DC Water completes major repairs on century old sewer tunnel

June 13, 2025
Phase 1 repair photo of tunnel and worker inside after completion

Following a nearly year-long construction effort, DC Water has completed repairs on a nine foot diameter, 140-year old sewer tunnel on 22nd Street Northwest. Construction was done in two phases, with the second phase completed one month ahead of schedule and under budget.

The work zone in the area of 22nd and Q streets is being demobilized. All northbound lanes are now open, and southbound lanes will be reopened later today prior to the evening rush hour. 

The tunnel section is part of the Northwest Boundary Trunk Sewer, built in the 1800’s. Last year, an inspection revealed a large void in the soil above measuring 13 feet long and 10 feet wide and the tunnel in danger of collapse, necessitating the long-term closure of a section of 22nd Street. 

Significant structural issues were also identified, as well as upstream and downstream from the emergency repair. These included longitudinal cracks, missing cobblestones and bricks, and root penetration prompting emergency repairs.

Construction, sometimes 24 hours a day, seven days a week, posed challenges with crews working two stories below ground in difficult conditions. At the same time the sewer pipe remained active with combined stormwater and sewer debris flowing through and prompting work stoppages when heavy rain inundated the system. 

The work involved reinforcing the sewer tunnel and stabilizing the soil around the initial void. This required injecting grout into the soil, framing the walls with rebar, and using high-pressure spray-applied shotcrete and geopolymer, four inches to as much as nine inches thick. This included: 

  • 139,000 linear feet of rebar
  • 25,450 rebar anchors
  • 28 tons of shotcrete
  • 459 tons of geopolymer

Emergency repairs began in July 2024 as part of the first phase of the project which involved stabilizing the soil and reinforcing the tunnel around the initial void. Additional inspections identified more structural deficiencies requiring a second phase to repair more than 1200 linear feet further upstream and downstream.

DC Water worked closely with the District Department of Transportation to minimize the disruption to traffic in the area and appreciates residents and commuters for their patience while repairs were made for the safety of the community. To help relieve the impact of the road closure, one northbound lane of 22nd Street earlier this year while construction continued.

DC Water operates approximately 2,000 miles of combined, separate, and stormwater sewers. Addressing aging water and sewer infrastructure throughout the District is a critical part of the 10-year, $9.6 billion Capital Improvement Program. This includes replacing or rehabilitating similar large diameter sewer lines that have reached the end of their useful life.

For more information about DC Water’s investment in infrastructure improvements view our Capital Improvement Program. 

Before and after images of Phase 1 and PIhase 2 work

Latest News

Pennyfield Lock Potomac Interceptor bypass pipeline running next to C & O Canal with equipment

There is no active spill or overflow. Work to strengthen the pipe to begin soon.

Today, DC Water completed construction on a temporary bypass system as part of sewer repairs on the Potomac Interceptor near Pennyfield Lock in Potomac, Maryland. Crews turned on the pumps and successfully tested the system. With the bypass now ready, it will allow us to begin the emergency repairs inside the pipe by carrying the wastewater around the repair area.

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Photo of the drop shaft looking from above down into the bottom

Starting the week of July 13, 2026, people who live, work or travel near the Canal Road NW entrance to Georgetown University may hear controlled blasting. This work is part of our Potomac River Tunnel Project.

When blasting happens, neighbors may hear a brief noise or feel light shaking. Drivers, cyclists, and pedestrians on Canal Road NW may also be stopped for a few minutes while we safely complete each blast.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking
DC Water Breaks Ground on Piney Branch Tunnel, Final Phase of DC Clean Rivers Project

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Latest Blog Post
Five photos from the American Water Works Association (AWWA) ACE26 conference featuring panel discussions, technical presentations, networking, and attendees posing at the ACE26 display.
ACE26 Highlights: How DC Water Advanced the Conversation on Water
More than 80 DC Water employees joined thousands of water professionals in Washington, D.C., sharing expertise, building partnerships and advancing conversations that will help shape the future of water.
Upcoming Meeting
Date
July 13, 2026
Monday, 2:00 PM

Upcoming Events

Jul 23
Jul 25

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.