Emergency Water Main Repair
Jan 30, 2026 | 01:35 PM

Emergency Water Main Repair
Jan 30, 2026 | 01:32 PM

EMERGENCY WATER OUTAGE
Jan 30, 2026 | 12:00 PM

DC Water completes major repairs on century old sewer tunnel

June 13, 2025
Phase 1 repair photo of tunnel and worker inside after completion

Following a nearly year-long construction effort, DC Water has completed repairs on a nine foot diameter, 140-year old sewer tunnel on 22nd Street Northwest. Construction was done in two phases, with the second phase completed one month ahead of schedule and under budget.

The work zone in the area of 22nd and Q streets is being demobilized. All northbound lanes are now open, and southbound lanes will be reopened later today prior to the evening rush hour. 

The tunnel section is part of the Northwest Boundary Trunk Sewer, built in the 1800’s. Last year, an inspection revealed a large void in the soil above measuring 13 feet long and 10 feet wide and the tunnel in danger of collapse, necessitating the long-term closure of a section of 22nd Street. 

Significant structural issues were also identified, as well as upstream and downstream from the emergency repair. These included longitudinal cracks, missing cobblestones and bricks, and root penetration prompting emergency repairs.

Construction, sometimes 24 hours a day, seven days a week, posed challenges with crews working two stories below ground in difficult conditions. At the same time the sewer pipe remained active with combined stormwater and sewer debris flowing through and prompting work stoppages when heavy rain inundated the system. 

The work involved reinforcing the sewer tunnel and stabilizing the soil around the initial void. This required injecting grout into the soil, framing the walls with rebar, and using high-pressure spray-applied shotcrete and geopolymer, four inches to as much as nine inches thick. This included: 

  • 139,000 linear feet of rebar
  • 25,450 rebar anchors
  • 28 tons of shotcrete
  • 459 tons of geopolymer

Emergency repairs began in July 2024 as part of the first phase of the project which involved stabilizing the soil and reinforcing the tunnel around the initial void. Additional inspections identified more structural deficiencies requiring a second phase to repair more than 1200 linear feet further upstream and downstream.

DC Water worked closely with the District Department of Transportation to minimize the disruption to traffic in the area and appreciates residents and commuters for their patience while repairs were made for the safety of the community. To help relieve the impact of the road closure, one northbound lane of 22nd Street earlier this year while construction continued.

DC Water operates approximately 2,000 miles of combined, separate, and stormwater sewers. Addressing aging water and sewer infrastructure throughout the District is a critical part of the 10-year, $9.6 billion Capital Improvement Program. This includes replacing or rehabilitating similar large diameter sewer lines that have reached the end of their useful life.

For more information about DC Water’s investment in infrastructure improvements view our Capital Improvement Program. 

Before and after images of Phase 1 and PIhase 2 work

Latest News

Photo of excavation of collapse site and containment in place

DC Water and its contractor have successfully excavated around the damaged section of the Potomac Interceptor, a sanitary sewer line that collapsed on January 19 and overflowed into the Potomac River. For the second straight day, there have been no sewer overflows from the damaged pipe.

Photo of collapse site and federal, state, local officials in background

Federal, State, and Local Officials Get Firsthand Look at Collapse Site and Repair Efforts

Over the past 24-hours, DC Water engineers for the first time report no sanitary sewer overflows escaping from a damaged section of the Potomac Interceptor since the incident happened. The 72-inch diameter pipe section collapsed on January 19, along Clara Barton Parkway and the C & O Canal National Historical Park in Montgomery County, MD.

Photo of collapse site of Potomac Interceptor and excavation underway

Excavation is underway to access a damaged section of the Potomac Interceptor, a major sewer line that collapsed on January 19, along Clara Barton Parkway near the 495-interchange and C & O National ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Map of lane closure
Traffic Advisory: Rock Creek and Potomac Parkway NW Lane Closure Beginning Jan 19

Beginning on or about January 19, 2026, weather permitting, DC Water will implement a temporary lane closure on Rock Creek and Potomac Parkway NW b

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 5, 2026
Thursday, 9:30 AM

Upcoming Events

Feb 2
6:30 pm - 9:00 pm

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.