UPDATE: Potomac Interceptor Overflow, Feburary 2, 2026

February 02, 2026

Cleaning efforts continue today on the Potomac Interceptor, to remove debris and obstructions inside the damaged section of the sewer line. The 72-inch pipe collapsed two weeks ago along Clara Barton Parkway and the 495 interchange and the C & O Canal National Historical Park in Montgomery County, Md.  Here is an update on the ongoing work. 

Potomac Interceptor Overflow Update
Monday, February 2, 2026

Containment

  • The vast majority of flows have been contained.
  • Site containment is capturing residual wastewater from excavation and cleaning, as well as a brief release of wastewater due to a pumping issue.
  • Eight bypass pumps are available to provide plenty of capacity for cleaning and maintenance.
  • Extra shoring was installed at the collapse site to stop erosion and keep things contained.

Excavation and Cleaning

  • Vacuum trucks are clearing pipe blockages, moving carefully toward the damaged section to avoid sending debris downstream.
  • We estimate several hundred tons of debris inside the pipe, though the exact amount is still unclear.
  • So far, we've cleared nine tons of debris from the pipe.
  • Debris includes sections of the damaged pipeline’s interior walls.
  • Cleaning is expected to take multiple days based on the type of debris found and potential for additional debris filling the pipe from the collapse site.
  • A second access point to the sewer pipe for cleaning has been opened downstream.
  • Large rocks and boulders too big for the vacuum are being removed manually from the interceptor slowing the cleaning process.
  • Debris includes sections of the damaged pipeline’s interior walls.
  • Crews and equipment are prepared and ready for potential snow overnight.
  • Heat tents and heating equipment are in place to help mitigate equipment and operational challenges posed by the extreme cold and possible snow.

Environmental Impacts and Evaluation

  • DC Water has hired independent experts to sample water and assess the environmental impact and remediation measures.
  • Early water quality sampling indicates decreasing bacteria levels at the drainage channel by Lock 10 where the sewer overflow had entered the Potomac River, as well as at Fletcher’s Boathouse.
  • More water sampling will be needed to establish a statistical sample size to draw conclusions and establish a trend.
  • We are working to develop cleanup and remediation plans, which remain in the early stages and will be focused on immediately impacted areas such as the canal, drainage channels and portions of the Potomac River.
  • Cleanup measures will be determined in conjunction with federal, state, and local regulatory agencies.

Timeline for Repair

  • A timeline for repair has not been determined.
  • Once cleaning of the failure area is complete, we will assess the damage and determine a plan and timeline for repair.

 

Latest News

Bypass pumps in operation to reroute wastewater around the break

Potomac Interceptor Repairs Update

February 15, 2026 

  • No overflow events impacting surface waters have been reported in the past 24 hours.
  • The four high-capacity bypass pumps installed this week are now ...
Photo of access pit upstream with four pumps lined up ready for installation

Crews have completed construction of the two new access pits to support full installation of the enhanced bypass pumping system. Three high-capacity bypass pumps have been installed and are operational, with a fourth pump expected to be activated later tonight or early Sunday ahead of the forecasted weather to help manage anticipated higher flows associated with rainfall and snowmelt.

Placeholder DC Water Image

No overflow events impacting surface waters have been reported in the past 24 hours as crews continue advancing construction of the two new access pits to support full installation of the enhanced bypass pumping system. Additional high-capacity bypass pumps are on site in advance of the forecasted weather on Sunday to help manage anticipated higher flows associated with rainfall and snowmelt.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.