UPDATE: Crews Nearing Start of Repairs for Potomac Interceptor as Cleaning Continues

February 27, 2026
Photo of workers doing environmental rehab site preps

Potomac Interceptor Repairs Update
February 27, 2026

  • No overflows reaching the Potomac River for 19 days. The last release to enter the river occurred on February 8.
  • Cleaning continues in the area upstream of the damaged section of the Potomac Interceptor to remove muck, debris, and smaller rocks.
  • Crews were able to reach some of the additional large rocks downstream of the collapsed section and remove them without additional excavation.
  • Once the pipe is cleared, the next steps include a CCTV inspection inside the pipe, followed by pressure washing the walls, and the application of a geopolymer lining – a substance as strong as concrete – to strengthen and rehabilitate the pipe.
  • Site preparations have begun for the environmental rehabilitation which is expected to start this weekend.
  • Work remains on schedule to complete the emergency repair by mid-March. 

DC Water remains committed to protecting public health and safety and ensuring the immediate areas around the collapse site and areas of the Potomac River are rehabilitated.

Water Quality Sampling

DC Water is performing daily water quality sampling. It’s important to note that historically the E. coli levels in the Potomac and Anacostia rivers vary widely from day to day. This is reflected in recent sampling results with stormwater runoff from rain and snow impacting water quality. Fluctuations in water quality are influenced by factors such as weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways.

Given these variables, measurements taken much further downstream cannot be attributed solely to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day.

A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs

Below are the results of sampling during the period from February 16 – present. Past results may be found on our dedicated Potomac Interceptor Response page.

graphic of water quality sampling results

 

For more information about the Potomac Interceptor response efforts go to dcwater.com/potomac-interceptor-collapse.

 

Latest News

Photo of Potomac River at the overflow location

Hundreds of Sampling Results Confirm Return to Normal Bacteria Levels in Potomac River

DC Water has outlined its next steps to complete the environmental cleanup and its plan for continued water quality monitoring this summer, as part of the ongoing response to January’s failure in the Potomac Interceptor sewer pipeline. The plan, submitted to the Maryland Department of the Environment (MDE), is supported by extensive data from hundreds of samples.

crews removing soil in C & O Canal

Work continues to remove the remaining soil between locks 10 and 12 of the C & O Canal which was used as an emergency bypass while the Potomac Interceptor was repaired. Crews area also removing plants, trees, and shrubs in preparation for the long-term rehabilitation of the Potomac Interceptor.

Placeholder DC Water Image

DC Water has nearly completed construction site preparation for the Piney Branch Tunnel project, including tree removal, and installation of fences, erosion and sediment controls, utilities, and ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Placeholder DC Water Image
Piney Branch Parkway Temporary Closure and Relocation

DC Water has nearly completed construction site preparation for the Piney Branch Tunnel project, including tree removal, and installation of fences

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

May 16
2:00 pm - 6:00 pm
May 20

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.