DC Water Completes Critical Potomac Interceptor Sewer Line Repairs at Broad Run

September 03, 2026
Photo of manhole entrance withe completed geopolymer
Second of four high-priority repair projects is now complete

DC Water has completed the second of four critical repair projects on the Potomac Interceptor Sewer Line. Crews finished strengthening a 490-foot section of the pipe at Broad Run in Loudoun County today.

Work began in June after inspections found serious damage inside the 54-mile sewer line. Crews found corrosion, worn concrete and exposed steel supports. They repaired this 42-inch-wide section with a strong new lining using a concrete like material. Next a flexible liner was installed inside the pipe that was hardened in place to form a new pipe inside the existing one. Together, these repairs restored the pipe to like-new condition.

Broad Run is one of four locations that DC Water identified earlier this year for critical repairs. Work continues at Pennyfield Lock in Potomac, Maryland, and along Clara Barton Parkway near the Maryland-DC line. Last month, DC Water also completed repairs to a 600-foot section of ther Potomac Interceptor near Dulles International Airport.

Now that the pipe repairs are complete, DC Water will begin work to restore the Broad Run site.

Emergency repairs continue at the two remaining locations.

Pennyfield Lock

At Pennyfield Lock work is underway to prepare for the next phase of repairs. Crews are digging two large pits that will be used to place new pipe sections inside the existing pipe. Due to groundwater issues, crews are adding pumps and other safeguards to keep the pits dry. This work is taking longer than expected and may delay the start of pipe installation beyond September.

The possible schedule change is not expected to cause serious issues. The most critical section of pipe was repaired in late July. DC Water strengthened 175 feet of the sewer line where inspections found major corrosion and exposed steel supports. Crews added a new, stronger lining inside the pipe. This earlier repair helps protect the pipe while crews manage groundwater and prepare to repair the remainder of the 1,700 linear foot rehabilitation project.

Maryland-DC Line

Work also continues along Clara Barton Parkway near the Maryland-DC line. Crews have installed a temporary bypass pumping system, and it is now operating at the site. The system keeps wastewater flowing safely around the section under repair.

Crews are now adding a strong new lining inside the existing pipe. This will stabilize the pipe and allow crews to safely complete the permanent repair.

After the lining is complete, crews will prepare to place a new pipe inside the existing sewer line. The new pipe is designed to better resist corrosion, strengthen the sewer line and extend the life of the pipe for decades to come.

To do the work, sections of the pipe are open to pump the wastewater out and back into the pipe downstream. Another opening will be used to insert the new pipe section while wastewater continues to flow through the open sewer line. During this time, people may notice odors in the immediate area around the site. These odors, while unpleasant, do not pose a health risk. DC Water is working to add odor control measures to try and help reduce the smell.  

For more information about the Potomac Interceptor repairs, visit dcwater.com/potomacinterceptor.

Latest News

Photo of manhole entrance withe completed geopolymer

Second of four high-priority repair projects is now complete

DC Water has completed the second of four critical repair projects on the Potomac Interceptor Sewer Line. Crews finished strengthening a 490-foot section of the pipe at Broad Run in Loudoun County today.

Image of Clara Barton Parkway showing lane closure

Beginning this week and continuing through the end of September, DC Water will temporarily close one lane overnight on Clara Barton Parkway at the Maryland-D.C. border. The closures are necessary to allow crews to safely begin geopolymer work, a concrete-like material, applied inside the sewer line as part of emergency repairs to a section of the Potomac Interceptor.

Last gantry at the bottom of the shaft where crews connect it

Final Gantry Completes Mobile Support Train Behind Mary Stretching More Than 700 Feet

DC Water’s tunnel boring machine Mary may be the muscle behind the Potomac River Tunnel Project, but the gantries that trail behind her form the heart, brains, and guts of the operation. Now crews have lowered and connected the final gantry section, giving Mary the tools and equipment she needs to continue tunneling north.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Last gantry at the bottom of the shaft where crews connect it
Now Fully Assembled, It’s Full Speed Ahead for the tunnel boring machine Mary and the Potomac River Tunnel

Final Gantry Completes Mobile Support Train Behind Mary Stretching More Than 700 Feet

DC Water’s tunnel boring machine Mary may be the muscle behind the Potomac River Tunnel Project, but the gantries that trail behind her form the heart, brains, and guts of the operation. Now crews have lowered and connected the final gantry section, giving Mary the tools and equipment she needs to continue tunneling north.

Latest Blog Post
Emergency supplies arranged on a table, including bottled water, canned food, a backpack, first aid kit, flashlight, phone, medication and other essential items.
Simple Ways to Stay Prepared at Home
A few simple steps can help your household prepare for severe weather and temporary water or sewer service interruptions.
Upcoming Meeting

Upcoming Events

Sep 6
Sep 19

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.