Update on sewer repairs on 17th Street, NW

January 29, 2019

DC Water and its contractors continue to make repairs at 17th and D Streets, NW. The following road closures are still in effect:

  • 17th Street, between C and E Streets, NW; and
  • D Street, between 17th and 18th Streets, NW

The damage was more extensive than expected; however, DC Water and contractor crews have made significant progress. Over the weekend, crews assessed the damage and cleaned out debris from the pipes, and engineers planned the repairs which began Sunday. The sewer line repairs were completed yesterday and restoration work has begun.
 
There are several steps left before the road can be restored and weather may be a factor. Road restoration might begin as early as this weekend or next week.
 
DC Water will provide updates. The intersection remains closed to vehicular traffic at this time.

Latest News

Map of lane closure on Clara Barton Parkway at Maryland-DC Border

Drivers should expect delays on Clara Barton Parkway at the Maryland – DC border on Saturday, Sept 26. One lane will be closed from 7 a.m. to 3 p.m. while DC Water makes repairs as part of ongoing ...

Christening of TBM Emily with DC Water Interim General Manager Matt Brown holding bottle of tap water to christen Emily

DC Water celebrated the christening of Emily today. It’s the second giant tunnel boring machine (TBM) that will help build the 5.5-mile Potomac River Tunnel. The celebration continued with Community Day. Residents and families met Emily and stepped inside the tunnel where she will soon begin digging.

Map: Temporary closure of the southbound curb lane on Rock Creek and Potomac Parkway NW

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT

Drivers should expect a temporary southbound lane closure on Rock Creek and Potomac Parkway NW between F St and Virginia Ave on Saturday, September 19, and Sunday, September 20, 2026. The closure will be in place from 7 a.m. to 7 p.m. each day, weather permitting.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Christening of TBM Emily with DC Water Interim General Manager Matt Brown holding bottle of tap water to christen Emily
DC Water Welcomes the Community Underground to See the Potomac River Tunnel and Christens Tunnel Boring Machine Emily

DC Water celebrated the christening of Emily today. It’s the second giant tunnel boring machine (TBM) that will help build the 5.5-mile Potomac River Tunnel. The celebration continued with Community Day. Residents and families met Emily and stepped inside the tunnel where she will soon begin digging.

Latest Blog Post
Emergency supplies arranged on a table, including bottled water, canned food, a backpack, first aid kit, flashlight, phone, medication and other essential items.
Simple Ways to Stay Prepared at Home
A few simple steps can help your household prepare for severe weather and temporary water or sewer service interruptions.
Upcoming Meeting
Date
October 8, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.