EMERGENCY WATER OUTAGE
Feb 04, 2026 | 03:00 PM

Emergency Water Outage
Feb 04, 2026 | 03:30 PM

EMERGENCY WATER OUTAGE
Feb 04, 2026 | 01:30 PM

UPDATE: Potomac Interceptor Cleaning and Repair Effort, February 4, 2026

February 04, 2026
Three workers over the pit accessing the Potomac Interceptor for Cleaning

DC Water and its contractor are working to clean debris from a damaged section of the Potomac Interceptor, a sanitary sewer line that collapsed on January 19, along Clara Barton Parkway and the 495 interchange and the C & O Canal National Historical Park. While limited overflows occurred earlier in the week, no overflows from the site were reported today. Here is an update on the cleaning and repair efforts underway:

Containment Efforts

  • No overflow from the pipe was reported today.
  • The pump installed at the collapse site is effectively managing wastewater levels within the sinkhole and preventing overflow.
  • Wastewater continues to be pumped out and discharged further downstream into the Potomac Interceptor.
  • Potential overflow risks remain due to increased inflows from snowmelt, peak wastewater periods, and periodic pump clogs.
  • On-site containment measures and bypass pumping operations continue to   successfully limit the risk of overflow.

Cleaning Efforts

  • Active removal of blockages from the collapsed pipe is ongoing.
  • Large rocks and boulders that entered the pipe during the collapse are too big for vacuum equipment, presenting significant challenges.
  • Manual removal of rocks is necessary, requiring personnel to enter the access pit with live flow of wastewater.
  • CCTV inspection is planned to better determine the extent of the rock dam and blockage inside the damaged pipe.
  • 3D LiDAR scanning is planned to assess the structural integrity of the pipe around the damaged pipe.
  • These measures are critical to confirm the integrity of the adjacent pipe sections prior to restoring full flow and reducing the risk of additional failures.

Pumping Operation

  • Bypass pumps continue to operate stably with periodic maintenance required due to clogs from wipes and improperly disposed fats, oils, and grease.
  • A secondary access point is being constructed upstream of the collapse for improved wastewater pumping flexibility.
  • Additional pumps are being brought in to support operations from the new access point.
  • These measures are intended to reduce flows through the collapse site and improve safety and efficiency during debris and rock removal activities.

Environmental Impact and Evaluation

  • Limited overflows into the Potomac River have resulted in slight increases in coliform levels near Lock 10 over the past two days.
  • More water sampling will be needed to establish a statistical sample size to draw conclusions and establish a trend.
  • Independent environmental experts are conducting ongoing water quality monitoring. 
  • DC Water continues to coordinate with federal, state, and local regulators on environmental evaluation and restoration planning.

 

Latest News

Three workers over the pit accessing the Potomac Interceptor for Cleaning

DC Water and its contractor are working to clean debris from a damaged section of the Potomac Interceptor, a sanitary sewer line that collapsed on January 19, along Clara Barton Parkway and the 495 ...

Picture of the work site where cleaning is taking place and pumps being installed

Potomac Interceptor Overflow Update
Tuesday, February 3, 2026

 Work to clean and repair the damaged section of the Potomac Interceptor continues, though progress is being slowed by large boulders and ...

Placeholder DC Water Image

Cleaning efforts continue today on the Potomac Interceptor, to remove debris and obstructions inside the damaged section of the sewer line. The 72-inch pipe collapsed two weeks ago along Clara Barton ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 5, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.