UPDATE: Emergency Repair Work Set to Begin on Potomac Interceptor

March 03, 2026
Protective Encasement for workers to apply the geopolymer lining

Potomac Interceptor Repair Update
March 3, 2026

  • Repair efforts continue as we reach 23 days in which no overflows have entered the Potomac River. The last release to reach the river occurred on February 8.
  • Crews finished pressure washing the pipe upstream of the damaged section of the Potomac Interceptor in advance of the geopolymer application. 
  • Preparations are underway to mobilize equipment and materials to begin spraying the geopolymer lining in the upstream portion of the pipe. The geopolymer which is similar in strength to concrete will reinforce and strengthen the pipe.
  • A protective steel encasement is being placed inside the pipe, providing a protective barrier for crews to work as they apply the geopolymer and move through the upstream section of pipe. (see photo above)
  • Cleaning and debris removal continues in the pipe downstream of the collapse site. Once the geopolymer is applied upstream, work will move to the downstream section to complete the emergency repair.
  • Environmental restoration work is underway; however, work cannot be done when there is measurable rain and precipitation due to the risk of further contamination. 
  • DC Water is adding two new water quality sampling locations, bringing the total to 10. The new locations include Sycamore Island and the feeder channel near Lock 6 with a kayak slalom course frequently used for training.  Sampling is expected to begin later this week. 
  • Emergency repairs remain on schedule to be completed by mid-March, at which time the full flow and functionality will be restored to the Potomac Interceptor and the bypass pumping operation using the C & O Canal will be deactivated.

Water Quality Sampling Results

Fluctuations in water quality are influenced by factors such as weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways. Given these variables, measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs

Sample results from February 23 - present. Past results may be found here.

water sample graphic

For more on the ongoing Potomac Interceptor Repair efforts, including the latest news and updates, water quality sampling, and additional information go to dcwater.com/potomac-interceptor-collapse.

Latest News

Photo of Potomac River at the overflow location

Hundreds of Sampling Results Confirm Return to Normal Bacteria Levels in Potomac River

DC Water has outlined its next steps to complete the environmental cleanup and its plan for continued water quality monitoring this summer, as part of the ongoing response to January’s failure in the Potomac Interceptor sewer pipeline. The plan, submitted to the Maryland Department of the Environment (MDE), is supported by extensive data from hundreds of samples.

crews removing soil in C & O Canal

Work continues to remove the remaining soil between locks 10 and 12 of the C & O Canal which was used as an emergency bypass while the Potomac Interceptor was repaired. Crews area also removing plants, trees, and shrubs in preparation for the long-term rehabilitation of the Potomac Interceptor.

Placeholder DC Water Image

DC Water has nearly completed construction site preparation for the Piney Branch Tunnel project, including tree removal, and installation of fences, erosion and sediment controls, utilities, and ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Placeholder DC Water Image
Piney Branch Parkway Temporary Closure and Relocation

DC Water has nearly completed construction site preparation for the Piney Branch Tunnel project, including tree removal, and installation of fences

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

May 16
2:00 pm - 6:00 pm
May 20

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.