ANACOSTIA FORCE MAIN HIGH PRIORITY PROJECT KENILWORTH AND EASTLAND GARDENS AREA NEIGHBORHOODS – ANC 7D

Map of Project Area

overview

The Anacostia Force Main (AFM) is a 33,000-foot pipeline made of 108-inch diameter prestressed concrete cylinder pipe. It was built to carry up to 305 million gallons per day (mgd). During an inspection conducted in connection with emergency work in July 2025, DC Water identified structural concerns that require timely repair to maintain reliable service. Because the AFM serves as a primary conveyance of flows from WSSC’s Pump Station, maintaining its integrity is critical to protecting surrounding communities and the environment.  These repairs are a top priority and are included in DC Water’s Capital Improvement Program. Work will occur along Anacostia Avenue NE near Kenilworth Aquatic Gardens.

 

scope of work

  • Excavation and installation of approximately 1,200 linear feet of 84-inch diameter redundant pipeline parallel to the existing AFM, for temporary flow diversion while rehabilitation work is completed on the existing pipe and future redundancy.
  • Structural rehabilitation of approximately 1,200 linear feet of the existing force main.
  • Cleaning of the existing force main
  • Replacement of air release valves

 

schedule

  • Anticipated construction starts: November 2026
  • Anticipated construction completion: November 2027
  • Normal work hours: Monday-Saturday, 7 a.m. to 5 p.m. (10-hour workdays)
  • The contractor will work at night or on weekends, depending upon certain construction activities, inclement weather, and approval by regulatory stakeholders (e.g. NPS)

 

important information 

  • DC Water will work to ensure disruptions are minimized during construction operations and will restore all work sites to their original condition upon completion of the project.
  • The construction activities are limited to wastewater infrastructure and will not affect DC Water’s drinking water system.

 

traffic 

  • Lane closures and flagging operations may be required daily for each phase of construction to maintain traffic in the construction work zone. All Traffic Control Plans will be approved by the District Department of Transportation (DDOT).

  • Notifications regarding “No-Parking” zones will be posted 72 hours prior to construction, in certain areas in and around the job site, as required by DDOT.

 

partners

  • In addition to working closely with the National Park Service, DC Water is working to ensure minimal disruption during this project. Regular updates will be provided to impacted residents, Advisory Neighborhood Commission 7D, Ward 7 representatives in the Mayor’s Office of Community Relations and Services, and Ward 7 Councilmember Wendell Felder and members of his staff.

 

 

Contact Information

For more information, please contact:

DC Water Project Manager
Yonas Kidanemariam
(202) 787-4059
yonas.kidanemariam@dcwater.com

DC Water Project Contractor
Spiniello
Angel Cruz
(201) 396-9565
acruz@spinielloco.com 

DC Water Standard Contacts
DC Water 24-hr Emergency/Command Center
(202) 612-3400

DC Water Office of External Affairs
(202) 787-2200

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Christening of TBM Emily with DC Water Interim General Manager Matt Brown holding bottle of tap water to christen Emily
DC Water Welcomes the Community Underground to See the Potomac River Tunnel and Christens Tunnel Boring Machine Emily

DC Water celebrated the christening of Emily today. It’s the second giant tunnel boring machine (TBM) that will help build the 5.5-mile Potomac River Tunnel. The celebration continued with Community Day. Residents and families met Emily and stepped inside the tunnel where she will soon begin digging.

Latest Blog Post
Emergency supplies arranged on a table, including bottled water, canned food, a backpack, first aid kit, flashlight, phone, medication and other essential items.
Simple Ways to Stay Prepared at Home
A few simple steps can help your household prepare for severe weather and temporary water or sewer service interruptions.
Upcoming Meeting
Date
November 5, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.