Blue Plains Tunnel Project

BPT_finished

The Blue Plains Tunnel Project received the Engineering News Record (ENR) 2016 Best Project Award for the Mid-Atlantic Region for Water/Environment. The project was selected by industry judges that evaluated a large number of projects according to overcoming challenges, contribution to the industry and community, safety and quality.

Overview

The Blue Plains Tunnel was the first of DC Water's large tunnel contracts to go to construction. "Lady Bird" Tunnel Boring Machine, the First Lady of Clean Rivers, constructed 24,300 linear feet of reinforced concrete tunnel as part of the project.

Check out this great video of "Lady Bird" building the Blue Plains Tunnel.

 

 

"Lady Bird" Tunnel Boring Machine

"Lady Bird" Quick Facts Performance

26 feet, 4 inches diameter

Total length of 443 feet

1,323 Tons (equal to approximately 7.5 Boeing 747s)

Earth Pressure Balance Machine

Manufactured by Herrenknecht

Approximate $30M cost

Named after after Claudia Alta "Lady Bird" Johnson, First Lady and wife of President Lyndon B. Johnson

Christened with DC Water tap in a ceremony with former Mayor Vincent C. Gray, Ward 3 Councilmember Mary M. Cheh, US EPA Regional Administrator Shawn M. Garvin, District City Administrator and DC Water Board Chair Allen Y. Lew and DC Water General Manager George S. Hawkins

Mining start: 7/29/13

Mining end: 7/25/15

726 calendar days

24,300 foot drive

Bolted and gasketed concrete steel fiber reinforced segments

Mined successfully beneath sensitive structures

Mined predominantly through stiff clay

Moved approximately 13 million cubic feet of soil for this project - enough material to fill the reflecting pool 14.5 times

Moved 72,500 truckloads of soil

Project Location Map

 

clean river
Clean Rivers

The Clean Rivers Project is DC Water's ongoing program to reduce combined sewer overflows into the District's waterways - the Anacostia and Potomac Rivers and Rock Creek. The Project is a massive infrastructure and support program designed to capture and clean water during heavy rainfalls before it ever reaches our rivers.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Last gantry at the bottom of the shaft where crews connect it
Now Fully Assembled, It’s Full Speed Ahead for the tunnel boring machine Mary and the Potomac River Tunnel

Final Gantry Completes Mobile Support Train Behind Mary Stretching More Than 700 Feet

DC Water’s tunnel boring machine Mary may be the muscle behind the Potomac River Tunnel Project, but the gantries that trail behind her form the heart, brains, and guts of the operation. Now crews have lowered and connected the final gantry section, giving Mary the tools and equipment she needs to continue tunneling north.

Latest Blog Post
Emergency supplies arranged on a table, including bottled water, canned food, a backpack, first aid kit, flashlight, phone, medication and other essential items.
Simple Ways to Stay Prepared at Home
A few simple steps can help your household prepare for severe weather and temporary water or sewer service interruptions.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.