Soil Removal Underway on Section of C & O Canal

March 31, 2026
Soil Removal Underway with Excavator in Canal
  • Today, DC Water and its contractors began removing contaminated soil between locks 13 and 14 in the C & O Canal, which was used as a temporary bypass during the Potomac Interceptor repair effort.
  • Crews will remove the soil down to the clay liner and reconstruct the canal to National Park Service specifications.
  • Clean-up efforts continue at Lock 10, with sludge removal now underway between locks 11 and 13.
  • Beautification and revegetation efforts are pending evaluation of soil sampling in the areas directly impacted by the overflow, including the drainage channel, Culvert 12 (Rock Run Culvert), and the tributary to the Potomac River.
  • Demobilization of the pumping site continues, and work is underway to prepare the site for the previously planned long-term rehabilitation of 2700 linear feet of the Potomac Interceptor that has been accelerated in this area.
  • Crews have begun clearing brush and trees to begin excavation on a section of the pipeline outside the I-495 Beltway, where a trench box is being installed with supportive excavation. The site will be used for slip lining, a process where new pipe sections are inserted into the existing pipe to rehabilitate it to like-new condition.
  • This is one of three locations that will be used for slip lining, including the open pipe sections where the collapse occurred and the opening for the bypass pumps. Each site provides a long, straight section necessary to slip line.
  • Ground penetrating radar is being used to look for rocks and boulders in the area that could pose additional risk, like the blockage that occurred during the collapse.
  • An aerial assessment of the 54-mile Potomac Interceptor is underway and will continue through the end of the week. Drones equipped with LiDAR scanning are being used to map current site conditions along the Potomac Interceptor alignment.
  • The data will provide a better understanding of the changing landscape and development as part of strategic planning for DC Water’s ongoing 10-year, $625 million rehabilitation of the interceptor.

Water Quality Sampling Results

It's important to understand that rain, snow, heat, contaminated runoff, and natural sources of E. coli such as wildlife can cause higher bacteria levels in urban rivers such as the Potomac River. 

As there have been no overflows to the river from the Potomac Interceptor for more than a month prior to completion of emergency repairs, recent fluctuations in measurements are more likely due to these other known factors.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs.

Sample results from March 23 - present. Past results may be found here.

Graphic of water quality sampling results

For the latest updates and information, including how to provide feedback on the environmental rehabilitation, go to our dedicated Potomac Interceptor Response page.

Latest News

Photo of surcharge coming out of a manhole and flooding on South Capitol St

DC Water crews are responding to South Capitol St and Firth Stirling Ave SE due flooding caused by the excessive stormwater entering the sewer system. South Capitol Street SE is closed in both directions between the Frederick Douglass Memorial Bridge and the intersection of Firth Stirling Ave and Defense Blvd.

Workers in the excavation pit with the sliplining complete and the pipe sealed

Fourth and final repair at Pennyfield Lock is expected to be done next month

DC Water is nearing the finish line on emergency repairs to the Potomac Interceptor sewer line. DC Water and its contractors finished repairs along Clara Barton Parkway at the Maryland–DC border. It is the third of four emergency repairs identified earlier this year to be completed following a full inspection of the 54-mile sewer line.

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m. - 1 p.m. while tree removal equipment is delivered to DC Water’s Park Road construction site ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains
TRAFFIC ADVISORY: Temporary Road Closure for Equipment Delivery May cause delays on Park Road NW

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m.

Latest Blog Post
Before-and-after comparison of a 12-inch blowoff connected to a 36-inch water main near Massachusetts Avenue and Macomb Street NW. The images show the inside of the structure before the repair, repair work around the pipe, and the interior after the repair was completed.
One Repair, Millions of Gallons Saved
How Teamwork Helped DC Water Stop Hidden Water Loss
Upcoming Meeting
Date
December 22, 2026
Tuesday, 11:00 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.