UPDATE: Potomac Interceptor Sewer Overflow Incident, February 7

February 07, 2026
Trench boxes at construction site for new pit accessing Potomac Interceptor Upstream

Potomac Interceptor Update

Saturday, February 7, 2026

DC Water and its contractors continue to make progress constructing new access points to the Potomac Interceptor, one upstream of the damaged section, and an additional entry downstream to divert more wastewater flow from the pipe. These access points will allow crews to install a bulkhead, blocking flow in the pipe upstream of the collapsed area, keeping the site as dry as possible so crews can safely remove an extensive rock dam currently blocking the pipe.

With no overflows reported from the site yesterday and today, water quality sampling for E.  coli continues to trend downward at the Lock 10 channel where the overflow occurred. Sampling results at downstream sampling locations continue to remain within EPA standards for acceptable levels.

Here is an update on today’s work:

Containment

  • No overflows reported today.
  • Crews continue to monitor bypass pumping operations 24/7, performing routine cleaning and maintenance to ensure continued pumping capacity and reliability.

Pipe Cleaning Efforts

  • Excavation was completed at the pit near the I-495 interchange and Clara Barton Parkway to access a section of the Potomac Interceptor upstream of the break.
  • Trench boxes were installed around the upstream section of pipe and backfilled to stabilize the excavation.
  • Work continues on a third flume to the Potomac Interceptor as part of the bypass system, allowing wastewater to be returned to the system further downstream of the collapse site.
  • Installation of additional bypass pumps and the upstream bulkhead is expected to take 4-6 weeks from the time work began on February 6.
  • These steps are necessary before crews can begin to safely remove the blockage inside the pipe.
  • Removal of the rock and boulder obstruction will require a combination of manual work inside the pipe and the use of heavy equipment.

Water Quality Sampling Results

Grid of test results

Historical data indicate typical E. coli levels in the Potomac River can range from 10 to 5,000 MPN/100mL. Variability in E. coli results are common and are influenced by multiple factors, such as weather (rainfall/snow melt and associated runoff) and subwatershed activities and conditions, including aging sewer infrastructure and illicit discharges.

Latest News

Placeholder DC Water Image

DC Water will host a virtual community meeting on Thursday, June 11, 2026, to inform residents and other stakeholders about the emergency rehabilitation of a section of the Potomac Interceptor at Muddy Branch in Potomac, Maryland.

Four CCTV images of the pipe showing the condition of particular areas of the pipe

Measures are in place to help protect downstream drinking water infrastructure

DC Water is accelerating rehabilitation work on a section of the Potomac Interceptor at Muddy Branch near Pennyfield Lock (Lock 22) in Potomac, Maryland. Inspections found structural deterioration, including significant corrosion and exposed rebar, that requires immediate attention.

Photo of temporarily relocated section of Piney Branch Parkway

Following a 27-day closure, DC Water will reopen a section of Piney Branch Parkway between Arkansas Avenue and Beach Drive NW early Monday morning, restoring an important cross-town connection for thousands of District commuters. During the closure, a section of the road was temporarily relocated for construction of DC Water’s Piney Branch Tunnel Project.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of temporarily relocated section of Piney Branch Parkway
Piney Branch Parkway Section to Reopen Monday, Restoring a Key Route for DC Commuters

Following a 27-day closure, DC Water will reopen a section of Piney Branch Parkway between Arkansas Avenue and Beach Drive NW early Monday morning, restoring an important cross-town connection for thousands of District commuters. During the closure, a section of the road was temporarily relocated for construction of DC Water’s Piney Branch Tunnel Project.

Latest Blog Post
DC Water General Manager and CEO David Gadis recognizes Lily MacDonald during the May Board of Directors meeting.
From Classroom to Community: A Student Spotlight on DC Water's SPLASH Program
A speechwriting assignment became a call to action for water access and affordability through DC Water's SPLASH program.
Upcoming Meeting
Date
June 18, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.