Restoration complete: 3rd Street Tunnel reopened in entirety

August 29, 2021
3rd Street Tunnel

Tonight, DC Water and the District Department of Transportation (DDOT) plan to reopen the 3rd Street Tunnel and I-395 roadway at 11 pm on Sunday, August 29, well ahead of the Monday morning rush hour. The announcement comes after the pair of agencies completed seven days of investigation, repair and restoration.

The tunnel closure began in the early hours of Monday, August 23, when a broken water main flooded the roadway. DC Water first isolated the water main break to stop the flow of water into the tunnel and then restored water service to all customers. Upon identifying the exact location of the break, crews repaired the water main.

Next, crews spent several days assessing damage, backfilling voids caused by the force of the water, and performing concrete and pavement repairs. Tonight, both DDOT and DC Water walked through the tunnel for a final inspection before reopening the roadway.

“We thank you for your patience,” commented David L. Gadis, DC Water’s CEO and General Manager. “This has truly been a collaborative effort. Numerous agencies responded initially, and several have worked hand-in-hand as we diagnosed problems and planned and executed repairs this past week. DDOT inspectors were with us, approving repairs as we proceeded, which sped up the process and created a new model of agency coordination. We learned some valuable lessons that we will carry forward.”

“I am incredibly proud of the hard work that the DDOT team has done over the last six days in lock step with DC Water, our colleagues at DC Homeland Security Agency and the Metropolitan Police Department,” said Acting DDOT Director Everett Lott. “This water main break and the subsequent tunnel closure reminds us why Mayor Bowser’s commitment to strengthening our infrastructure is critical to the safety of our city and our region.”

Latest News

Photo of completed repair with concrete encasing the sewr pipe

DC Water has successfully completed emergency repairs on a critical section of the Anacostia Force Main following a failure near Anacostia Avenue and Ponds Street Northeast in July. With repairs finalized, attention now turns to rehabilitating other vulnerable segments of the 6.25-mile pipeline to ensure long-term reliability and resilience. 

Map of construction area on Clara Barton Parkway near I495

DC Water will be doing construction as part of a sanitary sewer rehabilitation project on Clara Barton Parkway in Maryland from Sept 8 - Oct 10, 2025, which may cause delays inbound near the I-495 Beltway interchange. One lane will be closed in the work zone to reline an 800-foot section of the sewer line, known as the Potomac Inteceptor. Access to the inner and outer loops of the Beltway will remain available.

Rock Creek Trail Site for Potomac River Tunnel Project

Starting the week of August 25, DC Water will take another big step forward in the Potomac River Tunnel Project. Ground stabilization will begin at the Rock Creek Trail site, near the Watergate Complex, to drill secant piles that will form a retaining wall for the drop shaft.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Rock Creek Trail Site for Potomac River Tunnel Project
Ground Stabilization Work Begins Near Watergate Complex, starting Aug 25

Starting the week of August 25, DC Water will take another big step forward in the Potomac River Tunnel Project. Ground stabilization will begin at the Rock Creek Trail site, near the Watergate Complex, to drill secant piles that will form a retaining wall for the drop shaft.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
September 18, 2025
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.