Initial Phase of Environmental Rehabilitation on West Section of Drainage Channel Nearing Completion

March 11, 2026
Photo of workers doing environmental rehab in west section of Area 1
  • With 32 days of no overflows reaching the Potomac River, DC Water and its contractor continue to make progress on the Environmental Rehabilitation of the areas impacted by the failure in the Potomac Interceptor.
  • In Area 1, which is divided into two sections from the collapse site to the length of the drainage channel along Clara Barton Parkway, DC Water crews have completed about 70% of the initial phase of rehabilitation on the west section.
  • Additional rehabilitation work continues on the east side of Area 1 and in Area 2 around the Rock Run culvert down to the tributary, working in coordination with the Environmental Protection Agency and US Army Corps of Engineers.
  • The first phase of the clean-up includes brush and debris removal, mucking, soil raking and soil removal, and assessment.
  • Work remains on target to complete the emergency repair by mid-March to return full flow to the interceptor. This process will involve carefully removing the bulkhead gate blocking the flow, while methodically turning pumps off as more flow is introduced to the pipe.
  • Once all the pumps are turned off and flow returned to the interceptor, the C & O Canal will no longer be needed for the bypass system. The remaining wastewater will continue to drain into the Potomac Interceptor downstream of the collapse site, and any residual wastewater will be pumped out of the canal to allow the environmental rehabilitation to begin.
  • The emergency repair is now focused on applying geopolymer to the trench boxes around the excavated pipe sections to provide a waterproof seal to successfully return the flow to the interceptor.
  • The trench boxes will provide an “open flow channel” allowing the wastewater to flow through sections of the pipe where the crown has been removed. These openings will be used to insert new pipe sections into the existing pipe as part of the long-term rehabilitation that when complete will return it to like-new condition.

Water Quality Sampling Results

Fluctuations in water quality are influenced by factors such as rain, heat, or other weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways. Given these variables, measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs.

As of March 4, two new sampling locations have been added at Sycamore Island and Lock 6. Sample results from March 2 - present. Past results may be found here.

water quality sampling chart

For more information, including the latest news and updates, and to provide feedback on the Environmental Rehabilitation Plan go to our dedicated page for the Potomac Interceptor Repairs.

Latest News

Photo of manhole entrance withe completed geopolymer

Second of four high-priority repair projects is now complete

DC Water has completed the second of four critical repair projects on the Potomac Interceptor Sewer Line. Crews finished strengthening a 490-foot section of the pipe at Broad Run in Loudoun County today.

Image of Clara Barton Parkway showing lane closure

Beginning this week and continuing through the end of September, DC Water will temporarily close one lane overnight on Clara Barton Parkway at the Maryland-D.C. border. The closures are necessary to allow crews to safely begin geopolymer work, a concrete-like material, applied inside the sewer line as part of emergency repairs to a section of the Potomac Interceptor.

Last gantry at the bottom of the shaft where crews connect it

Final Gantry Completes Mobile Support Train Behind Mary Stretching More Than 700 Feet

DC Water’s tunnel boring machine Mary may be the muscle behind the Potomac River Tunnel Project, but the gantries that trail behind her form the heart, brains, and guts of the operation. Now crews have lowered and connected the final gantry section, giving Mary the tools and equipment she needs to continue tunneling north.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Last gantry at the bottom of the shaft where crews connect it
Now Fully Assembled, It’s Full Speed Ahead for the tunnel boring machine Mary and the Potomac River Tunnel

Final Gantry Completes Mobile Support Train Behind Mary Stretching More Than 700 Feet

DC Water’s tunnel boring machine Mary may be the muscle behind the Potomac River Tunnel Project, but the gantries that trail behind her form the heart, brains, and guts of the operation. Now crews have lowered and connected the final gantry section, giving Mary the tools and equipment she needs to continue tunneling north.

Latest Blog Post
Emergency supplies arranged on a table, including bottled water, canned food, a backpack, first aid kit, flashlight, phone, medication and other essential items.
Simple Ways to Stay Prepared at Home
A few simple steps can help your household prepare for severe weather and temporary water or sewer service interruptions.
Upcoming Meeting

Upcoming Events

Sep 6
Sep 19

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.