DC Water Begins Demobilizing Emergency Repair Operations, Transition to Long-Term Pipe Rehabilitation

March 17, 2026
workers spraying and mucking sludge from canal
  • After three days of stable operations following completion of emergency repairs to restore flow to the Potomac Interceptor, the bypass pumping system is being demobilized. Crews have begun disassembling the bypass pipes and removing them from the upstream section of the interceptor, where pumps were used to divert wastewater around the collapse site and back into the interceptor further downstream.
  • DC Water and its contractors continue to remove sludge and debris from the C & O Canal as part of the initial environmental rehabilitation and clean-up.
  • The initial phase of environmental rehabilitation is nearing completion in the areas directly impacted by the overflow, including the drainage channel along Clara Barton Parkway, Rock Run culvert, the unnamed tributary to the Potomac River, and the immediate shoreline along the river.
  • Some work remains in the eastern section of Area 1 within the drainage channel. The initial rehabilitation work includes clearing brush and debris, mucking, removing contaminated soil, and installing erosion control and soil stabilization measures for the initial phase of clean-up.
  • The area will remain an active construction site for the next 9-10 months, as DC Water demobilizes from the emergency repair and transitions to the previously planned long-term rehabilitation.
  • Site preparations will soon begin to bring in equipment and materials needed to rehabilitate more than 2700 linear feet of the interceptor, using a process called slip lining. A new pipe will be inserted into the existing interceptor to strengthen and reinforce it to like-new condition.
  • DC Water is also preparing for two community meetings this week to provide updates and answer questions about the repairs and environmental rehabilitation:
    • Wednesday, March 18 at 6:30 PM | Walt Whitman High School (Cafeteria) | 7100 Whittier Blvd., Bethesda, MD 20817
    • Thursday, March 19 at 7:00 PM | Lee Center Auditorium | 1108 Jefferson St., Alexandria, VA 22314
    • Those interested in attending may RSVP at events@dcwater.com. Please include which meeting you plan to attend.

Water Quality Sampling Results

Fluctuations in water quality are influenced by factors such as rain, heat, or other weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways. This is reflected in the March 16 sampling results that coincided with a rain event. Given these variables and that overflows have been contained for more than a month prior to completing emergency repairs, measurements taken much further downstream are likely unrelated to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs.

Due to severe weather on Monday, we were unable to perform water quality sampling at two locations. Sampling resumed today and results will be available tomorrow.

Sample results from March 9 - present. Past results may be found here.

graphic of water quality results

For the latest updates and information, including how to provide feedback on the environmental rehabilitation, go to our dedicated Potomac Interceptor Response page.

 

Latest News

A section of the canal where the soil has been removed
  • Crews are close to completing the removal of remaining soil from Locks 11 to 13 in the section of the C&O Canal that was used as an emergency bypass after the collapse of the Potomac Interceptor sewer ...
Excavation site outside the I-495 Beltway showing section of the PI

Crews completed cleaning on Lock 11 of the C & O Canal as prescribed by the National Park Service, with soil removal also nearing completion within the lock area. Tree removal is also underway, after DC Water received the permits to move forward as part of the site preparations for the long-term accelerated rehabilitation of more than 2700 linear feet of the Potomac Interceptor sewer line that had been previously planned.

Photo of long stretch of C & O Canal with soil removed

DC Water has excavated a section of the Potomac Interceptor along Clara Barton Parkway, outside the I-495 Beltway as part of the accelerated rehabilitation of more than 2700 linear feet of the interceptor that was previously planned. As part of the long-term rehabilitation project, crews are beginning to remove trees which is necessary to construct a bypass chamber that will divert wastewater around sections of the pipe while they are being rehabilitated.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

The shields for the tunnel boring machine Mary being lowered by cranes into the shaft
DC Water Earns Prominent Award for Sustainable Finance Leadership through Green Bonds

Recognition highlights DC Water’s commitment to environmental stewardship during Earth Month

DC Water has been honored with the “Green Bond of the Year – US Muni Bond” Award by Environmental Finance, a leading industry publication. This achievement celebrates DC Water’s leadership in sustainability and its dedication to responsible municipal financing.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
May 5, 2026
Tuesday, 1:00 PM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.