UPDATE: Potomac Interceptor Cleaning and Repair Effort, February 4, 2026

February 04, 2026
Three workers over the pit accessing the Potomac Interceptor for Cleaning

DC Water and its contractor are working to clean debris from a damaged section of the Potomac Interceptor, a sanitary sewer line that collapsed on January 19, along Clara Barton Parkway and the 495 interchange and the C & O Canal National Historical Park. While limited overflows occurred earlier in the week, no overflows from the site were reported today. Here is an update on the cleaning and repair efforts underway:

Containment Efforts

  • No overflow from the pipe was reported today.
  • The pump installed at the collapse site is effectively managing wastewater levels within the sinkhole and preventing overflow.
  • Wastewater continues to be pumped out and discharged further downstream into the Potomac Interceptor.
  • Potential overflow risks remain due to increased inflows from snowmelt, peak wastewater periods, and periodic pump clogs.
  • On-site containment measures and bypass pumping operations continue to   successfully limit the risk of overflow.

Cleaning Efforts

  • Active removal of blockages from the collapsed pipe is ongoing.
  • Large rocks and boulders that entered the pipe during the collapse are too big for vacuum equipment, presenting significant challenges.
  • Manual removal of rocks is necessary, requiring personnel to enter the access pit with live flow of wastewater.
  • CCTV inspection is planned to better determine the extent of the rock dam and blockage inside the damaged pipe.
  • 3D LiDAR scanning is planned to assess the structural integrity of the pipe around the damaged pipe.
  • These measures are critical to confirm the integrity of the adjacent pipe sections prior to restoring full flow and reducing the risk of additional failures.

Pumping Operation

  • Bypass pumps continue to operate stably with periodic maintenance required due to clogs from wipes and improperly disposed fats, oils, and grease.
  • A secondary access point is being constructed upstream of the collapse for improved wastewater pumping flexibility.
  • Additional pumps are being brought in to support operations from the new access point.
  • These measures are intended to reduce flows through the collapse site and improve safety and efficiency during debris and rock removal activities.

Environmental Impact and Evaluation

  • Limited overflows into the Potomac River have resulted in slight increases in coliform levels near Lock 10 over the past two days.
  • More water sampling will be needed to establish a statistical sample size to draw conclusions and establish a trend.
  • Independent environmental experts are conducting ongoing water quality monitoring. 
  • DC Water continues to coordinate with federal, state, and local regulators on environmental evaluation and restoration planning.

 

Latest News

Section of Potomac River in Cabin John, MD showing river and trees

Testing will continue through September 10 at six Maryland locations closest to January sewer collapse

DC Water is moving from daily Potomac River water quality testing to testing twice a week. The change is part of our continued response to the January Potomac Interceptor sewer collapse. Daily testing continued past the original July 31 end date and today will be the last day DC Water will test at the 10 current locations.

Map: Temporary southbound lane closure on Rock Creek and Potomac Parkway NW.

Starting on or about Aug. 7, 2026, weather permitting, drivers can expect a temporary lane closure southbound on Rock Creek and Potomac Parkway NW near the intersection of Virginia Avenue NW and F ...

Photo of inside Potomac Interceptor at Dulles showing newly lined tunnel

First of four emergency repairs on Potomac Interceptor finished

DC Water has finished the first of four emergency repair projects on the Potomac Interceptor sewer line. Crews completed work today to strengthen a 600-foot section of pipe at Dulles International Airport.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Latest Blog Post
Plastic bottles, cups and other floating debris on the surface of the Anacostia River before the Anacostia River Tunnel began operating.
Cleaner Waterways Start With Everyday Choices
Protecting our waterways starts with everyday actions and continues through critical infrastructure designed to keep pollution out of our rivers.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.