DC Water Begins Environmental Restoration to Areas Impacted by Sewer Overflow from the Potomac Interceptor

March 02, 2026
Workers clearing brush and debris from drainage channel
National Park Service Issues Special Use Permit to Move Forward with Restoration Plan

DC Water has begun the rehabilitation and environmental restoration to address areas affected by the sewer overflow from a section of the Potomac Interceptor that collapsed January 19. Contaminated material is being hauled away and work is underway to clear trees, brush, and contaminated debris in and around the collapse site as part of the environmental restoration plan approved by the National Park Service (NPS).

On February 28, NPS issued a Special Use Permit for the repair, rehabilitation, and environmental restoration of the Potomac Interceptor and the C&O Canal National Historical Park at the area of the Potomac Interceptor collapse between Locks 10 and 14.

DC Water continues to evaluate the environmental impacts of the overflow and is exploring further restoration efforts based on input from concerned residents and community groups, along with the ongoing collaboration with federal, state, and local regulators overseeing the environmental restoration.

In response to feedback, DC Water will be adding another water quality sampling location at Sycamore Island. Sampling is expected to begin at the new location this week. This is in addition to two locations on Minnie’s Island that were added last month and increases the number of sampling locations from the six original sites to nine.

The restoration plan sets out a roadmap for recovery, focusing on stabilizing the drainage channel, cleaning up debris, and rehabilitating wetlands, streams, and the canal within the C & O Canal National Historical Park.

The work will be carried out in two primary phases. The first phase focuses on immediate stabilization and remediation at the collapse site, including the removal of contaminated soil, debris, and vegetation, as well as the initial stabilization of affected drainage channels and areas along the Potomac River and impacted shoreline. This is expected to take one to two months to complete.

The second phase will address the broader environmental restoration and final stabilization, including the C&O Canal once the emergency repair is completed and the bypass pumping system is deactivated, which is anticipated to occur in mid-March. Work will be sequenced to minimize environmental disruption and protect public safety throughout the process.

Restoration activities are planned for three distinct areas: 1) the collapse site itself, where emergency repairs and soil remediation are ongoing; 2) the adjacent wetlands and stream corridors, which require rehabilitation to restore natural hydrology and habitat; and 3) the section of the C&O Canal impacted by the overflow, where sediment and debris will be removed, and native vegetation will be replanted. Each section will be addressed according to its specific needs, with progress carefully monitored and coordinated with NPS and Maryland Department of the Environment (MDE) to ensure environmental compliance and effective recovery.

The plan was developed with input and collaboration with NPS, the U.S. Army Corps of Engineers (USACE), MDE, Environmental Protection Agency (EPA), and District Department of Energy & Environment (DOEE).

Looking ahead, DC Water will continue to monitor progress and conduct post-restoration assessments to ensure the effectiveness of these efforts. As restoration activities advance, updates will be provided to keep the community informed and involved. Our goal is to return the parklands and waterways to their natural state, fostering a safe and vibrant environment for all.

The Environmental Restoration Plan and the NPS Special Use Permit are available for review on our dedicated page for the Potomac Interceptor Repairs. You will also find daily updates on the repair work, water quality sampling results, and additional information about the ongoing work and community outreach.

Water Quality Sampling Results

Fluctuations in water quality are influenced by factors such as weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways. Given these variables, measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs

Sample results from February 23 - present. Past results may be found here.

water sampling chart

Latest News

Workers doing ongoing rehabilitation work

As work nears completion on the initial clean-up and temporary stabilization of the areas directly impacted by the Potomac Interceptor overflows, DC Water is beginning preparations for beautification and revegetation to restore native plants, trees, and shrubs.

Before moving to the next phase of environmental rehabilitation, DC Water is working with the Environmental Protection Agency to conduct soil sampling to verify the clean-up efforts.

Photo of someone using the tap water with the dates of the annual water line cleaning March 23 - May 4

Spring cleaning isn’t just for closets and cabinets. DC Water’s system gets a refresh too!

Starting March 23, DC Water will begin work that helps maintain more than 1,300 miles of water lines across the District. During this time, the disinfectant used in drinking water will temporarily switch from chloramine to chlorine through May 4. This switch helps support overall water quality throughout the year.

photos of workers with hoses vacuuming out canal

Work is ongoing to complete the initial phase of environmental rehabilitation and temporary stabilization this week in areas directly impacted by the overflows. A small section of the drainage channel along Clara Barton Parkway remains. Preliminary clean-up of the culvert, tributary, and Potomac River shoreline has also been completed.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.