Like a Cicada, Chris the Tunnel Boring Machine Emerges

May 04, 2021
Image of the tunnel boring machine cutterhead.

After a three-year, five-mile journey below the District, “Chris” the Tunnel Boring Machine (TBM) has finished excavating the Northeast Boundary Tunnel. 

Now crews will break him into 20 smaller pieces and use a crane to lift him to the surface at the R Street, NW construction site where he will be transported away. This process will run between May and June 2021 following three years underground – not as long as a Brood X cicada but still a long time away from daylight. 

Each truck transport will carry one or two parts of the TBM’s cutterhead and middle shield sections and there will be some traffic impacts during these late night hours. Up to two deliveries will be scheduled per evening between 11 PM and 3 AM. The remaining parts of the TBM will be moved through the Northeast Boundary Tunnel to the shaft near RFK Stadium, where Chris’s work began. 

The first removal of the TBM parts will occur on or about May 6, 2021. The parts will be hauled on a flatbed truck and escorted by vehicles and flaggers to help navigate turns, if necessary. Short duration road closures will occur along the haul route and temporary detour routes will be in effect until the truck passes. 

The truck route begins at the R Street construction site at Rhode Island Avenue, NW near 6th Street NW, heads south on Florida Avenue, NW to New York Avenue, NE. The truck will merge onto I-295, exit on East Capitol Street, SE and stop at the project construction site near parking lot 8 of RFK Stadium.  

Project Details 

The Northeast Boundary Tunnel (NEBT) is the largest component of the Clean Rivers Project. It begins south of RFK Stadium and extends north to Rhode Island Avenue NE and west to 6th Street NW. The tunnel was excavated by “Chris” the tunnel boring machine (TBM). Its five-mile journey began in 2018 at the CSO 019 construction site located south of the RFK Stadium. It reached its destination in the Shaw neighborhood in April 2021.  Once the NEBT is connected to the other Clean Rivers tunnels, combined sewer overflows to the Anacostia River will be reduced by 98 percent. In addition to controlling combined sewer overflows, the construction of the Northeast Boundary Tunnel will reduce the chance of flooding in the areas it serves from approximately 50 to 7 percent in any given year. 

For more information, please contact 

Email: dccleanrivers@dcwater.com 

24/7 NEBT Hotline: (800) 988-6151 

Northeast Boundary Tunnel Project Website: dcwater.com/NEBT 

Latest News

Photo of completed repair with concrete encasing the sewr pipe

DC Water has successfully completed emergency repairs on a critical section of the Anacostia Force Main following a failure near Anacostia Avenue and Ponds Street Northeast in July. With repairs finalized, attention now turns to rehabilitating other vulnerable segments of the 6.25-mile pipeline to ensure long-term reliability and resilience. 

Map of construction area on Clara Barton Parkway near I495

DC Water will be doing construction as part of a sanitary sewer rehabilitation project on Clara Barton Parkway in Maryland from Sept 8 - Oct 10, 2025, which may cause delays inbound near the I-495 Beltway interchange. One lane will be closed in the work zone to reline an 800-foot section of the sewer line, known as the Potomac Inteceptor. Access to the inner and outer loops of the Beltway will remain available.

Rock Creek Trail Site for Potomac River Tunnel Project

Starting the week of August 25, DC Water will take another big step forward in the Potomac River Tunnel Project. Ground stabilization will begin at the Rock Creek Trail site, near the Watergate Complex, to drill secant piles that will form a retaining wall for the drop shaft.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Rock Creek Trail Site for Potomac River Tunnel Project
Ground Stabilization Work Begins Near Watergate Complex, starting Aug 25

Starting the week of August 25, DC Water will take another big step forward in the Potomac River Tunnel Project. Ground stabilization will begin at the Rock Creek Trail site, near the Watergate Complex, to drill secant piles that will form a retaining wall for the drop shaft.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
September 18, 2025
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.