UPDATE: Potomac Interceptor Cleaning and Repair Effort, February 4, 2026

February 04, 2026
Three workers over the pit accessing the Potomac Interceptor for Cleaning

DC Water and its contractor are working to clean debris from a damaged section of the Potomac Interceptor, a sanitary sewer line that collapsed on January 19, along Clara Barton Parkway and the 495 interchange and the C & O Canal National Historical Park. While limited overflows occurred earlier in the week, no overflows from the site were reported today. Here is an update on the cleaning and repair efforts underway:

Containment Efforts

  • No overflow from the pipe was reported today.
  • The pump installed at the collapse site is effectively managing wastewater levels within the sinkhole and preventing overflow.
  • Wastewater continues to be pumped out and discharged further downstream into the Potomac Interceptor.
  • Potential overflow risks remain due to increased inflows from snowmelt, peak wastewater periods, and periodic pump clogs.
  • On-site containment measures and bypass pumping operations continue to   successfully limit the risk of overflow.

Cleaning Efforts

  • Active removal of blockages from the collapsed pipe is ongoing.
  • Large rocks and boulders that entered the pipe during the collapse are too big for vacuum equipment, presenting significant challenges.
  • Manual removal of rocks is necessary, requiring personnel to enter the access pit with live flow of wastewater.
  • CCTV inspection is planned to better determine the extent of the rock dam and blockage inside the damaged pipe.
  • 3D LiDAR scanning is planned to assess the structural integrity of the pipe around the damaged pipe.
  • These measures are critical to confirm the integrity of the adjacent pipe sections prior to restoring full flow and reducing the risk of additional failures.

Pumping Operation

  • Bypass pumps continue to operate stably with periodic maintenance required due to clogs from wipes and improperly disposed fats, oils, and grease.
  • A secondary access point is being constructed upstream of the collapse for improved wastewater pumping flexibility.
  • Additional pumps are being brought in to support operations from the new access point.
  • These measures are intended to reduce flows through the collapse site and improve safety and efficiency during debris and rock removal activities.

Environmental Impact and Evaluation

  • Limited overflows into the Potomac River have resulted in slight increases in coliform levels near Lock 10 over the past two days.
  • More water sampling will be needed to establish a statistical sample size to draw conclusions and establish a trend.
  • Independent environmental experts are conducting ongoing water quality monitoring. 
  • DC Water continues to coordinate with federal, state, and local regulators on environmental evaluation and restoration planning.

 

Latest News

image of clara barton parkway with lane closure marked in red

Beginning this week and continuing through mid-August, DC Water will temporarily close one lane overnight on Clara Barton Parkway at the Maryland-D.C. border. The closures are needed so crews can ...

Pennyfield Lock Potomac Interceptor bypass pipeline running next to C & O Canal with equipment

There is no active spill or overflow. Work to strengthen the pipe to begin soon.

Today, DC Water completed construction on a temporary bypass system as part of sewer repairs on the Potomac Interceptor near Pennyfield Lock in Potomac, Maryland. Crews turned on the pumps and successfully tested the system. With the bypass now ready, it will allow us to begin the emergency repairs inside the pipe by carrying the wastewater around the repair area.

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking
DC Water Breaks Ground on Piney Branch Tunnel, Final Phase of DC Clean Rivers Project

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Latest Blog Post
Five photos from the American Water Works Association (AWWA) ACE26 conference featuring panel discussions, technical presentations, networking, and attendees posing at the ACE26 display.
ACE26 Highlights: How DC Water Advanced the Conversation on Water
More than 80 DC Water employees joined thousands of water professionals in Washington, D.C., sharing expertise, building partnerships and advancing conversations that will help shape the future of water.
Upcoming Meeting
Date
July 23, 2026
Thursday, 9:30 AM

Upcoming Events

Jul 23
Jul 25

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.