Sludge Removal Complete between locks 13 and 14, work continues on remaining C & O Canal sections

March 24, 2026
  • DC Water has completed sludge removal on a section of the C & O Canal between locks 13 and 14, which was used as a bypass to divert wastewater around the collapsed section of the Potomac Interceptor and back into the pipe further downstream. Crews are now constructing an access bridge to this section of the canal to allow soil removal to begin.
  • Work continues to clear sludge and debris from the remaining sections of the canal between locks 10 and 13.
  • Approximately 3100 feet of the canal is being cleaned and the soil removed down to the clay liner. Crews, working in coordination with National Park Service, will then rebuild the canal to NPS’s specifications.
  • DC Water continues working with National Park Service in developing plans to rehabilitate and clean the historic locks.
  • The initial clean-up and temporary stabilization are complete on the areas directly impacted by the overflows, including the drainage channel, Culvert 12 (Rock Run Culvert), the tributary, and portions of the Potomac River and shoreline where the overflow occurred.
  • Beautification and revegetation in these areas is pending results from soil sampling taken by the Environmental Protection Agency to verify clean-up efforts and determine if additional rehabilitation is necessary.
  • As part of the beautification and revegetation, native species will be replanted. Additional native trees will be planted in the fall which is the best time to plant to avoid heat stress during the summer.
  • DC Water is working with Maryland Department of the Environment to establish sediment testing locations and protocols.

Water Quality Sampling Results

It's important to understand that rain, snow, heat, contaminated runoff, and natural sources of E. coli such as wildlife can cause higher bacteria levels in urban rivers such as the Potomac. For this reason, experts recommend avoiding the water for at least 48-72 hours after heavy rain. This is reflected in the data last week, where significant spikes are seen that coincide with heavy rainfall including areas upstream where measurements are unrelated to the overflow event.

As there have been no overflows to the river from the Potomac Interceptor for more than a month prior to completion of emergency repairs, fluctuations in measurements are more likely due to these other known factors.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs.

Sample results from March 16 - present. Past results may be found here.

graphic of water quality sampling

For the latest updates and information, including how to provide feedback on the environmental rehabilitation, go to our dedicated Potomac Interceptor Response page.

Latest News

Overhead Photo of Potomac Interceptor

Comprehensive Survey to Guide Rehabilitation and Address Changing Site Conditions

Starting later this week, DC Water will conduct an aerial drone assessment along the 54-mile Potomac Interceptor (PI) to evaluate current site conditions and better understand the changing landscape and development along the Potomac Interceptor alignment, including areas where there may be rocks or boulders that need further on the ground inspections.

Placeholder DC Water Image

DC Water has completed sludge removal on a section of the C & O Canal between locks 13 and 14, which was used as a bypass to divert wastewater around the collapsed section of the Potomac Interceptor and back into the pipe further downstream. Crews are now constructing an access bridge to this section of the canal to allow soil removal to begin.

Workers doing ongoing rehabilitation work

As work nears completion on the initial clean-up and temporary stabilization of the areas directly impacted by the Potomac Interceptor overflows, DC Water is beginning preparations for beautification and revegetation to restore native plants, trees, and shrubs.

Before moving to the next phase of environmental rehabilitation, DC Water is working with the Environmental Protection Agency to conduct soil sampling to verify the clean-up efforts.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.