DC Water Response to Federal and State Lawsuits regarding the Potomac Interceptor Sewer Overflow

April 20, 2026

DC Water issues the following statement in response to the complaints filed by the Maryland Office of the Attorney General and the Department of Justice on behalf of the U.S. Environmental Protection Agency regarding the Potomac Interceptor sewer overflow into the Potomac River that occurred on January 19, 2026:

DC Water is fully committed to the long-term rehabilitation of the Potomac Interceptor. Although the lawsuits are still under review, they underscore our commitment to advance the planned repairs for the entire 54-mile pipeline, including the impacted segment. Executing this work on federal land requires close collaboration with the lead regulatory agency, which in this case is the National Park Service (NPS). Since 2018, DC Water has worked with NPS on site assessments, environmental reviews, and emergency repairs on portions of the pipeline to ensure environmental protection and public safety. DC Water will renew its requests for streamlined environmental reviews to allow rehabilitation of the interceptor to move forward more quickly. DC Water previously requested a categorical exclusion for this section of the pipe previously, but it was not approved. DC Water will continue to engage all stakeholders and work with the Maryland Department of the Environment on the environmental rehabilitation as we work to protect the Potomac River and serve the community.

From the outset, DC Water’s highest priority was to safely and quickly contain the overflow and repair the damaged section of the Potomac Interceptor. Crews implemented an emergency bypass system that successfully managed the majority of the overflow within five days and fully stopped all discharges to the Potomac River within 21 days. The repairs of the affected segment were completed in 55 days.

DC Water is working now to accelerate the rehabilitation of more than 2,700 linear feet of pipeline in this area that was previously scheduled for improvement. Initial environmental remediation efforts are also nearly complete, with ongoing water quality testing showing that downstream conditions have returned to normal and have remained stable for several months. In addition, recent testing results continue to indicate low bacteria levels near the site of the break.

Latest News

Graphic with details for the public hearing on June 23 at 6:30 p.m.

As DC Water’s Board of Directors considers proposed rate increases for the upcoming 2027 and 2028 fiscal years, we’re asking customers to provide feedback during a public hearing on Tuesday, June 23 at 6:30 p.m.

The proposed rate changes would support critical investments in safe, reliable drinking water, replacement of aging water and sewer lines, cleaner local waterways, and continued lead service line replacement across the District.

Photo of LFDC work on a street in the Trinidad NE Neighborhood

Public Encouraged to Provide Comment through June 23

DC residents who want to replace their lead service lines may soon have more options to do it sooner—without having to wait for construction to reach their block.  While the Lead Free DC Program replaces lead service lines at no cost, DC Water has proposed two updates to its program that would make it easier and faster for some residents to get their lead pipes replaced, especially those at higher risk of lead exposure. These proposed changes have been published in the DC Register and are now open for public review. 

Placeholder DC Water Image

DC Water will host a virtual community meeting on Thursday, June 11, 2026, to inform residents and other stakeholders about the emergency rehabilitation of a section of the Potomac Interceptor at Muddy Branch in Potomac, Maryland.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of temporarily relocated section of Piney Branch Parkway
Piney Branch Parkway Section to Reopen Monday, Restoring a Key Route for DC Commuters

Following a 27-day closure, DC Water will reopen a section of Piney Branch Parkway between Arkansas Avenue and Beach Drive NW early Monday morning, restoring an important cross-town connection for thousands of District commuters. During the closure, a section of the road was temporarily relocated for construction of DC Water’s Piney Branch Tunnel Project.

Latest Blog Post
DC Water General Manager and CEO David Gadis recognizes Lily MacDonald during the May Board of Directors meeting.
From Classroom to Community: A Student Spotlight on DC Water's SPLASH Program
A speechwriting assignment became a call to action for water access and affordability through DC Water's SPLASH program.
Upcoming Meeting
Date
June 23, 2026
Tuesday, 9:30 AM

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.