DC Water completes major repairs on century old sewer tunnel

June 13, 2025
Phase 1 repair photo of tunnel and worker inside after completion

Following a nearly year-long construction effort, DC Water has completed repairs on a nine foot diameter, 140-year old sewer tunnel on 22nd Street Northwest. Construction was done in two phases, with the second phase completed one month ahead of schedule and under budget.

The work zone in the area of 22nd and Q streets is being demobilized. All northbound lanes are now open, and southbound lanes will be reopened later today prior to the evening rush hour. 

The tunnel section is part of the Northwest Boundary Trunk Sewer, built in the 1800’s. Last year, an inspection revealed a large void in the soil above measuring 13 feet long and 10 feet wide and the tunnel in danger of collapse, necessitating the long-term closure of a section of 22nd Street. 

Significant structural issues were also identified, as well as upstream and downstream from the emergency repair. These included longitudinal cracks, missing cobblestones and bricks, and root penetration prompting emergency repairs.

Construction, sometimes 24 hours a day, seven days a week, posed challenges with crews working two stories below ground in difficult conditions. At the same time the sewer pipe remained active with combined stormwater and sewer debris flowing through and prompting work stoppages when heavy rain inundated the system. 

The work involved reinforcing the sewer tunnel and stabilizing the soil around the initial void. This required injecting grout into the soil, framing the walls with rebar, and using high-pressure spray-applied shotcrete and geopolymer, four inches to as much as nine inches thick. This included: 

  • 139,000 linear feet of rebar
  • 25,450 rebar anchors
  • 28 tons of shotcrete
  • 459 tons of geopolymer

Emergency repairs began in July 2024 as part of the first phase of the project which involved stabilizing the soil and reinforcing the tunnel around the initial void. Additional inspections identified more structural deficiencies requiring a second phase to repair more than 1200 linear feet further upstream and downstream.

DC Water worked closely with the District Department of Transportation to minimize the disruption to traffic in the area and appreciates residents and commuters for their patience while repairs were made for the safety of the community. To help relieve the impact of the road closure, one northbound lane of 22nd Street earlier this year while construction continued.

DC Water operates approximately 2,000 miles of combined, separate, and stormwater sewers. Addressing aging water and sewer infrastructure throughout the District is a critical part of the 10-year, $9.6 billion Capital Improvement Program. This includes replacing or rehabilitating similar large diameter sewer lines that have reached the end of their useful life.

For more information about DC Water’s investment in infrastructure improvements view our Capital Improvement Program. 

Before and after images of Phase 1 and PIhase 2 work

Latest News

Close-up of the TBM cutterhead suspended by a crane

DC Water’s Newest Tunnel Boring Machine to Dig Tunnel’s Southern Segment

Emily, DC Water’s second tunnel boring machine for the Potomac River Tunnel Project, has arrived at the West Potomac Park construction site. Once assembled and launched, she will excavate the tunnel’s southern section.

Information for the DC Water Town Hall on a graphic

DC Water is reminding community members that it will host a Town Hall on Thursday, May 28, from 7–9 p.m. at DC Water Headquarters to discuss proposed Fiscal Year 2027 budget updates and rate ...

Graphic with information about the town hall

DC Water’s proposed $1.9 billion operating and capital budget for Fiscal Year 2027, focused on Smart Spending for a Resilient Tomorrow, includes funding to help provide safe, reliable drinking water, upgrade aging water and sewer infrastructure, reduce pollution in local waterways, and continue removing lead service lines across the District.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Close-up of the TBM cutterhead suspended by a crane
From Germany to DC, Emily Arrives on a One-Way Ticket to Help Build the Potomac River Tunnel

DC Water’s Newest Tunnel Boring Machine to Dig Tunnel’s Southern Segment

Emily, DC Water’s second tunnel boring machine for the Potomac River Tunnel Project, has arrived at the West Potomac Park construction site. Once assembled and launched, she will excavate the tunnel’s southern section.

Latest Blog Post
DC Water General Manager and CEO David Gadis recognizes Lily MacDonald during the May Board of Directors meeting.
From Classroom to Community: A Student Spotlight on DC Water's SPLASH Program
A speechwriting assignment became a call to action for water access and affordability through DC Water's SPLASH program.
Upcoming Meeting
Date
June 4, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.