EMERGENCY WATER OUTAGE
Feb 07, 2026 | 11:00 PM

Emergency Water Outage
Feb 07, 2026 | 04:00 PM

Emergency Water Outage
Feb 07, 2026 | 03:00 PM

Tingey Street Lane Shift On or About January 5

January 06, 2015

(Washington, DC) – DC Water and its contractor, Corman Construction, will be completing road realignment work at the DC Clean Rivers Main Pumping Station Diversions Project site on Monday, January 5, 2015, weather permitting. This work will involve shifting traffic lanes on Tingey Street, SE. More specifically, the parking lane on the north side of Tingey Street between New Jersey Avenue, SE and 3rd Street, SE will be converted to a travel lane in order to maintain two-way traffic along this portion of the roadway.

“No-Parking” signs will be placed along the north side Tingey Street parking lane, and these signs will be in effect 7 days per week, 24 hours, beginning January 5. Parking in this portion of Tingey Street will be prohibited through the duration of the project (until summer 2017).

Immediately upon completion of the road realignment work, the contractor will also need to extend the construction staging fence on Tingey Street approximately 20 feet north. While pedestrian access on Tingey Street will be maintained, pedestrian traffic immediately surrounding the work area will be detoured, as needed.

Important Information
* The parking lane located in the north side of Tingey Street, SE between New Jersey Avenue, SE and 3rd Street, SE will be converted to a travel lane through the duration of this project. Parking on this portion of Tingey Street will be prohibited.
* Pedestrian access on Tingey Street will be maintained, but pedestrian traffic immediately surrounding the work area will be detoured, as needed.
* Delays within the vicinity of the project area are anticipated.
* There will be no work performed on Federal holidays.

Temporary traffic signs have been set up throughout the area to alert motorists and pedestrians to the upcoming lane shift. To keep everyone safe, motorists should stay alert and obey the posted speed limits when traveling through this area.

Project Details
The District of Columbia Water and Sewer Authority (DC Water) is implementing the DC Clean Rivers Project for the District’s combined sewer system which comprises a system of tunnels and diversion sewers for the capture of combined sewer overflows (CSOs) to Rock Creek and the Anacostia and Potomac Rivers for treatment at DC Water’s Blue Plains Advanced Wastewater Treatment Plant. The entire project will reduce CSOs annually by 96 percent throughout the system and by 98 percent for the Anacostia River alone.

###
About DC Water
DC Water, is an industry leading multi-jurisdictional regional utility that provides drinking water, wastewater collection and treatment to 600,000 residential, commercial and governmental customers in the District of Columbia, 17.8 million annual visitors and also collects and treats wastewater for 1.6 million customers in Montgomery and Prince George’s counties in Maryland and Fairfax and Loudoun counties in Virginia.

DC Water’s service area covers approximately 725 square miles and the utility operates the world’s largest advanced wastewater treatment plant with a capacity of 370 million gallons per day and a peak capacity of 1.076 billion gallons per day.

Please visit dcwater.com/cleanrivers for more information on the DC Clean Rivers Project.

Latest News

Trench boxes at construction site for new pit accessing Potomac Interceptor Upstream

DC Water and its contractors continue to make progress constructing new access points to the Potomac Interceptor, one upstream of the damaged section, and an additional entry downstream to divert more wastewater flow from the pipe. These access points will allow crews to install a bulkhead, blocking flow in the pipe upstream of the collapsed area, keeping the site as dry as possible so crews can safely remove an extensive rock dam currently blocking the pipe.

Photo of giant rock and boulder removed

DC Water is releasing new findings regarding the environmental impacts following the January 19, collapse in a section of the Potomac Interceptor. Based on flow monitoring data collected before and after interim bypass pumping was activated, DC Water estimates approximately 243 million gallons of wastewater has overflowed from the collapse site.

Image of rock blockage taken by CCTV inside the Potomac Interceptor downstream of the collapse

Update on Extended Repairs, Safety Measures, and Water Quality Monitoring

Overnight CCTV inspection of the Potomac Interceptor revealed the blockage inside the collapsed sewer line is far more significant, showing a large rock dam stretching approximately 30 feet downstream of the original failure.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.