Northbound Lanes of 14th Street NW Reopen Following Emergency Repairs to Abandoned Sewer Tunnel

February 13, 2026
Photo of concrete being poured through a manhole or access point

Tonight, DC Water has reopened the northbound lanes of 14th Street NW between L Street and Thomas Circle, following the successful completion of emergency repairs to a century-old, abandoned sewer tunnel beneath the roadway. These repairs took place over the past week, ensuring the safety and stability of this critical thoroughfare.

The emergency work focused on filling and sealing an old, brick-lined sewer tunnel that was found to be compromised and at risk of collapse. To resolve this issue, DC Water crews used specialized flowable fill concrete material, which provides superior reinforcement and rapid stabilization. Crews carefully placed 200 cubic feet of concrete into the tunnel over several days, filling 600 linear feet of tunnel to reinforce and stabilize the area beneath the street.

A water main break repair had led to the discovery that the sewer tunnel was not properly filled and sealed when abandoned more than 50 years ago. That prompted DC Water to inspect the tunnel and assess the condition. Using CCTV cameras, the inspection found a 70-foot crack in the crown that compromised the structural integrity. Working in close coordination with the District Department of Transportation, emergency lane closures were implemented immediately out of an abundance of caution and to protect public safety.

DC Water crews worked through the week on a comprehensive stabilization effort and to get the road reopened as soon as safely possible. The repair process involved pouring concrete through existing manholes and creating additional access points to ensure the tunnel was completely filled and sealed. This method provided a reliable and lasting solution to eliminate the risk of collapse and restore the integrity of 14th Street.

We appreciate the patience and understanding of residents, commuters, and local businesses throughout this emergency work. Additional work will continue along 14th Street to address non-emergency work to complete the remaining length of the abandoned pipe but does not require full lane closures.

 

Latest News

Excavators in the canal digging up soil and another excavator removing the soil to a dump truck to be hauled away

DC Water and its contractor have made significant progress on soil removal, reaching the clay liner between locks 13 and 14 of the C & O Canal, which was used as a bypass for wastewater during the Potomac Interceptor repairs.

Work continues to remove sludge between locks 10 and 13, which is expected to be completed by mid- to late-April. The soil will then be removed down to the clay liner as the final step, and the canal reconstructed to meet National Park Service specifications.

Soil Removal Underway with Excavator in Canal

Today, DC Water and its contractors began removing contaminated soil between locks 13 and 14 in the C & O Canal, which was used as a temporary bypass during the Potomac Interceptor repair effort. Clean-up efforts are ongoing at Lock 10 with work to remove sludge now getting underway between locks 11 and 13.

Aerial shot of Blue Plains Advanced Wastewater Treatement Plant

Series 2026 Bond Transaction Delivers Significant Long-Term Cost Savings

DC Water has closed on a refinancing deal for its Series 2026 bonds that will save customers millions of dollars and keep rates affordable across the District. The refinancing transaction, which closed this month, delivers approximately $54 million in budget savings over the next twenty years, directly benefiting DC ratepayers through reduced costs.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Map of lane closure
Traffic Advisory: Rock Creek and Potomac Parkway NW Lane Closure Beginning Jan 19

Beginning on or about January 19, 2026, weather permitting, DC Water will implement a temporary lane closure on Rock Creek and Potomac Parkway NW b

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
April 7, 2026
Tuesday, 9:30 AM

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.