UPDATE: Potomac Interceptor Cleaning and Repair Effort, February 4, 2026

February 04, 2026
Three workers over the pit accessing the Potomac Interceptor for Cleaning

DC Water and its contractor are working to clean debris from a damaged section of the Potomac Interceptor, a sanitary sewer line that collapsed on January 19, along Clara Barton Parkway and the 495 interchange and the C & O Canal National Historical Park. While limited overflows occurred earlier in the week, no overflows from the site were reported today. Here is an update on the cleaning and repair efforts underway:

Containment Efforts

  • No overflow from the pipe was reported today.
  • The pump installed at the collapse site is effectively managing wastewater levels within the sinkhole and preventing overflow.
  • Wastewater continues to be pumped out and discharged further downstream into the Potomac Interceptor.
  • Potential overflow risks remain due to increased inflows from snowmelt, peak wastewater periods, and periodic pump clogs.
  • On-site containment measures and bypass pumping operations continue to   successfully limit the risk of overflow.

Cleaning Efforts

  • Active removal of blockages from the collapsed pipe is ongoing.
  • Large rocks and boulders that entered the pipe during the collapse are too big for vacuum equipment, presenting significant challenges.
  • Manual removal of rocks is necessary, requiring personnel to enter the access pit with live flow of wastewater.
  • CCTV inspection is planned to better determine the extent of the rock dam and blockage inside the damaged pipe.
  • 3D LiDAR scanning is planned to assess the structural integrity of the pipe around the damaged pipe.
  • These measures are critical to confirm the integrity of the adjacent pipe sections prior to restoring full flow and reducing the risk of additional failures.

Pumping Operation

  • Bypass pumps continue to operate stably with periodic maintenance required due to clogs from wipes and improperly disposed fats, oils, and grease.
  • A secondary access point is being constructed upstream of the collapse for improved wastewater pumping flexibility.
  • Additional pumps are being brought in to support operations from the new access point.
  • These measures are intended to reduce flows through the collapse site and improve safety and efficiency during debris and rock removal activities.

Environmental Impact and Evaluation

  • Limited overflows into the Potomac River have resulted in slight increases in coliform levels near Lock 10 over the past two days.
  • More water sampling will be needed to establish a statistical sample size to draw conclusions and establish a trend.
  • Independent environmental experts are conducting ongoing water quality monitoring. 
  • DC Water continues to coordinate with federal, state, and local regulators on environmental evaluation and restoration planning.

 

Latest News

Photo of LFDC workers digging

DC Water's Lead Free DC Program accelerated its work across all eight wards last year, replacing 43% more lead service lines in Fiscal Year 2025 than the prior year. This marks a significant achievement for the program in the newly released annual report on Lead Free DC.

graphic with meeting information

We hope to see you tonight for our upcoming Lead Free DC Virtual Meeting! We will discuss Losing the Lead Without Losing Your Yard. This session is an in-depth look at an important concern for many homeowners: how Lead Free DC restores your yard following a lead service line replacement.

Photo of Potomac River at the overflow location

Hundreds of Sampling Results Confirm Return to Normal Bacteria Levels in Potomac River

DC Water has outlined its next steps to complete the environmental cleanup and its plan for continued water quality monitoring this summer, as part of the ongoing response to January’s failure in the Potomac Interceptor sewer pipeline. The plan, submitted to the Maryland Department of the Environment (MDE), is supported by extensive data from hundreds of samples.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Placeholder DC Water Image
Piney Branch Parkway Temporary Closure and Relocation

DC Water has nearly completed construction site preparation for the Piney Branch Tunnel project, including tree removal, and installation of fences

Latest Blog Post
DC Water General Manager and CEO David Gadis recognizes Lily MacDonald during the May Board of Directors meeting.
From Classroom to Community: A Student Spotlight on DC Water's SPLASH Program
A speechwriting assignment became a call to action for water access and affordability through DC Water's SPLASH program.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.