Initial Phase of Environmental Rehabilitation on West Section of Drainage Channel Nearing Completion

March 11, 2026
Photo of workers doing environmental rehab in west section of Area 1
  • With 32 days of no overflows reaching the Potomac River, DC Water and its contractor continue to make progress on the Environmental Rehabilitation of the areas impacted by the failure in the Potomac Interceptor.
  • In Area 1, which is divided into two sections from the collapse site to the length of the drainage channel along Clara Barton Parkway, DC Water crews have completed about 70% of the initial phase of rehabilitation on the west section.
  • Additional rehabilitation work continues on the east side of Area 1 and in Area 2 around the Rock Run culvert down to the tributary, working in coordination with the Environmental Protection Agency and US Army Corps of Engineers.
  • The first phase of the clean-up includes brush and debris removal, mucking, soil raking and soil removal, and assessment.
  • Work remains on target to complete the emergency repair by mid-March to return full flow to the interceptor. This process will involve carefully removing the bulkhead gate blocking the flow, while methodically turning pumps off as more flow is introduced to the pipe.
  • Once all the pumps are turned off and flow returned to the interceptor, the C & O Canal will no longer be needed for the bypass system. The remaining wastewater will continue to drain into the Potomac Interceptor downstream of the collapse site, and any residual wastewater will be pumped out of the canal to allow the environmental rehabilitation to begin.
  • The emergency repair is now focused on applying geopolymer to the trench boxes around the excavated pipe sections to provide a waterproof seal to successfully return the flow to the interceptor.
  • The trench boxes will provide an “open flow channel” allowing the wastewater to flow through sections of the pipe where the crown has been removed. These openings will be used to insert new pipe sections into the existing pipe as part of the long-term rehabilitation that when complete will return it to like-new condition.

Water Quality Sampling Results

Fluctuations in water quality are influenced by factors such as rain, heat, or other weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways. Given these variables, measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs.

As of March 4, two new sampling locations have been added at Sycamore Island and Lock 6. Sample results from March 2 - present. Past results may be found here.

water quality sampling chart

For more information, including the latest news and updates, and to provide feedback on the Environmental Rehabilitation Plan go to our dedicated page for the Potomac Interceptor Repairs.

Latest News

Excavation site outside the I-495 Beltway showing section of the PI

Crews completed cleaning on Lock 11 of the C & O Canal as prescribed by the National Park Service, with soil removal also nearing completion within the lock area. Tree removal is also underway, after DC Water received the permits to move forward as part of the site preparations for the long-term accelerated rehabilitation of more than 2700 linear feet of the Potomac Interceptor sewer line that had been previously planned.

Photo of long stretch of C & O Canal with soil removed

DC Water has excavated a section of the Potomac Interceptor along Clara Barton Parkway, outside the I-495 Beltway as part of the accelerated rehabilitation of more than 2700 linear feet of the interceptor that was previously planned. As part of the long-term rehabilitation project, crews are beginning to remove trees which is necessary to construct a bypass chamber that will divert wastewater around sections of the pipe while they are being rehabilitated.

The shields for the tunnel boring machine Mary being lowered by cranes into the shaft

Recognition highlights DC Water’s commitment to environmental stewardship during Earth Month

DC Water has been honored with the “Green Bond of the Year – US Muni Bond” Award by Environmental Finance, a leading industry publication. This achievement celebrates DC Water’s leadership in sustainability and its dedication to responsible municipal financing.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

The shields for the tunnel boring machine Mary being lowered by cranes into the shaft
DC Water Earns Prominent Award for Sustainable Finance Leadership through Green Bonds

Recognition highlights DC Water’s commitment to environmental stewardship during Earth Month

DC Water has been honored with the “Green Bond of the Year – US Muni Bond” Award by Environmental Finance, a leading industry publication. This achievement celebrates DC Water’s leadership in sustainability and its dedication to responsible municipal financing.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
May 4, 2026
Monday, 2:00 PM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.