UPDATE: Potomac Interceptor Overflow, Feburary 2, 2026

February 02, 2026

Cleaning efforts continue today on the Potomac Interceptor, to remove debris and obstructions inside the damaged section of the sewer line. The 72-inch pipe collapsed two weeks ago along Clara Barton Parkway and the 495 interchange and the C & O Canal National Historical Park in Montgomery County, Md.  Here is an update on the ongoing work. 

Potomac Interceptor Overflow Update
Monday, February 2, 2026

Containment

  • The vast majority of flows have been contained.
  • Site containment is capturing residual wastewater from excavation and cleaning, as well as a brief release of wastewater due to a pumping issue.
  • Eight bypass pumps are available to provide plenty of capacity for cleaning and maintenance.
  • Extra shoring was installed at the collapse site to stop erosion and keep things contained.

Excavation and Cleaning

  • Vacuum trucks are clearing pipe blockages, moving carefully toward the damaged section to avoid sending debris downstream.
  • We estimate several hundred tons of debris inside the pipe, though the exact amount is still unclear.
  • So far, we've cleared nine tons of debris from the pipe.
  • Debris includes sections of the damaged pipeline’s interior walls.
  • Cleaning is expected to take multiple days based on the type of debris found and potential for additional debris filling the pipe from the collapse site.
  • A second access point to the sewer pipe for cleaning has been opened downstream.
  • Large rocks and boulders too big for the vacuum are being removed manually from the interceptor slowing the cleaning process.
  • Debris includes sections of the damaged pipeline’s interior walls.
  • Crews and equipment are prepared and ready for potential snow overnight.
  • Heat tents and heating equipment are in place to help mitigate equipment and operational challenges posed by the extreme cold and possible snow.

Environmental Impacts and Evaluation

  • DC Water has hired independent experts to sample water and assess the environmental impact and remediation measures.
  • Early water quality sampling indicates decreasing bacteria levels at the drainage channel by Lock 10 where the sewer overflow had entered the Potomac River, as well as at Fletcher’s Boathouse.
  • More water sampling will be needed to establish a statistical sample size to draw conclusions and establish a trend.
  • We are working to develop cleanup and remediation plans, which remain in the early stages and will be focused on immediately impacted areas such as the canal, drainage channels and portions of the Potomac River.
  • Cleanup measures will be determined in conjunction with federal, state, and local regulatory agencies.

Timeline for Repair

  • A timeline for repair has not been determined.
  • Once cleaning of the failure area is complete, we will assess the damage and determine a plan and timeline for repair.

 

Latest News

Map of lane closure on Clara Barton Parkway at Maryland-DC Border

Drivers should expect delays on Clara Barton Parkway at the Maryland – DC border on Saturday, Sept 26. One lane will be closed from 7 a.m. to 3 p.m. while DC Water makes repairs as part of ongoing ...

Christening of TBM Emily with DC Water Interim General Manager Matt Brown holding bottle of tap water to christen Emily

DC Water celebrated the christening of Emily today. It’s the second giant tunnel boring machine (TBM) that will help build the 5.5-mile Potomac River Tunnel. The celebration continued with Community Day. Residents and families met Emily and stepped inside the tunnel where she will soon begin digging.

Map: Temporary closure of the southbound curb lane on Rock Creek and Potomac Parkway NW

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT

Drivers should expect a temporary southbound lane closure on Rock Creek and Potomac Parkway NW between F St and Virginia Ave on Saturday, September 19, and Sunday, September 20, 2026. The closure will be in place from 7 a.m. to 7 p.m. each day, weather permitting.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Christening of TBM Emily with DC Water Interim General Manager Matt Brown holding bottle of tap water to christen Emily
DC Water Welcomes the Community Underground to See the Potomac River Tunnel and Christens Tunnel Boring Machine Emily

DC Water celebrated the christening of Emily today. It’s the second giant tunnel boring machine (TBM) that will help build the 5.5-mile Potomac River Tunnel. The celebration continued with Community Day. Residents and families met Emily and stepped inside the tunnel where she will soon begin digging.

Latest Blog Post
Emergency supplies arranged on a table, including bottled water, canned food, a backpack, first aid kit, flashlight, phone, medication and other essential items.
Simple Ways to Stay Prepared at Home
A few simple steps can help your household prepare for severe weather and temporary water or sewer service interruptions.
Upcoming Meeting
Date
October 8, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.