DC Water Response to Federal and State Lawsuits regarding the Potomac Interceptor Sewer Overflow

April 20, 2026

DC Water issues the following statement in response to the complaints filed by the Maryland Office of the Attorney General and the Department of Justice on behalf of the U.S. Environmental Protection Agency regarding the Potomac Interceptor sewer overflow into the Potomac River that occurred on January 19, 2026:

DC Water is fully committed to the long-term rehabilitation of the Potomac Interceptor. Although the lawsuits are still under review, they underscore our commitment to advance the planned repairs for the entire 54-mile pipeline, including the impacted segment. Executing this work on federal land requires close collaboration with the lead regulatory agency, which in this case is the National Park Service (NPS). Since 2018, DC Water has worked with NPS on site assessments, environmental reviews, and emergency repairs on portions of the pipeline to ensure environmental protection and public safety. DC Water will renew its requests for streamlined environmental reviews to allow rehabilitation of the interceptor to move forward more quickly. DC Water previously requested a categorical exclusion for this section of the pipe previously, but it was not approved. DC Water will continue to engage all stakeholders and work with the Maryland Department of the Environment on the environmental rehabilitation as we work to protect the Potomac River and serve the community.

From the outset, DC Water’s highest priority was to safely and quickly contain the overflow and repair the damaged section of the Potomac Interceptor. Crews implemented an emergency bypass system that successfully managed the majority of the overflow within five days and fully stopped all discharges to the Potomac River within 21 days. The repairs of the affected segment were completed in 55 days.

DC Water is working now to accelerate the rehabilitation of more than 2,700 linear feet of pipeline in this area that was previously scheduled for improvement. Initial environmental remediation efforts are also nearly complete, with ongoing water quality testing showing that downstream conditions have returned to normal and have remained stable for several months. In addition, recent testing results continue to indicate low bacteria levels near the site of the break.

Latest News

Photo of inside Potomac Interceptor at Dulles showing newly lined tunnel

First of four emergency repairs on Potomac Interceptor finished

DC Water has finished the first of four emergency repair projects on the Potomac Interceptor sewer line. Crews completed work today to strengthen a 600-foot section of pipe at Dulles International Airport.

Picture of repaired segment before the geopolymer work and after the work is done

Crews also reach a major milestone near Dulles International Airport as the next phase of repairs begins this week

DC Water has completed the first major step in emergency repairs to a 175-foot section of the Potomac Interceptor near Pennyfield Lock in Potomac, Maryland. Crews added a new, stronger lining inside the pipe after inspections found serious wear and damage. The work is part of ongoing repairs to 1,700 linear feet of pipe near Pennyfield Lock. Work began on Friday to apply geopolymer, a concrete-like material, inside the pipe. With the new lining complete, crews are preparing for the next phase of work for the remainder of the pipe segment.

image of clara barton parkway with lane closure marked in red

Beginning this week and continuing through mid-August, DC Water will temporarily close one lane overnight on Clara Barton Parkway at the Maryland-D.C. border. The closures are needed so crews can ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking
DC Water Breaks Ground on Piney Branch Tunnel, Final Phase of DC Clean Rivers Project

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Latest Blog Post
Plastic bottles, cups and other floating debris on the surface of the Anacostia River before the Anacostia River Tunnel began operating.
Cleaner Waterways Start With Everyday Choices
Protecting our waterways starts with everyday actions and continues through critical infrastructure designed to keep pollution out of our rivers.
Upcoming Meeting

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.