Initial Phase of Environmental Rehabilitation on West Section of Drainage Channel Nearing Completion

March 11, 2026
Photo of workers doing environmental rehab in west section of Area 1
  • With 32 days of no overflows reaching the Potomac River, DC Water and its contractor continue to make progress on the Environmental Rehabilitation of the areas impacted by the failure in the Potomac Interceptor.
  • In Area 1, which is divided into two sections from the collapse site to the length of the drainage channel along Clara Barton Parkway, DC Water crews have completed about 70% of the initial phase of rehabilitation on the west section.
  • Additional rehabilitation work continues on the east side of Area 1 and in Area 2 around the Rock Run culvert down to the tributary, working in coordination with the Environmental Protection Agency and US Army Corps of Engineers.
  • The first phase of the clean-up includes brush and debris removal, mucking, soil raking and soil removal, and assessment.
  • Work remains on target to complete the emergency repair by mid-March to return full flow to the interceptor. This process will involve carefully removing the bulkhead gate blocking the flow, while methodically turning pumps off as more flow is introduced to the pipe.
  • Once all the pumps are turned off and flow returned to the interceptor, the C & O Canal will no longer be needed for the bypass system. The remaining wastewater will continue to drain into the Potomac Interceptor downstream of the collapse site, and any residual wastewater will be pumped out of the canal to allow the environmental rehabilitation to begin.
  • The emergency repair is now focused on applying geopolymer to the trench boxes around the excavated pipe sections to provide a waterproof seal to successfully return the flow to the interceptor.
  • The trench boxes will provide an “open flow channel” allowing the wastewater to flow through sections of the pipe where the crown has been removed. These openings will be used to insert new pipe sections into the existing pipe as part of the long-term rehabilitation that when complete will return it to like-new condition.

Water Quality Sampling Results

Fluctuations in water quality are influenced by factors such as rain, heat, or other weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways. Given these variables, measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs.

As of March 4, two new sampling locations have been added at Sycamore Island and Lock 6. Sample results from March 2 - present. Past results may be found here.

water quality sampling chart

For more information, including the latest news and updates, and to provide feedback on the Environmental Rehabilitation Plan go to our dedicated page for the Potomac Interceptor Repairs.

Latest News

image of clara barton parkway with lane closure marked in red

Beginning this week and continuing through mid-August, DC Water will temporarily close one lane overnight on Clara Barton Parkway at the Maryland-D.C. border. The closures are needed so crews can ...

Pennyfield Lock Potomac Interceptor bypass pipeline running next to C & O Canal with equipment

There is no active spill or overflow. Work to strengthen the pipe to begin soon.

Today, DC Water completed construction on a temporary bypass system as part of sewer repairs on the Potomac Interceptor near Pennyfield Lock in Potomac, Maryland. Crews turned on the pumps and successfully tested the system. With the bypass now ready, it will allow us to begin the emergency repairs inside the pipe by carrying the wastewater around the repair area.

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking
DC Water Breaks Ground on Piney Branch Tunnel, Final Phase of DC Clean Rivers Project

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Latest Blog Post
Five photos from the American Water Works Association (AWWA) ACE26 conference featuring panel discussions, technical presentations, networking, and attendees posing at the ACE26 display.
ACE26 Highlights: How DC Water Advanced the Conversation on Water
More than 80 DC Water employees joined thousands of water professionals in Washington, D.C., sharing expertise, building partnerships and advancing conversations that will help shape the future of water.
Upcoming Meeting
Date
July 23, 2026
Thursday, 9:30 AM

Upcoming Events

Jul 23
Jul 25

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.