damaged section of the Potomac Interceptor in advance of the geopolymer application. 
  • Preparations are underway to mobilize equipment and materials to begin spraying the geopolymer lining in the upstream portion of the pipe. The geopolymer which is similar in strength to concrete will reinforce and strengthen the pipe.
  • A protective steel encasement is being placed inside the pipe, providing a protective barrier for crews to work as they apply the geopolymer and move through the upstream section of pipe. (see photo above)
  • Cleaning and debris removal continues in the pipe downstream of the collapse site. Once the geopolymer is applied upstream, work will move to the downstream section to complete the emergency repair.
  • Environmental restoration work is underway; however, work cannot be done when there is measurable rain and precipitation due to the risk of further contamination. 
  • DC Water is adding two new water quality sampling locations, bringing the total to 10. The new locations include Sycamore Island and the feeder channel near Lock 6 with a kayak slalom course frequently used for training.  Sampling is expected to begin later this week. 
  • Emergency repairs remain on schedule to be completed by mid-March, at which time the full flow and functionality will be restored to the Potomac Interceptor and the bypass pumping operation using the C & O Canal will be deactivated.

Water Quality Sampling Results

Fluctuations in water quality are influenced by factors such as weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways. Given these variables, measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs

Sample results from February 23 - present. Past results may be found here.

water sample graphic

For more on the ongoing Potomac Interceptor Repair efforts, including the latest news and updates, water quality sampling, and additional information go to dcwater.com/potomac-interceptor-collapse.

Latest News

Section of Potomac River in Cabin John, MD showing river and trees

Testing will continue through September 10 at six Maryland locations closest to January sewer collapse

DC Water is moving from daily Potomac River water quality testing to testing twice a week. The change is part of our continued response to the January Potomac Interceptor sewer collapse. Daily testing continued past the original July 31 end date and today will be the last day DC Water will test at the 10 current locations.

Map: Temporary southbound lane closure on Rock Creek and Potomac Parkway NW.

Starting on or about Aug. 7, 2026, weather permitting, drivers can expect a temporary lane closure southbound on Rock Creek and Potomac Parkway NW near the intersection of Virginia Avenue NW and F ...

Photo of inside Potomac Interceptor at Dulles showing newly lined tunnel

First of four emergency repairs on Potomac Interceptor finished

DC Water has finished the first of four emergency repair projects on the Potomac Interceptor sewer line. Crews completed work today to strengthen a 600-foot section of pipe at Dulles International Airport.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Latest Blog Post
Plastic bottles, cups and other floating debris on the surface of the Anacostia River before the Anacostia River Tunnel began operating.
Cleaner Waterways Start With Everyday Choices
Protecting our waterways starts with everyday actions and continues through critical infrastructure designed to keep pollution out of our rivers.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.