Weekend Trail and Lane Closure for Ongoing Repair to Rock Creek Sewer Line

November 05, 2025
picture of damage inside the RCMI

Starting Friday, November 7 at 8 p.m. through Monday, November 10 at 5 a.m., and again on November 14-17, a section of the Rock Creek Multi-use Trail near Rose Park—between P Street NW and Pennsylvania Avenue NW— will be temporarily closed for construction. One sounthbound lane of Rock Creek and Potomac Parkway will also be closed, impacting traffic. This closure is part of ongoing high-priorty repairs to the Rock Creek Main Interceptor (RCMI), a  major sewer line which transports more than 100 million gallons of wastewater each day. 

The construction plan initially announced in early October involves two phases. During the first phase, crews will peform work to help restore one of two sewer gates located within a structure along the trail. Once completed, crews will move on to the second phase of the project, now expected to start in early 2026. These repairs are a high priority to prevent potential sewage discharge into Rock Creek and are part of DC Water’s Capital Improvement Program.

The gate restoration was intially expected to require two weekend trail and lane closures. However, due to unforseen complications construction is now expected to require an additional 5-7 weekends. Additional dates have not yet been determined but will involve the same restrictions as detailed below: 

  • Closure Dates: Friday, November 7-10 and 14-17, 2025
  • Closure Times: Friday 8PM through Monday 5 AM (both weekends)
  • Trail Segment: Between P Street NW and Pennsylvania Avenue NW
  • Detour: Available via Rose Park
  • Work Hours: Continuous, 24/7 throughout the weekend

During the gate restoration, one lane of southbound Rock Creek and Potomac Parkway will also be closed. Visitors in this area should follow trail detours. For safety, do not walk on the roadway. 

Map of full project area next to map of Rock Creek Trail Site

The first phase of construction to repair the gates is essential to allow internal inspections of the pipe, paving the way for more comprehensive rehabilitation efforts in Phase 2.

The gates being refurbished play a vital role in controlling wastewater flow during both construction and periods of heavy rainfall. Positioned at strategic locations along the RCMI system—including near the Smithsonian National Zoo, the Rock Creek Trail by Rose Park, and the Georgetown Waterfront—these gates enable DC Water to redirect flow away from active work zones. During storms, they can be opened to boost system capacity and help prevent overflows, protecting infrastructure and the surrounding environment.

Looking ahead, Phase 2 will focus on restoring approximately 3,000 feet of the 72-inch diameter pipe. This phase is expected to continue through September 2026.

DC Water thanks the community for its patience and cooperation as crews work to maintain the integrity of this essential infrastructure. The team will monitor noise and traffic impacts throughout the project and provide regular updates.

 

 

Latest News

Section of Potomac River in Cabin John, MD showing river and trees

Testing will continue through September 10 at six Maryland locations closest to January sewer collapse

DC Water is moving from daily Potomac River water quality testing to testing twice a week. The change is part of our continued response to the January Potomac Interceptor sewer collapse. Daily testing continued past the original July 31 end date and today will be the last day DC Water will test at the 10 current locations.

Map: Temporary southbound lane closure on Rock Creek and Potomac Parkway NW.

Starting on or about Aug. 7, 2026, weather permitting, drivers can expect a temporary lane closure southbound on Rock Creek and Potomac Parkway NW near the intersection of Virginia Avenue NW and F ...

Photo of inside Potomac Interceptor at Dulles showing newly lined tunnel

First of four emergency repairs on Potomac Interceptor finished

DC Water has finished the first of four emergency repair projects on the Potomac Interceptor sewer line. Crews completed work today to strengthen a 600-foot section of pipe at Dulles International Airport.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Latest Blog Post
Plastic bottles, cups and other floating debris on the surface of the Anacostia River before the Anacostia River Tunnel began operating.
Cleaner Waterways Start With Everyday Choices
Protecting our waterways starts with everyday actions and continues through critical infrastructure designed to keep pollution out of our rivers.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.