DC Water Continues Initial Clean-Up of C & O Canal, Prepares Site for Severe Weather

March 16, 2026
Odor Control Measures near Open Trench with Pumps
  • DC Water and its contractor continue to work to remove sludge and debris from the C & O Canal which was temporarily used as a bypass during the emergency repair of the Potomac Interceptor.
  • Construction continues on the freshwater dam at Lock 14, which is being fed by water from the Potomac River at Violet’s Lock. The freshwater will be pumped into the canal to help flush the sludge and debris. The flushed material is being directed back into the Potomac Interceptor further downstream. Rainfall throughout the day has assisted in flushing the canal and supporting the initial clean-up.
  • DC Water expects to complete the initial removal of debris, soil, and contaminants along the Western section of Area 1 along the drainage channel and adjacent to the collapse site this week.
  • There are no issues with the flow that was returned to the Potomac Interceptor. Some sections of the interceptor remain open, operating under what is known as an open channel flow. These openings will also facilitate the long-term repairs allowing crews to insert a new pipe into the existing interceptor.
  • While these sections remain open, the impact of any rainfall is expected to be minimal. The main open pipe sections are approximately 20 feet below ground, contained by waterproof trench boxes to prevent flow from getting in or out of the work area.
  • Based on the forecast of up to one inch of rain over 72-hours, direct rainfall into the openings would only add about 1200 gallons spread over the entire 72-hour period. The interceptor has between one and three million gallons going through at any given moment, and the impact of any direct rainfall through these openings would be negligible.
  • Crews also worked to secure fencing and other materials and equipment at the site, in preparation for high winds and extreme weather.
  • Due to the severe weather threat today, crews were unable to collect water quality samples at every site. This will be reflected in the data tomorrow.
  • DC Water will hold two community meetings this week to continue the dialogue and for the public to ask questions about the Potomac Interceptor repairs and environmental rehabilitation:
    • Wednesday, March 18 at 6:30 PM | Walt Whitman High School (Cafeteria) | 7100 Whittier Blvd., Bethesda, MD 20817
    • Thursday, March 19 at 7:00 PM | Lee Center Auditorium | 1108 Jefferson St., Alexandria, VA 22314
    • Those interested in attending may RSVP at events@dcwater.com. Please include which meeting you plan to attend.

 

Water Quality Sampling Results

Fluctuations in water quality are influenced by factors such as rain, heat, or other weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways. Given these variables and that overflows have been contained for more than a month prior to completing emergency repairs, measurements taken much further downstream are likely unrelated to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs.

Sample results from March 9 - present. Past results may be found here.

water quality sampling data

For the latest updates and information, including how to provide feedback on the environmental rehabilitation, go to our dedicated Potomac Interceptor Response page.

 

Latest News

A section of the canal where the soil has been removed
  • Crews are close to completing the removal of remaining soil from Locks 11 to 13 in the section of the C&O Canal that was used as an emergency bypass after the collapse of the Potomac Interceptor sewer ...
Excavation site outside the I-495 Beltway showing section of the PI

Crews completed cleaning on Lock 11 of the C & O Canal as prescribed by the National Park Service, with soil removal also nearing completion within the lock area. Tree removal is also underway, after DC Water received the permits to move forward as part of the site preparations for the long-term accelerated rehabilitation of more than 2700 linear feet of the Potomac Interceptor sewer line that had been previously planned.

Photo of long stretch of C & O Canal with soil removed

DC Water has excavated a section of the Potomac Interceptor along Clara Barton Parkway, outside the I-495 Beltway as part of the accelerated rehabilitation of more than 2700 linear feet of the interceptor that was previously planned. As part of the long-term rehabilitation project, crews are beginning to remove trees which is necessary to construct a bypass chamber that will divert wastewater around sections of the pipe while they are being rehabilitated.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

The shields for the tunnel boring machine Mary being lowered by cranes into the shaft
DC Water Earns Prominent Award for Sustainable Finance Leadership through Green Bonds

Recognition highlights DC Water’s commitment to environmental stewardship during Earth Month

DC Water has been honored with the “Green Bond of the Year – US Muni Bond” Award by Environmental Finance, a leading industry publication. This achievement celebrates DC Water’s leadership in sustainability and its dedication to responsible municipal financing.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
May 5, 2026
Tuesday, 1:00 PM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.