SANITARY SEWER REHABILITATION PROJECT DOWNTOWN DC AREA – ANCs 2A & 2C

Map of Project Area

OVERVIEW

As part of its Capital Improvement Program, DC Water will be performing a sanitary sewer rehabilitation project within the Downtown DC area (See back page for construction location map). While extending the service life of this local sewer system, other benefits of this rehabilitation project will include improved structural integrity of the sewer, while also maintaining adequate hydraulic capacity and mitigating potential sanitary sewer overflows.

 

SCOPE OF WORK

  • Rehabilitation of approximately 8,648 linear feet of 6-inch to 42-inch sewer pipe within the project area using Cured-In-Place Pipe (CIPP) methods
  • Point repairs to portions of pipe, where needed (this will require some excavation).
  • Rehabilitation of approximately 10 manholes along the sewer alignment.

 

SCHEDULE

  • Estimated Construction start: April 2025
  • Estimated Construction completion: July 2026
  • Normal work hours: 9:30AM to 3:30PM, Monday through Friday
    • For arterial and collector roads: 9:30am to 3:30pm, Monday through Friday
    • For local roads: 7:00am to 7:00pm, Monday through Friday
  • Contractor may work at night or on weekends, dependent upon certain construction activities or inclement weather

 

IMPORTANT INFORMATION

  • If a temporary water service shut-off is necessary at any point during the project, affected residents will be notified 48 hours in advance. All scheduled service interruptions will be Minimal.
  • DC Water will work to achieve minimal disruption during construction operations.
  • Noise and vibrations will be closely monitored throughout the project.
  • During construction, bypass piping will be installed from manhole to manhole to divert sewer flow.
  • For any necessary temporary interruption of sewer services during construction, affected customers will be notified 7 days in advance.
  • Some odor may be noticed temporarily during construction operations.

 

TRAFFIC

  • Flagging operations may be used daily for each construction phase to maintain traffic in the construction work zone.  All Traffic Control Plans will be approved by the District Department of Transportation (DDOT).
  • During construction, “no-parking” signs may be placed in certain areas in and around the job site. Notifications regarding “no-parking” zones will be posted 72 hours prior to construction, as required by DDOT.

 

PARTNERS

DC Water is working to ensure minimal disruption during this project. Regular updates will be provided to impacted residents, Advisory Neighborhood Commission 2A & 2C, Ward 2 representatives in the Mayor’s Office of Community Relations and Services, and Ward 2 Councilmember Brooke Pinto and members of her staff. 


 

Contact Information

For More Information, Please Contact:

DC Water Project Manager: 
Nahome Menker 
202-787-4297 
nahome.menker@dcwater.com

DC Water Project Contractor: 
Garret Gansor
410-530-4142
ggansor@azuria.com 

 

DC Water Standard Contacts:

Water Quality And Technology Division 
(202) 612-3440

24-hr Emergency/Command Center
(202) 612-3400 

Office of Marketing and Communications
(202) 787-2200

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking
DC Water Breaks Ground on Piney Branch Tunnel, Final Phase of DC Clean Rivers Project

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Latest Blog Post
Plastic bottles, cups and other floating debris on the surface of the Anacostia River before the Anacostia River Tunnel began operating.
Cleaner Waterways Start With Everyday Choices
Protecting our waterways starts with everyday actions and continues through critical infrastructure designed to keep pollution out of our rivers.
Upcoming Meeting
Date
July 28, 2026
Tuesday, 9:30 AM

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.