Updated Maps: Independence Avenue, SW, Temporary Lane and Sidewalk Closures

July 24, 2024
Hydro excavating utilities with a vac truck.

(Washington, DC) – DC Water's Potomac River Tunnel Project contractor began utility tie-in operations along Independence Avenue, SW between Ohio Drive, SW, and West Basin Drive, SW on June 16, 2024. This work requires phased temporary closures of one to two eastbound travel lanes and one to two westbound travel lanes on Independence Avenue the crosswalk at West Basin Drive and Independence Avenue and the sidewalk on the south side of Independence Avenue (adjacent to West Potomac Park). Work hours are Monday through Friday from 7:00 pm to 5:30 am for the two-lane closures and from 9:30 am to 2:30 pm for the single-lane closures, weather permitting. All travel lanes reopen during non-working hours. Please refer to Maps A, B, and C below for additional details.

The tie-in work is necessary to construct a relocated Ohio Drive and to prepare the site for the Potomac River Tunnel (PRT) Project. The contractor will restore the work areas when the tie-in work is completed. 

Independence Avenue, SW Work (Maps A, B, & C)

  • Date: June 16 – October 6, 2024
  • Time: Monday – Friday, from 7:00 pm – 5:30 am for two-lane closures; Monday – Friday, from 9:30 am – 2:30 pm for single-lane closures.
  • Location: Independence Avenue, SW between Ohio Drive, SW and West Basin Drive, SW
  • Traffic Patterns and Pedestrian Detours: 
    • Traffic: Temporary eastbound and westbound lane closures on Independence Avenue between Ohio Drive and West Basin Drive. See Maps A and B for additional details.
    • Pedestrian Detours: Temporary sidewalk and crosswalk closures adjacent to West Potomac Park along Independence Avenue between Ohio Drive and West Basin Drive. See Map C for additional details.

Independence Ave one lane closure

Map A: (Independence Ave, SW) One Lane Closure Configuration

 

Independence Ave two lane closures

Map B: (Independence Ave, SW) Two Lane Closure Configuration

 

Independence Ave pedestrian detour

Map C: (Independence Ave, SW) Pedestrian Detour

Important Information

  • The sidewalk and crosswalk identified on the maps above will remain closed for the duration of the tie-in work. 
  • Motorists and pedestrians will notice road signs and flagging personnel directing them around the work zones. 
  • Please plan your travel routes accordingly and anticipate potential delays. Traffic control measures will be in place to guide motorists safely through the area.
  • Alternative pedestrian routes will be provided, and signage will be posted to direct pedestrians to safe pathways. Refer to Map C for the detour route. 

Project Details

The Potomac River Tunnel is the next major phase of the DC Clean Rivers Project. The project consists of a large-diameter deep sewer tunnel, diversion facilities, drop shafts, and support structures to capture flows from existing combined sewer overflows (CSOs) along the Potomac River and convey them to the Blue Plains Advanced Wastewater Treatment Plant. The project is needed to reduce CSOs that contribute to water quality impairment of the Potomac River and ultimately the Chesapeake Bay; and to comply with the 2005 Federal Consent Decree entered by DC Water, the District of Columbia, the US Environmental Protection Agency, and the US Department of Justice, as amended in January 2016.

CSOs are released into the Potomac River from CSO Outfalls during rainfalls that exceed the system capacity. CSOs impair water quality by increasing water bacteria levels, contributing to low dissolved oxygen impacting aquatic life, and increasing the amount of trash in waterways. An estimated 654 million gallons of CSOs currently enter the Potomac River in a year of average rainfall. The proposed controls are estimated to reduce the volume of CSOs to the Potomac River by 93% and reduce their frequency from approximately 74 events to 4 events in a year of average rainfall.

For more information 

Project Email: dcpotomacrivertunnel@dcwater.com
Dedicated Project Hotline: 202-972-1388
Project Website: www.dcwater.com/prt 
DC Water 24-hour Emergency: 202-612-3400

Latest News

Photo of four workers at NW DC home replacing the lead service line. Worker brings a ladder in.

Online public meeting series starts in November

DC Water is introducing a new webinar series starting in November to share progress reports and helpful information about its Lead Free DC (LFDC) program ...

Workers replacing lead service line at a home in Northwest DC

Additional activities, pop-up event scheduled to highlight value of water   

DC Water joins utilities nationwide today asking the public to ‘Imagine a Day Without Water’ in a National Day of Action to ...

View of the Alexandria Aqueduct

(Washington, DC) –As a part of DC Water’s Potomac River Tunnel Project, temporary traffic lane closures, trail detours, and parking restrictions will extend from Water Street Northwest to the Capital ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

View of the Alexandria Aqueduct
Capital Crescent Trail: Temporary Travel Lane, Trail Detours, and Parking Restrictions

(Washington, DC) –As a part of DC Water’s Potomac River Tunnel Project, temporary traffic lane closures, trail detours, and parking restrictions wi

Latest Blog Post
Photo of Great Falls of the Potomac River with fast moving rapids going over the falls
The Critical Need for a More Resilient Water Source and Protecting the One We Have
Source Water Protection Week highlights the case for second water source.
Upcoming Meeting

Upcoming Events

Nov 14