Traffic Advisory: Northeast Boundary Tunnel Brings Median Removal to Rhode Island Avenue, NW

April 04, 2019

(Washington, DC) – In preparation for construction associated with the DC Water Northeast Boundary Tunnel (NEBT) (dcwater.com/NEBT), contractors will remove portions of the medians on Rhode Island Avenue, NW between 2nd Street and North Capitol Street, NW. This removal is needed to allow for various detours and lane shifts during construction. While the construction was scheduled to begin March 11, work was delayed as we worked with the District Department of Transportation and the Urban Forestry Division to further reduce the number of trees removed from the medians while assuring construction site safety. When the NEBT construction is complete, the medians will be restored, and new trees will be planted.

Median removal work will be completed in two phases. Work will begin for Phase 1 on or about April 9, 2019. Phase 2 work will immediately follow Phase 1. Work hours will be 7 am to 7 pm Monday through Friday.

Construction Phases

Phase 1 (Duration 2.5 weeks):

The contractor will remove the median on Rhode Island Avenue, NW between 2nd Street and First Street, NW to prepare for detours and lane shifts.

Travel and Parking Restrictions: 

  • Traffic on Rhode Island Avenue, NW will be reduced from three lanes to two lanes and 24-hour parking restrictions will be in place for the following locations:
    • The eastbound side of Rhode Island Avenue, NW between 3rd Street and First Street, NW. 
    • The westbound side of Rhode Island Avenue, NW between North Capitol Street and 2nd Street, NW. 

Phase 2 (Duration 2.5 Weeks):

The contractor will remove the median along Rhode Island Avenue NW between First Street and North Capitol Street.

Travel and Parking Restrictions: 

  • Traffic on Rhode Island Avenue will be reduced from three lanes to two lanes and 24-hour parking restrictions will be in place for the following locations:
    • The eastbound side of Rhode Island Avenue NW between 3rd Street NW and First Street NW. 
    • The westbound side of Rhode Island Avenue NW between North Capitol Street NW and 2nd Street NW. 

Additional Information

  • People who live or work near the affected location(s) may notice additional equipment as well as noise associated with construction activities.
  • Commuters and pedestrians may notice road signs and/or flagging personnel directing them around the work site.

DC Clean Rivers has worked closely with the District Department of Transportation, Department of Energy and Environment, Urban Forestry Division, and other supporting agencies to design a plan that minimizes impact to traffic and pedestrian travel and conserves several trees important to the landscape of the neighborhood. 

Project Details

The NEBT is the largest component of the Clean Rivers Project and will start south of RFK Stadium and extend north to Rhode Island Avenue, NE, and west to 6th Street, NW. When complete, the approximately five-mile long tunnel will significantly reduce chronic flooding in the areas it serves, while reducing the amount of combined sewer overflows into the Anacostia River.
 

###

 

For more information, please contact

Email: dccleanrivers@dcwater.com

Northeast Boundary Tunnel Project Webpage: dcwater.com/NEBT

24/7 Hotline: (800) 988-6151

Latest News

Workers manually removing soil between the locks

Work is progressing on the clean-up for the C & O Canal which was used as a bypass while the Potomac Interceptor was repaired. Workers are focused on removing sludge between locks 11 and 12. Soil removal is also nearly complete between locks 12 and 14, reaching the canal's clay liner. Workers are now manually removing additional materials in some areas.

Excavators in the canal digging up soil and another excavator removing the soil to a dump truck to be hauled away

DC Water and its contractor have made significant progress on soil removal, reaching the clay liner between locks 13 and 14 of the C & O Canal, which was used as a bypass for wastewater during the Potomac Interceptor repairs.

Work continues to remove sludge between locks 10 and 13, which is expected to be completed by mid- to late-April. The soil will then be removed down to the clay liner as the final step, and the canal reconstructed to meet National Park Service specifications.

Soil Removal Underway with Excavator in Canal

Today, DC Water and its contractors began removing contaminated soil between locks 13 and 14 in the C & O Canal, which was used as a temporary bypass during the Potomac Interceptor repair effort. Clean-up efforts are ongoing at Lock 10 with work to remove sludge now getting underway between locks 11 and 13.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Map of lane closure
Traffic Advisory: Rock Creek and Potomac Parkway NW Lane Closure Beginning Jan 19

Beginning on or about January 19, 2026, weather permitting, DC Water will implement a temporary lane closure on Rock Creek and Potomac Parkway NW b

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
April 10, 2026
Friday, 9:30 AM

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.