UPDATE: Potomac Interceptor Sewer Overflow Incident, February 7

February 07, 2026
Trench boxes at construction site for new pit accessing Potomac Interceptor Upstream

Potomac Interceptor Update

Saturday, February 7, 2026

DC Water and its contractors continue to make progress constructing new access points to the Potomac Interceptor, one upstream of the damaged section, and an additional entry downstream to divert more wastewater flow from the pipe. These access points will allow crews to install a bulkhead, blocking flow in the pipe upstream of the collapsed area, keeping the site as dry as possible so crews can safely remove an extensive rock dam currently blocking the pipe.

With no overflows reported from the site yesterday and today, water quality sampling for E.  coli continues to trend downward at the Lock 10 channel where the overflow occurred. Sampling results at downstream sampling locations continue to remain within EPA standards for acceptable levels.

Here is an update on today’s work:

Containment

  • No overflows reported today.
  • Crews continue to monitor bypass pumping operations 24/7, performing routine cleaning and maintenance to ensure continued pumping capacity and reliability.

Pipe Cleaning Efforts

  • Excavation was completed at the pit near the I-495 interchange and Clara Barton Parkway to access a section of the Potomac Interceptor upstream of the break.
  • Trench boxes were installed around the upstream section of pipe and backfilled to stabilize the excavation.
  • Work continues on a third flume to the Potomac Interceptor as part of the bypass system, allowing wastewater to be returned to the system further downstream of the collapse site.
  • Installation of additional bypass pumps and the upstream bulkhead is expected to take 4-6 weeks from the time work began on February 6.
  • These steps are necessary before crews can begin to safely remove the blockage inside the pipe.
  • Removal of the rock and boulder obstruction will require a combination of manual work inside the pipe and the use of heavy equipment.

Water Quality Sampling Results

Grid of test results

Historical data indicate typical E. coli levels in the Potomac River can range from 10 to 5,000 MPN/100mL. Variability in E. coli results are common and are influenced by multiple factors, such as weather (rainfall/snow melt and associated runoff) and subwatershed activities and conditions, including aging sewer infrastructure and illicit discharges.

Latest News

Section of Potomac River in Cabin John, MD showing river and trees

Testing will continue through September 10 at six Maryland locations closest to January sewer collapse

DC Water is moving from daily Potomac River water quality testing to testing twice a week. The change is part of our continued response to the January Potomac Interceptor sewer collapse. Daily testing continued past the original July 31 end date and today will be the last day DC Water will test at the 10 current locations.

Map: Temporary southbound lane closure on Rock Creek and Potomac Parkway NW.

Starting on or about Aug. 7, 2026, weather permitting, drivers can expect a temporary lane closure southbound on Rock Creek and Potomac Parkway NW near the intersection of Virginia Avenue NW and F ...

Photo of inside Potomac Interceptor at Dulles showing newly lined tunnel

First of four emergency repairs on Potomac Interceptor finished

DC Water has finished the first of four emergency repair projects on the Potomac Interceptor sewer line. Crews completed work today to strengthen a 600-foot section of pipe at Dulles International Airport.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Latest Blog Post
Plastic bottles, cups and other floating debris on the surface of the Anacostia River before the Anacostia River Tunnel began operating.
Cleaner Waterways Start With Everyday Choices
Protecting our waterways starts with everyday actions and continues through critical infrastructure designed to keep pollution out of our rivers.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.