UPDATE: Potomac Interceptor Overflow, Feburary 2, 2026

February 02, 2026

Cleaning efforts continue today on the Potomac Interceptor, to remove debris and obstructions inside the damaged section of the sewer line. The 72-inch pipe collapsed two weeks ago along Clara Barton Parkway and the 495 interchange and the C & O Canal National Historical Park in Montgomery County, Md.  Here is an update on the ongoing work. 

Potomac Interceptor Overflow Update
Monday, February 2, 2026

Containment

  • The vast majority of flows have been contained.
  • Site containment is capturing residual wastewater from excavation and cleaning, as well as a brief release of wastewater due to a pumping issue.
  • Eight bypass pumps are available to provide plenty of capacity for cleaning and maintenance.
  • Extra shoring was installed at the collapse site to stop erosion and keep things contained.

Excavation and Cleaning

  • Vacuum trucks are clearing pipe blockages, moving carefully toward the damaged section to avoid sending debris downstream.
  • We estimate several hundred tons of debris inside the pipe, though the exact amount is still unclear.
  • So far, we've cleared nine tons of debris from the pipe.
  • Debris includes sections of the damaged pipeline’s interior walls.
  • Cleaning is expected to take multiple days based on the type of debris found and potential for additional debris filling the pipe from the collapse site.
  • A second access point to the sewer pipe for cleaning has been opened downstream.
  • Large rocks and boulders too big for the vacuum are being removed manually from the interceptor slowing the cleaning process.
  • Debris includes sections of the damaged pipeline’s interior walls.
  • Crews and equipment are prepared and ready for potential snow overnight.
  • Heat tents and heating equipment are in place to help mitigate equipment and operational challenges posed by the extreme cold and possible snow.

Environmental Impacts and Evaluation

  • DC Water has hired independent experts to sample water and assess the environmental impact and remediation measures.
  • Early water quality sampling indicates decreasing bacteria levels at the drainage channel by Lock 10 where the sewer overflow had entered the Potomac River, as well as at Fletcher’s Boathouse.
  • More water sampling will be needed to establish a statistical sample size to draw conclusions and establish a trend.
  • We are working to develop cleanup and remediation plans, which remain in the early stages and will be focused on immediately impacted areas such as the canal, drainage channels and portions of the Potomac River.
  • Cleanup measures will be determined in conjunction with federal, state, and local regulatory agencies.

Timeline for Repair

  • A timeline for repair has not been determined.
  • Once cleaning of the failure area is complete, we will assess the damage and determine a plan and timeline for repair.

 

Latest News

image of clara barton parkway with lane closure marked in red

Beginning this week and continuing through mid-August, DC Water will temporarily close one lane overnight on Clara Barton Parkway at the Maryland-D.C. border. The closures are needed so crews can ...

Pennyfield Lock Potomac Interceptor bypass pipeline running next to C & O Canal with equipment

There is no active spill or overflow. Work to strengthen the pipe to begin soon.

Today, DC Water completed construction on a temporary bypass system as part of sewer repairs on the Potomac Interceptor near Pennyfield Lock in Potomac, Maryland. Crews turned on the pumps and successfully tested the system. With the bypass now ready, it will allow us to begin the emergency repairs inside the pipe by carrying the wastewater around the repair area.

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking
DC Water Breaks Ground on Piney Branch Tunnel, Final Phase of DC Clean Rivers Project

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Latest Blog Post
Five photos from the American Water Works Association (AWWA) ACE26 conference featuring panel discussions, technical presentations, networking, and attendees posing at the ACE26 display.
ACE26 Highlights: How DC Water Advanced the Conversation on Water
More than 80 DC Water employees joined thousands of water professionals in Washington, D.C., sharing expertise, building partnerships and advancing conversations that will help shape the future of water.
Upcoming Meeting
Date
July 23, 2026
Thursday, 9:30 AM

Upcoming Events

Jul 23
Jul 25

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.