Emergency Water Outage
Apr 02, 2026 | 06:30 PM

Emergency Water Outage
Apr 02, 2026 | 05:30 PM

UPDATE: Potomac Interceptor Cleaning and Repair Effort, February 4, 2026

February 04, 2026
Three workers over the pit accessing the Potomac Interceptor for Cleaning

DC Water and its contractor are working to clean debris from a damaged section of the Potomac Interceptor, a sanitary sewer line that collapsed on January 19, along Clara Barton Parkway and the 495 interchange and the C & O Canal National Historical Park. While limited overflows occurred earlier in the week, no overflows from the site were reported today. Here is an update on the cleaning and repair efforts underway:

Containment Efforts

  • No overflow from the pipe was reported today.
  • The pump installed at the collapse site is effectively managing wastewater levels within the sinkhole and preventing overflow.
  • Wastewater continues to be pumped out and discharged further downstream into the Potomac Interceptor.
  • Potential overflow risks remain due to increased inflows from snowmelt, peak wastewater periods, and periodic pump clogs.
  • On-site containment measures and bypass pumping operations continue to   successfully limit the risk of overflow.

Cleaning Efforts

  • Active removal of blockages from the collapsed pipe is ongoing.
  • Large rocks and boulders that entered the pipe during the collapse are too big for vacuum equipment, presenting significant challenges.
  • Manual removal of rocks is necessary, requiring personnel to enter the access pit with live flow of wastewater.
  • CCTV inspection is planned to better determine the extent of the rock dam and blockage inside the damaged pipe.
  • 3D LiDAR scanning is planned to assess the structural integrity of the pipe around the damaged pipe.
  • These measures are critical to confirm the integrity of the adjacent pipe sections prior to restoring full flow and reducing the risk of additional failures.

Pumping Operation

  • Bypass pumps continue to operate stably with periodic maintenance required due to clogs from wipes and improperly disposed fats, oils, and grease.
  • A secondary access point is being constructed upstream of the collapse for improved wastewater pumping flexibility.
  • Additional pumps are being brought in to support operations from the new access point.
  • These measures are intended to reduce flows through the collapse site and improve safety and efficiency during debris and rock removal activities.

Environmental Impact and Evaluation

  • Limited overflows into the Potomac River have resulted in slight increases in coliform levels near Lock 10 over the past two days.
  • More water sampling will be needed to establish a statistical sample size to draw conclusions and establish a trend.
  • Independent environmental experts are conducting ongoing water quality monitoring. 
  • DC Water continues to coordinate with federal, state, and local regulators on environmental evaluation and restoration planning.

 

Latest News

Excavators in the canal digging up soil and another excavator removing the soil to a dump truck to be hauled away

DC Water and its contractor have made significant progress on soil removal, reaching the clay liner between locks 13 and 14 of the C & O Canal, which was used as a bypass for wastewater during the Potomac Interceptor repairs.

Work continues to remove sludge between locks 10 and 13, which is expected to be completed by mid- to late-April. The soil will then be removed down to the clay liner as the final step, and the canal reconstructed to meet National Park Service specifications.

Soil Removal Underway with Excavator in Canal

Today, DC Water and its contractors began removing contaminated soil between locks 13 and 14 in the C & O Canal, which was used as a temporary bypass during the Potomac Interceptor repair effort. Clean-up efforts are ongoing at Lock 10 with work to remove sludge now getting underway between locks 11 and 13.

Aerial shot of Blue Plains Advanced Wastewater Treatement Plant

Series 2026 Bond Transaction Delivers Significant Long-Term Cost Savings

DC Water has closed on a refinancing deal for its Series 2026 bonds that will save customers millions of dollars and keep rates affordable across the District. The refinancing transaction, which closed this month, delivers approximately $54 million in budget savings over the next twenty years, directly benefiting DC ratepayers through reduced costs.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Map of lane closure
Traffic Advisory: Rock Creek and Potomac Parkway NW Lane Closure Beginning Jan 19

Beginning on or about January 19, 2026, weather permitting, DC Water will implement a temporary lane closure on Rock Creek and Potomac Parkway NW b

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
April 7, 2026
Tuesday, 9:30 AM

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.